Image Resources Nl · ASX:IMA

Image Resources Nl — Shareholder Meeting (May 2024)

29 slides from Image Resources Nl's shareholder meeting presentation, May 28, 2024

  1. Slide 1: Chapter 2: Growth and Sustainability – Annual General Meeting

    Chapter 2: Growth and Sustainability Annual General Meeting of Shareholders 28 May 2024 Patrick Mutz Managing Director Image Resources NL ASX: IMA

  2. Slide 2: Disclaimer and Forward-Looking Statements

    Disclaimer and Forward-Looking Statements This presentation/document has been prepared by the management of Image Resources NL ("Image”, “IMA“, or “the Company”). The information presented includes an indicative outlook of the business activities of Image for the calendar year (CY) 2024 and beyond a

  3. Slide 3: Company Description

    Company Description  Producer and Supplier of Critical Minerals Concentrate  Titanium, Zirconium and Rare Earths Elements  Feedstocks for Pigments, Ceramics, Critical Metals, Electronics…  Mining and Processing in Australia  Successful Project Development  Transitioned from advanced explorer t

  4. Slide 4: Project Area Location Map

    Project Area Location Map me GERALDTO! époconon b .6600000mN .6400000mN Indian Ocean Indian Darwi Western Australia Brisbane

  5. Slide 5: Project Location – Initial Portfolio 2016

    Project Location – Initial Portfolio 2016 Initial Tenement Portfolio (2017) 1,232 km2 ATLAS - planned mining to commence FY2024 12 Project Areas; 100%-owned 29Mt Ore Reserves Ore Reserves (Dec 2022) 93Mt dry mining Mineral Resources 5.5 million tonnes 236Mt dredge mining Mineral Resources 9.2% THM 2

  6. Slide 6: Transition to Active Miner

    Transition to Active Miner  Active miner – Chapter 1  Simple business model: One mine, one product, one customer  2017 BFS plan; mine and process ore at Boonanarring then self-fund relocation of equipment and mine and process ore at Atlas (series operations)  Still working 2017 plan; completed o

  7. Slide 7: Chapter 1 – Active Miner

    Chapter 1 – Active Miner  Chapter 1 Projects; operated in series Project Million THM Slimes Oversize Zircon Rutile Leucoxene Ilmenite VHM Strip Ilmenite Tonnes % % % %* %* %* %* %* Ratio %TiO2 Boonanarring 15.8 8.0 15 4 28 2.5 2.0 47 80 7:1 55 (actual) Atlas 5.5 9.2 15 5 12 8 5 53 79 1:1 60 (Ore Re

  8. Slide 8: Project Location Map – Expanded Portfolio

    Project Location Map – Expanded Portfolio Eneabba Tenements Acquisition 232 km2 Initial Portfolio of Tenements 1,232 km2 McCalls Project Acquisition 224 km2 8

  9. Slide 9: Transitioning to Chapter 2

    Transitioning to Chapter 2  Strategic Acquisitions  Two acquisitions of mineral sands projects in Western Australia in 1H 2022 • Eneabba Tenements added ~200mt of Mineral Resources resulting in 3-fold increase in dry mining Mineral Resources portfolio • McCalls Project added 5.8 billion tonnes of

  10. Slide 10: Growth & Sustainability Strategy

    Growth & Sustainability Strategy  Chapter 2 Philosophy and Ambitions  Multiple mines, multiple products, global market + value-add • Develop multiple projects to be operated simultaneously • Separate HMC into multiple products (zircon, ilmenite, rutile, leucoxene, monazite etc.) for sale into glob

  11. Slide 11: Growth & Sustainability Strategy

    Growth & Sustainability Strategy  Chapter 2 Projects Project Million THM Slimes Oversize Zircon Rutile Leucoxene Ilmenite VHM Strip Ilmenite Tonnes % % % %* %* %* %* %* Ratio %TiO2 Bidaminna (Ore Reserves) 123 1.8 4 4 5 4.1 13 72 94 1:1 65 Yandanooka (Mineral Resources) 61 3.0 15 11 12 3.5 3.6 70 8

