Sylvania Platinum Ltd. · LSE:SLP

Sylvania Platinum — H1 FY2012 Earnings Presentation

19 slides from Sylvania Platinum's earnings presentation, March 2012

  1. Slide 1: Half year Results and Production update to March 2012

    Sylvania Platinum Half year Results and Production update to March 2012 www.sylvaniaplatinum.com

  2. Slide 2: Disclaimer

    Disclaimer Certain forward-looking statements may be contained in this presentation which include, without limitation, expectations regarding platinum prices, estimates of production, operating expenditure, capital expenditure and projections regarding the completion of capital projects as well as t

  3. Slide 3: Company Overview

    Company Overview • Domiciled in Bermuda • Listings – Primary:- Australian securities Exchange (ASX:SLP) o Delists end April 2012 – Secondary:- London’s AIM market (AIM:SLP) – Shares in issue: 301 251 805 • Market Capitalisation: GBP 60.25 million * • Shareholders # with > 4% of shares in issue (>50%

  4. Slide 4: Operational Highlights

    Operational Highlights Half year ended 31st Dec 2011 compared to (half year ended June 11) •PGM production increased 12% to 25,179 oz (22,483 oz) •Plant feed increased 4% to 779,653 tonnes (752,146 tonnes) •PGM Plant feed tonnes increased by 4% to 365,982 tonnes (353,411 tonnes) •PGM recoveries incr

  5. Slide 5: Consistent delivery

    Consistent delivery • Share performance in-line with peers • Impact of growth and good margins not appreciated by market Sylvania vs Peer Group (-12M) Sylvania 5

  6. Slide 6: Long Term Performance

    Long Term Performance SDO Profit Before Tax & Depreciation Sylvania Platinum Turnover 14 000 30 000 US$ ‐Thousands US$ ‐Thousands 12 000 25 000 10 000 20 000 8 000 15 000 6 000 10 000 4 000 2 000 5 000 ‐ ‐ June Dec June Dec June Dec June Dec June Dec June Dec June Dec June Dec June Dec June Dec 2007

  7. Slide 7: US$/oz cash costs at operation level & per plant

    US$/oz cash costs at operation level & per plant Represents average basket price Source: RBC Equity Research 7

  8. Slide 8: Sylvania assets in the Bushveld complex of South Africa

    Sylvania assets in the Bushveld complex of South Africa Northern All plants operated by Sylvania Dump Operations (SDO) limb section – 6 plants operational – 7th plant about to be constructed at Tweefontein. – Growth potential o Tweefontein MG2 Volspruit o UG 2 Dumps section Eastern limb dump operati

  9. Slide 9: Sylvania Dump Operations: ROM & Twin Plant at Mooinooi

    Sylvania Dump Operations: ROM & Twin Plant at Mooinooi 8: 8: Scrubbing Scrubbing and and Milling Milling Current Current Arisings Arisings Feed Feed 10: 10: Thickener Thickener Dump Feed Feed Dump 11: 11: Flotation Flotation 7: 7: Secondary Secondary Crushing Crushing 9: Chrome 9: Chrome Spiral Spir

  10. Slide 10: Q3 and Year End outlook

    Q3 and Year End outlook • Year end forecast now at 50 koz – Company continues to show a good growth trend – Forecast below planned target of 60 koz – Production growth from 2008 to 2012 remains good o Average growth per year of + 8 koz • Q3 production impacted by a number of unforeseen incidents – T

  11. Slide 11: Strong Mineral Resource

    Strong Mineral Resource – Life of mine planned ounces produced from Dump Material, Current Arisings & Run of Mine improved o 60 koz per year targeted for the next 10 years – Expansion of MG2 operations through synergy between host mine and Sylvania will extend mine life o Mooinooi project complete o

  12. Slide 12: Near Term Projects

    Near Term Projects Proposed Iron ore spin out •Iron ore asset to be spun out into a separate AIM listed company; Mercury Recycling Group plc •Shares to be distributed to existing shareholders as “in specie” dividend •Team in place and initial drilling complete Everest North •Detailed studies underwa

  13. Slide 13: Volspruit (Southern section of northern limb)

    Volspruit (Southern section of northern limb) • Extensive trials completed and project viability independently verified – Smelting trials produced metal alloy ready for refining – Refining trials have produced PGM rich metal powder and pure Nickel powder • Total project design well underway – PFS fo

  14. Slide 14: Volspruit & Northern Limb Project Development Strategy

    Volspruit & Northern Limb Project Development Strategy • Operating Strategy Mine – The Volspuit project becomes the model for future mines • Operations Overview – Open pit mine • Conventional drill and blast Pelletizer Crushing and Milling • Ore transported to concentrator plant Flotation – Processi

  15. Slide 15: Growth Potential Northern Limb Projects

    Growth Potential Northern Limb Projects SYLVANIA RESOURCES -12 000 E -11 000 E -10 000 E -90 00 E -80 00 E -70 00 E -60 00 E Hotspots at Aurora-Hacra •Harriets Wish -2598000 N The MSA Group Date: 29 March 2011N -2598000 0 250 500 750 1000 1250 1500 – Drilling to determine extent of new reef horizon

  16. Slide 16: Opportunities

    Opportunities • South Africa has a vast opportunity in the MG and LG horizons where symbiotic projects between chrome mining and platinum mining can be exploited. – Many mines have a planned operating life of +50 years • MG2 mining will extend mine life – Mooinooi plant is currently exploiting the M

  17. Slide 17: Sylvania Platinum upside potential

    Sylvania Platinum upside potential • Longer term production potentially anticipated to build up to > 225 koz per year 17

  18. Slide 18: Conclusion

    Conclusion • Dump process working well and profitable – Robust margins • Upside with expansion via MG, LG chrome and UG2 PGM dumps • SDO will achieve an approximate 25% growth year on year ~ 50 000 oz – SDO remains confident of ability to achieve 15 koz per quarter into the future • Proposed disposa

  19. Slide 19: Attractive company valuations

    Attractive company valuations Recent research reports 19