  1. Slide 1: 2021 Denver Gold Forum

    For personal use only 2021 Denver Gold Forum High-grade Bellevue Gold Project in WA fully funded to first production

  2. Slide 2: Disclaimers & Compliance Statements

    Disclaimers & Compliance Statements This Presentation has been prepared by Bellevue Gold Limited (Company) and is authorised by the Managing Director of Bellevue Gold Limited. DISCLAIMER For personal use only This Presentation has been prepared by the Company based on information from its own and th

  3. Slide 3: Disclaimers & Compliance Statements - JORC

    Disclaimers & Compliance Statements JORC COMPLIANCE STATEMENTS For personal use only It is a requirement of the ASX Listing Rules that the reporting of ore reserves and mineral resources in Australia comply with the Joint Ore Reserves Committee’s Australasian Code for Reporting of Mineral Resources

  4. Slide 4: Investment Highlights

    Investment Highlights The recent A$106m underwritten placement and A$200m debt facility ensures Bellevue is fully funded to first production and on track to deliver the project in the June quarter of 2023, whilst continuing the exploration program For personal use only One of the highest-grade, lowe

  5. Slide 5: Dual track strategy delivering Value with the FS2 study

    Dual track strategy delivering Value with the FS2 study • Bellevue’s dual track strategy of exploration and a pathway to production continues to unlock value • In only 6 months FS2 has added A$701m, or a 65% increase in free cash flow and increased the IRR to 72% (pre-tax) For personal use only • Fu

  6. Slide 6: A Resource that continues to grow rapidly

    A Resource that continues to grow rapidly • Since the discovery hole in November 2017, the Resource has grown at a compound annual growth rate of 81% at a discovery For personal use only cost of A$18/oz BGL Resource Growth (koz) † BGL Resource per Share (oz/Msh) † † . 3,000 koz 2,410 koz 1,040 koz 3

  7. Slide 7: A deposit that continues to grow in every direction

    A deposit that continues to grow in every direction • Since the Tribune discovery hole in November 2017, the Resource has grown at a compound annual growth rate of 81% • The recent Lucknow discovery extends the strike to over 5km and the Lucien discovery sits 300m beneath the Deacon lode; For person

  8. Slide 8: FS2 vs FS1 – adding immediate value to the project

    FS2 vs FS1 – adding immediate value to the project Stage 2 Study delivers a significant improvement in all key project metrics, including production, life of mine, costs, free cash flow, profit and return metrics; all without a material change in capital costs For personal use only Key LOM Productio

  9. Slide 9: BGL joining an exclusive gold club

    BGL joining an exclusive gold club • There are only 7 other assets globally in Tier 1 jurisdictions, that produce over 180kozpa with a head grade over 5g/t • FS2 will see the project produce over 200kozpa for the first 5 years and a LOM average of 183kozpa for 8.1 years • Further Resource conversion

  10. Slide 10: BGL – FS2 delivers substantial production growth

    BGL – FS2 delivers substantial production growth • Updated Stage 2 Feasibility Study provides for a production increase of 21% over the life of the project • Significant increase to production demonstrated within six months of previous study, with significant cashflow generation from For personal us

  11. Slide 11: BGL – Forecast to deliver sector-leading financial returns

    BGL – Forecast to deliver sector-leading financial returns • BGL’s production is forecast to commence in FY23 and set to deliver sector-leading profitability compared to its ASX listed For personal use only peer group LTM EBITDA Margin vs BGL LOM EBITDA Margin % LTM AISC Margin vs BGL LOM AISC Margi

  12. Slide 12: BGL - Forecast to be Australia’s lowest greenhouse gas emitter/oz

    BGL - Forecast to be Australia’s lowest greenhouse gas emitter/oz • Bellevue is forecast to become the lowest emitter on a per ounce basis in Australia; the Stage 2 Feasibility Study shows a For personal use only forecasted greenhouse gas intensity of 0.202 t CO2e / oz. This has improved by ~30% due