  12. Slide 12: Chapter 2 Projects and Value-Adding Steps

    Chapter 2 Projects and Value-Adding Steps  Diverse 100%-Owned Development Pipeline in Western Australia (JORC 2012)  Bidaminna – 123mt Ore Reserves1 at 1.8% HM (DFS underway) 10 yrs.*  Yandanooka2 – 30mt Ore Reserves1 at 3.9% HM (DFS underway) 8 yrs.**  McCalls2 – 3,610mt Mineral Resources1 at 1

  13. Slide 13: Synthetic Rutile Value Proposition

    Synthetic Rutile Value Proposition (CY2021-22 relative pricing) highest mass Convert ilmenite to synthetic rutile lowest price  Line graphs of mass contribution in HMC added  Bar graphs represent rough min and max for various Image projects commodity prices across CY2021-22 (for relative compariso

  14. Slide 14: Ilmenite Conversion to Synthetic Rutile (SR)

    Ilmenite Conversion to Synthetic Rutile (SR) Initial bench-scale test results – ASX announcement 9 August 2023 14

  15. Slide 15: SR Production Process Patent(s)

    SR Production Process Patent(s)  Initial ilmenite conversion testing conducted using fluidised bed reactor  New process formulated using different furnace with numerous advantages:  Accepts variable feedstock moisture content  Lower energy consumption  Substantially less material short-circuiti

  16. Slide 16: Preliminary, Conceptual Project Development Plan

    Preliminary, Conceptual Project Development Plan Cautionary statement: The following conceptual plan should only be read in conjunction with the Disclaimer and Forward-Looking Statements at the beginning of this presentation. The information provided in the following preliminary plan is conceptual a

  17. Slide 17: Chapter 1

    Preliminary, Conceptual Project Development Plan Chapter 1 • • One operation (at a time) One product (HMC concentrate) • One customer (offtake into China) • Limited project life 17

  18. Slide 18: Chapter 1 Chapter 2

    Preliminary, Conceptual Project Development Plan Chapter 1 Chapter 2 18

  19. Slide 19: Bidaminna Pre-Feasibility Study – June 2023

    Bidaminna Pre-Feasibility Study – June 2023 PFS Highlights: • Pre-tax NPV8: A$192 million • Pre-tax IRR8: 28% • Capital estimate: A$194 million • Capital payback (post first revenue): 3.8 years • EBITDA: A$379 million • Forecast mine-life: 10.5 years • Total Heavy Mineral Concentrate (“HMC”) product

  20. Slide 20: Yandanooka Pre-Feasibility Study – April 2024

    Yandanooka Pre-Feasibility Study – April 2024 PFS Highlights: • Pre-tax NPV8: A$151 million • Pre-tax IRR8: 72% • Capital estimate: A$50.3 million • Capital payback (post first revenue): 15 months • EBITDA: A$277 million • Forecast mine-life: 8.2 years • Total Heavy Mineral Concentrate (“HMC”) produ

  21. Slide 21: ESG & Sustainability

    ESG & Sustainability FOCUSED ON SUSTAINABILE PERFORMANCE 21

  22. Slide 22: Corporate Snapshot

    Corporate Snapshot Top Five Shareholders Board of Directors ASX Code IMA Murray Zircon PL 16.0% Bob Besley – Chair (Ind.) Share Price A$0.081 (24 May 2024) Vestpro International Limited 13.2% Patrick Mutz – Managing Director HSBC Custody Nominees 7.8% Aaron Chong Veoy Soo – NED (Ind.) Share on Issue

  23. Slide 23: For further information

    For further information Image Resources NL info@imageres.com.au Office: +61 8 9485 2410 Level 2, 7 Ventnor Avenue West Perth, WA 6005 PO Box 469, West Perth, WA 6872 www.imageres.com.au 23

  24. Slide 24: Mineral Resources and Ore Reserves Statement

    Mineral Resources and Ore Reserves Statement 24

  25. Slide 25: Mineral Resources and Ore Reserves Statement

    Mineral Resources and Ore Reserves Statement 25

  26. Slide 26: Mineral Resources and Ore Reserves Statement

    Mineral Resources and Ore Reserves Statement 26

  27. Slide 27: Mineral Resources and Ore Reserves Statement

    Mineral Resources and Ore Reserves Statement 27

  28. Slide 28: Mineral Resources and Ore Reserves Statement

    Mineral Resources and Ore Reserves Statement 28

  29. Slide 29: Mineral Resources and Ore Reserves Statement

    Mineral Resources and Ore Reserves Statement 29