Oroco Resources Corp. · TSXV:OCO

Oroco Resources — Oroco Resource — Investor Presentation (June 2012)

16 slides from Oroco Resources's investor presentation, June 2012

  1. Slide 1: Corporate Presentation June 2012

    JUNE 2012 2012年6月 TSX-V: OCO Frankfurt: OR6 US: ORRCF www.orocoresourcecorp.com

  2. Slide 2: Executive Summary

    EXECUTIVE SUMMARY執行摘要 Oroco Resource Corp. (TSX-V:OCO) is a Canadian-based mineral exploration company whose primary focus is the accelerated development of gold and silver production from the gold-bearing oxide zones of the Cerro Prieto Mine contained within the boundaries of our 7,000 ha of 100% o

  3. Slide 3: Directors and Management

    DIRECTORS and MANAGEMENT董事和管理層 Craig Dalziel, President, Director總裁,董事 Mr. Dalzial has over 30 years of financial, investment and administrative experience. As President of Ming Financial during the 1990’s he facilitating the re-opening and operation of the Rambler Mine and its 1,000 t.p.d. copper/g

  4. Slide 4: Directors and Management cont. / Contractors and Consultants

    DIRECTORS and MANAGEMENT cont.董事和管理層續 Steve Vanry, CFA, Director and Chief Financial Officer特許金融分析師,董事及首席財務官 Mr. Vanry's career includes over 20 years with public and private natural resource companies at both the management and board levels, concentrated in fund raising, mergers and acquisitions, r

  5. Slide 5: Project Locations

    PROJECT LOCATIONS!&€ 8 tis ¥ 4 CERRO PRIETO PROJECT % HERMOSILLO MEXICO CITY # XOCHIPALA PROJECT 4

  6. Slide 6: Cerro Prieto Project: Mining Concessions

    CERRO PRIETO PROJECT: MINING CONCESSIONS CERRO PRIETO項目:開採礦權區 • 7,000 ha land position containing 17.5 km strike length of mineralized structure • 7,000公頃土地面積,包含17.5公里長礦化結構走向 • 221 ha San Felix*, San Francisco* and Elba concessions, 100% owned • 221公頃的San Felix*、San Francisco*和Elba礦權 區,100%所有 • 2,50

  7. Slide 7: Cerro Prieto Project Highlights

    CERRO PRIETO PROJECT HIGHLIGHTS: CERRO PRIETO項目亮點: • Oxide Gold and Silver Resource: 390,000 ounces gold and 6,193,000 ounces silver, 98% in the Measured and Indicated resource confidence classification, with additional strike length of geological structure drilled in 2012 yet to be incorporated int

  8. Slide 8: Drill, Define, Mine: Critical Path to Mining at Cerro Prieto

    DRILL, DEFINE, MINE: CRITICAL PATH TO MINING AT CERRO PRIETO 鑽探、定義、採掘:開採CERRO PRIETO的關鍵途徑 April 2012 Entered into $19.75 million project financing arrangement ($15 million gold prepayment arrangement, $3.75 million convertible debenture, and a $1 million cost overrun facility) 2012年4月 達成1,975萬美元項目融資

  9. Slide 9: Preliminary Economic Assessment and Mine Plan

    PRELIMINARY ECONOMIC ASSESSMENT and MINE PLAN 初步經濟評估和礦山計劃 Gold Silver Undiscounted NPV at 5% IRR Payback Cash Flow discount period (oz) (oz) (millions) (millions) % (years) $1,000 $18.00 $45.75 $37.45 92 0.84 $1,200 $21.60 $70.44 $58.25 129 0.66 $1,350 $29.00 $89.54 $74.32 157 0.57 •Complete 3D UNDE

  10. Slide 10: NI 43-101 Compliant Resource

    NI 43-101 COMPLIANT RESOURCE* NI 43-101資源量* CATEGORY TONNES GOLD SILVER LEAD ZINC > Cut-Off (g/T) (g/T) (%) (%) MEASURED 3,740,000 1.10 15.82 0.19 0.52 INDICATED 11,000,000 0.71 11.82 0.38 1.14 TOTAL M&I 14,740,000 0.81 12.83 0.33 0.98 INFERRED 281,000 0.66 12.55 0.22 0.74 CONTAINED METAL RESOURCE*

  11. Slide 11: Cerro Prieto Project: Exploration Upside

    CERRO PRIETO PROJECT: EXPLORATION UPSIDE CERRO PRIETO項目:勘探潛力 • Deposit remains open on strike to the north and south as well as at depth • 礦床仍延走向朝南北方向並朝深處延伸 • Additional resource development targets identified by surface sampling and drilling • 通過地表取樣和鑽探劃定額外的資源開發靶區 • 500 meters of strike length dril

  12. Slide 12: Xochipala Project: Guerrero Gold Belt

    XOCHIPALA PROJECT: GUERRERO GOLD BELT XOCHIPALA項目: GUERRERO金礦帶 Oroco owns a 100% interest in the Xochipala Project, consisting of important and historical concessions contained within the original Morelos National Mining Reserve (more recently Locations of Ana Paula (Newstrike called the Guerrero Go

  13. Slide 13: Xochipala Project: Guerrero Gold Belt

    XOCHIPALA PROJECT: GUERRERO GOLD BELT XOCHIPALA項目: GUERRERO金礦帶 ANA APULA PROJECT: NEWSTRIKE CAPITAL: SIGNIFICANT NEW AU DISCOVERY ANA APULA項目:NEWSTRIKE CAPITAL:重要 新金礦發現 EL LIMON PROJECT: TOREX GOLD RESOURCES: + 4.84 MILLION OZ AU M&I EL LIMON項目:TOREX GOLD RESOURCES:探明和控制黃金資源量超過 484萬盎司 NUKAY and LOS

  14. Slide 14: Xochipala Project: Guerrero Gold Belt

    XOCHIPALA PROJECT: GUERRERO GOLD BELT XOCHIPALA項目: GUERRERO金礦帶 “The Xochipala claims cover ground in the Guerrero Gold Belt sufficient to potentially generate reserves greater than 1 million ounces gold in ore bodies similar to the productive high-grade ore bodies that have been discovered in the pa

  15. Slide 15: Capital Structure

    CAPITAL STRUCTURE資本結構 Common Shares Issued and Outstanding (June 1, 2012): 69,376,155 Share Purchase Warrants $0.30, Exp. Oct., 2012 1,000,000 $0.45, Exp. August 12, 2012 1,970,667 $0.42, Exp. October 26, 2012 2,125,000 $0.40, Exp. May 23, 2013 2,386,000 $0.40, Exp. Sept. 2013 2,935,000 Options $0.1

  16. Slide 16: Oroco Resource Corp. Contact and Disclaimer

    OROCO RESOURCE CORP. Suite 789-999 West Hastings Street Vancouver, BC V6C 2W2 Canada Phone 電話(604) 688-6200 Fax 傳真(604) 688-6260 info@orocoresourcecorp.com www.orocoresourcecorp.com TSX-V: OCO Frankfurt: OR6 US: ORRCF Date of update of this presentation: June 1, 2012 該演示文稿的更新日期:2012年6月1日 DISCLAIMER免