  13. Slide 13: BGL – Forecast to become a Top Australian gold mine

    BGL – Forecast to become a Top 20 Australian gold mine • The updated Stage 2 Feasibility Study shows BGL is forecast to enter the Top 20 largest producing gold mines in Australia For personal use only • 21% uplift in LOM average production compared to the Stage 1 Feasibility Study released in Februa

  14. Slide 14: BGL – Forecast to enter the bottom quartile on AISC vs peers

    BGL – Forecast to enter the bottom quartile on AISC vs peers • The Stage 2 DFS positions BGL in the bottom cost quartile with a forecast LOM All In Sustaining Cost (AISC) of A$1,014/oz For personal use only • In the first 5 years of production the project will average an AISC of A$922/oz 2,104 2,034

  15. Slide 15: A$200M Fully Underwritten Credit Approved Project Finance

    A$200M Fully Underwritten Credit Approved Project Finance • Macquarie was Bellevue’s first institutional investor and has elected to take the majority of upfront fees in Bellevue shares For personal use only • Due to the forecast strong free cash flow generation Bellevue will be in the enviable posi

  16. Slide 16: Development & de-risking continues a rapidly growing Resource

    Development & de-risking continues a rapidly growing Resource • FS2 further de risks the project with 5 independent mining areas accessed prior to production. Deacon, Viago, Armand, Marceline and Tribune with the total A$1,502m of capital and operating costs incorporated into the A$1,014/oz AISC For

  17. Slide 17: Current Development timetable with targeted first gold production

    Current Development timetable with targeted first gold production June Q 20231 For personal use only 2021 2022 2023 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Existing Decline Rehabilitation Development Underground Exploration Access Project Approvals and Permitting Early Works Infrastruc

  18. Slide 18: Exploiting Our Competitive Advantages

    Exploiting Our Competitive Advantages One of Australia’s highest-grade gold mines, with exciting exploration potential and an accelerated development For personal use only timeline: “Real People, Real Profits, Real Growth” 3.0Moz 2.4 MozFCF A$1.8b + 10.0g/t at 9.9g/t 72% IRR GRADE & SCALE PROFITABIL

  19. Slide 19: Appendices

    For personal use only Appendices Click here for the 3D Inventum model

  20. Slide 20: Outstanding forecast EBITDA and free cash flow generation

    Outstanding forecast EBITDA and free cash flow generation The Bellevue mine design and project has been optimised on profitability and free cash flow and not grade and the For personal use only project generates an average LOM FCF/oz of A$1,405/oz (pre tax and post commissioning) Pre-tax and at a sp

  21. Slide 21: Sources and uses of funds

    Sources and uses of funds For personal use only Proceeds from the Offer, in conjunction with the A$200 million Macquarie loan facility, will be used to fund the development of the Bellevue Project Sources of funds A$m Uses of funds A$m Proceeds from Placement 106 Development and construction capital

  22. Slide 22: A Robust, Independent Feasibility Study

    A Robust, Independent Feasibility Study On the pathway to production Bellevue has engaged industry leading experts to assist and drive the Feasibility Studies For personal use only Studies, mine design, scheduling Non-processing infrastructure Process plant and infrastructure Geotechnical engineerin

  23. Slide 23: FS1 vs FS2 - What’s Changed?

    FS1 vs FS2 - What’s Changed? Key de-risking events achieved on the project since underground activities commenced Study Parameters FS1 FS2 Outcome For personal use only Mill Size 750 ktpa 1 Mtpa (and repriced) 33% Improvement  Decreased risk with additional Independent Mining Areas Three areas and

  24. Slide 24: Sources and Uses Of Funds from July 2021

    Sources and Uses Of Funds from Stage 1 July 2020 For personal use only FS2 FS1 and Stage 1 Work Completed from Sources of funds A$m Uses of funds A$m2 Development2 July 2020 Current Cash1 71 Mine development and construction capital3 252 255 Nil Proceeds from Underwritten Early works (A$20m), pre-de

  25. Slide 25: Fully Funded to Production

    Fully Funded to Production For personal use only Pre-Production Capital Expenditure (A$M) Site and Sustaining Capital 66 Processing Plant 82 Open Pit 14 Underground1 132 Capitalised operating costs 19 Capitalised revenue (61) Sub Total 252 Contingency2 15 Total 267 Variations to FS1 include optimisa

  26. Slide 26: Conventional Processing Facility – to deliver LOM recoveries of 96.7%

    Conventional Processing Facility – to deliver LOM recoveries of 96.7% For personal use only Processing Plant • Total LOM recoveries forecasted at 96.7% • Process plant designed to recover high gravity component at the front end. Test work indicates between 58% and 85% is recoverable through gravity

  27. Slide 27: Conventional mining methods

    Conventional mining methods For personal use only Sub Horizontal Lodes (13% LOM Ounces) • Areas with footwall dips < 45o utilise a modified cut and fill method with sub level stoping • Primary development is driven along strike of the ore zones, the ore is then stripped out (up to 4.2m) • The primar

  28. Slide 28: Project Operating Costs

    Project Operating Costs For personal use only Operating Costs A$M A$/T Milled A$/oz Produced Operating Costs (post-production) • Underground & Open Pit Mining – Rates supplied by UG & OP Mining 649 81.99 438 competitive Request for Quotation (RFQ) processes. Costs include recovery of ore and deliver

  29. Slide 29: BGL – Site Updated 3D Inventum video & Site Flyover Video

    BGL – Site Updated 3D Inventum video & Site Flyover Video For personal use only 3D Inventum Link Click Below Project Flyover Link Click Below https://inventum3d.com/c/BGL/Bellevue https://bellevuegold.wistia.com/medias/w9cw1f5wk2 29

  30. Slide 30: Corporate Summary

    Corporate Summary Building Strong Foundations For personal use only ASX Code Current Share Price (as at 30 August 2021) A$0.85 BGL ASX 300 (September 2019) Market Capitalisation ~ A$837M Shares on issue ~985m Cash1 ~ A$202m Management & consultant options & Hits up to 163g/t New high grade Stage 1 F

  31. Slide 31: Management Team with a proven track record

    Management Team with a proven track record For personal use only Daina Del Borrello Craig Jones Sam Brooks Luke Gleeson Maddison Cramer Rod Jacobs Amber Stanton GM People and Company Culture Chief Operating Officer Chief Geologist Head of Corporate Development Joint Company Secretary Project Directo

  32. Slide 32: Board of Directors

    Board of Directors For personal use only Kevin Tomlinson Steve Parsons Fiona Robertson Shannon Coates Michael Naylor Executive Independent Chairman Managing Director Non-Executive Independent Director Non-Executive Independent Director Executive Director Mr Tomlinson has over 30 years’ Mr Parsons is

  33. Slide 33: Tier 1 location in world-class gold belt

    Tier 1 location in world-class gold belt Bellevue has Major Landholding of Over 2,780km² For personal use only Excellent infrastructure: Historically significant producing region: • Services at Leinster, Leonora and Wiluna • Major gold deposits & producing gold mines in proximity to Bellevue’s Proje

  34. Slide 34: A$23-28m exploration budget: An organic pipeline of growth

    A$23-28m exploration budget: An organic pipeline of growth Bellevue discovery to resource growing at a compound annual growth rate of 81%. Armand Lode discovered August 2020, Marceline Lode discovered recently post the first Feasibility Study, multiple advanced targets ready for further For personal

  35. Slide 35: Bellevue’s economic contributions to society to grow with FS2

    Bellevue’s economic contributions to society to grow with FS2 • Since the ‘discovery hole’ in November 2017, Bellevue has injected over A$88m into the Australian economy For personal use only • During construction and operation, our Stage 1 Feasibility Study forecasts to generate A$2.3 billion into

  36. Slide 36: BGL’s approach to ESG = no greenwashing

    BGL’s approach to ESG = no greenwashing • Our Stage 1 Feasibility Study estimated that the gas power station would contribute 73% of the mine’s overall emissions For personal use only • The latest plans for the Bellevue power station will further reduce emissions, whilst maintaining reliability and

  37. Slide 37: ESG & the opportunity to be ‘best in class’ corporate citizens

    ESG & the opportunity to be ‘best in class’ corporate citizens BGL is evaluating all options on the pathway to development For personal use only - Smart blasting ✓ - Use of renewable electricity (eg. Climate consideration examples: - Energy efficient grinding ✓ solar, batteries) to power - Bushfires

  38. Slide 38: Bellevue is an industry leader in diversity

    Bellevue is an industry leader in diversity Bellevue has a Cultural Heritage Management Plan and a Diversity Policy For personal use only • Bellevue is leading the Australian mining sector for gender diversity and has a 0% gender pay-gap for like-for-like roles • Key metrics of our diversity results

  39. Slide 39: Why Bellevue?- Click Here

    Why Bellevue?- Click Here For personal use only 39

  40. Slide 40: Values and Vision

    Values and Vision “To create a standout gold mining and exploration company that is an industry benchmark” For personal use only At Bellevue we believe we have a unique opportunity to develop a standout gold mining company that is the benchmark for others to be measured against. We believe our four

  41. Slide 41: The sustainability pathway - a vision to be best in class

    The sustainability pathway - a vision to be best in class For personal use only Begin TCFD TCFD gap Develop climate Climate considerations analysis and risks and for new infrastructure, TCFD phase 3: phase 1: integrate identify Refresh TCFD staged action opportunities efficiency options and benchmar

  42. Slide 42: Bellevue’s leading commitment on efficient energy use

    Bellevue’s leading commitment on efficient energy use • The Bellevue Gold Project has been designed to optimize energy use and reduce environmental impact use only • Modeling places the project as of one of the most efficient gold mines, based on forecast energy use (GJ) per ounce produced • Since t

  43. Slide 43: Energy-emissions intensity – Bellevue is leading the way

    Energy-emissions intensity – Bellevue is leading the way • Energy-emissions intensity is the factor of emissions per unit of energy produced, such as tonnes of CO2e per GJ intensity (t CO e / GJ) use only • This trend shows that off-grid mines, powered by a gas-fired power station have a lower energ

  44. Slide 44: Scope 1 and Scope 2 emissions of Australian gold mines

    Scope 1 and Scope 2 emissions of Australian gold mines • The annual greenhouse gas emissions of Australian gold mines is plotted below personal use only • Due to the project’s low carbon emission intensity, Bellevue will have one of the lowest total greenhouse gas emissions per year of any Australia

  45. Slide 45: Bellevue’s community contributions and PACE values

    Bellevue’s community contributions and PACE values Our commitment to the Communities in which we operate is the ‘C’ in our PACE values For personal use only Bellevue is committed to supporting Aboriginal 2020 BELLEVUE GOLD people with pathways to employment. We offer trainees the opportunity to gain

  46. Slide 46: Processing Plant Overview

    Processing Plant Overview For personal use only 46

  47. Slide 47: Non Process Infrastructure

    Non Process Infrastructure For personal use only Infrastructure requirements • New office and facilities to support the mine activities • New 300-person camp located north of the project area with access from the Goldfields Highway • Potable water sourced, treated and distributed around the site (ha

  48. Slide 48: Project Finance Key Terms

    Project Finance Key Terms For personal use only Loan Facility Facility Amount A$200,000,000 (Fully Underwritten) Tenor 31 December 2027 (6 years) Repayment Period Quarterly, March 2024 - December 2027 Interest Rate 3.50% per annum pre-Project Completion and 3.00% per annum post Project Completion Ea

  49. Slide 49: Opportunities & Risks

    Opportunities & Risks For personal use only Opportunities Risks • Mill throughput increase to process lower grade stockpiles of mined • Gold price volatility and exchange rate risk material. Infrastructure design has allowed for readily expandable • Resource and Reserve estimates growth. • Risks as

  50. Slide 50: Mineral Resource and Ore Reserve Estimates

    Mineral Resource and Ore Reserve Estimates INDEPENDENT JORC 2012 RESOURCE AND RESERVE ESTIMATES FOR THE BELLEVUE GOLD PROJECT 3.5g/t gold lower cutoff, totals rounded to reflect acceptable position For personal use only Tonnes Grade Contained Ounces Mineral Resource (Mt) (g/t Au) (Moz) Indicated Min