  1. Slide 1: Advancing Chile's Next Major Copper Mine

    TSX-V:LA Advancing Chile's Next Major Copper Mine 1 TSX-V:LA Corporate Presentation March 15, 2022

  2. Slide 2: Disclaimer

    TS-V:LA /2 Disclaimer Certain of the information and statements contained in this presentation constitute “forward-looking information” within the meaning of applicable securities laws. Forward-looking information is often, but not always, identified by the use of words such as: “believe”, “expect”,

  3. Slide 3: Located Along Chile's Most Prolific Copper Belt

    TSX-V:LA /3 Located Along Chile's Most Prolific Copper Belt Proven & Measured & Inferred Probable Indicated Project Reserves Resources Resources Cu lb billions Cu lb billions Cu lb billions Los Pelambres 15.0 39.2 28.6 Los Bronces 16.4 8.8 27.9 Rio Blanco-Andina 20.3 81.1 217.4 Costal Range Block El

  4. Slide 4: Los Andes Copper: World Class Copper 100% Owned

    TSX-V:LA /4 LOS ANDES COPPER World Class Copper 100% Owned Advancing Leverage Los Andes owns a Significant Leverage to 1 0 0 % interest in a Copper with 13 Billion World Class Copper Pounds CuEQ Measured Asset that is advancing and Indicated Resource NOW TOWARDS PFS RARE Expansion NO STRATEGIC Drill

  5. Slide 5: Copper Key to Chile - World Needs Chile Copper

    TSX-V:LA /5 Copper Key to Chile - World Needs Chile Copper 10% of GDP 30% of Copper has a Key World Cu Economic Place in Chile World Needs Chile copper New President Senate Royalty Increase – Balanced Reasonable Proposal Recently, Upgrade Senate is balanced 50/50 leading to broadly of Environment ne

  6. Slide 6: Copper: The Essential Metal for Electrification

    TSX-V:LA /6 COPPER: THE ESSENTIAL METAL FOR ELECTRIFICATION Electrification is coming Renewables need more copper Global shift to urbanization requires copper Copper is getting harder to find and develop

  7. Slide 7: Fundamentals of Los Andes Copper

    TSX-V:LA FUNDAMENTALS OF /7 LOS ANDES COPPER Tier 1 in the best copper belt Chile is a mining country 2019 P EA estimated an Large resource base with and one of the best mining competitive grade and after tax NPV (@8%) of US$ jurisdictions in the world clean mineralization 2.7 Billion at long term c

  8. Slide 8: Corporate Update

    TSX-V:LA /1 Corporate Update Strengthened the Board Corinne Boone – Non-executive Director and Board Major shareholders of Los Chair of the Environmental, Social, and Governance Committee Andes Copper Warren Gilman – Non-executive Director Plan to continue to enhance the executive management team Ot

  9. Slide 9: Vizcachitas in the Community

    TSX-V:LA /1 VIZCACHITAS IN THE COMMUNITY Organized and Together with the local chamber of Regular meetings participated in commerce, provided sanitary kits public forums to to the community during the with stakeholder discuss pandemic community to inform them of the environmental Working in the deve

  10. Slide 10: Solid Economics Supporting the Project

    SOLID ECONOMICS 2significantly TSX-V:LA /11 01 9 PEA economics upgraded (base SUPPORTING THE PROJECT case 1 1 0 ktpd mill) 26.7% US$2.7 billion $3.50/lb NPV @ 8 % (post tax) IRR US $4.6 billion NPV @ 5 % (post tax) Copper price 20.8% US$1.8 billion $3.00/lb NPV @ 8 % (post tax) IRR US $3.2 billion N

  11. Slide 11: Significant Work Undertaken Since 2019 PEA

    TSX-V:LA SIGNIFICANT WORK UNDERTAKEN SINCE /12 2019 PEA The 2 01 9 PEA provided a conceptual plan for developing an economic open pit operation at Vizcachitas: US$2.7bn NPV and 2 6 . 7 % I R R US$1.9bn initial capex PEA pricing assumption: Current Price: Copper US$3.5/lb US$4.2/lb Molybdenum US$22.0

  12. Slide 12: The PFS Plan: Update Project Economics

    TSX-V:LA /13 The PFS plan: Update project Economics Materially de-risk the operation technically Design Project incorporating leading environmental principles of sustainable mining Reduced Energy Costs Because of P FS optimizations in the flow of all materials going Freeing up Area downstream and fr

  13. Slide 13: PFS Engineering Changes

    PFS ENGINEERING TSX-V:LA /14 CHANGES Topic PEA 2019 2022E PFS Impact Lower energy consumption Processing SAG Mill HPGR circuit Enhanced project economics grinding circuit Operational flexibility Reduced water and energy consumption Tailings Facility Thickened Filtered dry- Reduced footprint and oper

  14. Slide 14: Capital Cost Estimate

    TSX-V:LA /16 Initial Sustaining 45 yr LOM Description 11 0 ktpd 11 0 ktpd Capital Direct Costs Diversion Rocin River 52,912 2,500 Cost Access 29,731 Concentrate Transport 29,932 Pipeline Rocin-Chalaco Estimate General Facilities 35,000 Operations Platform 35,145 Mine 277,465 1,025,196 Plant 439,016

  15. Slide 15: Leveraged Exposure to Copper

    TSX-V:LA /17 LEVERAGED EXPOSURE TO C OPP ER C1 Cash Costs – US$1.36 /lb average US$1.8 billion after-tax NPV (8%) at $3.0 /lb Copper US$2.7 billion after-tax NPV (8%) at $3.5 /lb Copper C1 cash cost for the first 8 years of NPV (kUS$) Sensitivity Analysis – production Copper Price Variation (After T

  16. Slide 16: Engineering Factors

    TSX-V:LA /18 Engineering Factors Protection of the Environment OPPORTUNITY TO DESIGN A CLEAN GREEN MINE Reduced Footprint Valley Location River Diversion Reduced Water and Energy Consumption

  17. Slide 17: Surrounded by Mining Majors

    TSX-V:LA /19 Surrounded by Mining Majors Vizcachitas Project 0 3 6 9 Km

  18. Slide 18: Further Upside in Vizcachitas' District

    TSX-V:LA /20 FURTHER UPSIDE IN VIZCACHITAS’ DISTRICT Vizcachitas has a substantial land holding (308 km2) of which only a small portion has been properly explored Geological mapping and geophysics have identified drill ready targets to north of current mineral resource

  19. Slide 19: Advancing Development of Vizcachitas: Milestones

    TSX-V:LA /29 A D V A N C I N G DEVELOPMENT O F VIZCACHITAS Milestones Immediate path to increase value recognition Potential Commencement of commercial ENVIROMENT operations PERMITS AND 2027 Completion of CONST. DFS FUNDING 2024- Completion of 2023-24 2025 PFS Construction Drilling Q2-2022 2025 - 20

  20. Slide 20: Contact

    TSX-V:LA LOS A N D E S COPPER /30 TSX-V: LA Contact R. Michael Jones, CEO BLYTHEWEIGH (Financial PR) rmj@losandescopper.com Tim Blythe tim.blythe@blytheweigh.com Harry Nijjar, CFO harry.nijjar@losandescopper.com Megan Ray megan.ray@blytheweigh.com Antony J. Amberg, Chief Geologist antony.amberg@losa

  21. Slide 21: Appendix

    LOS ANDES COPPER.

  22. Slide 22: Vizcachitas Mineral Resources

    /32 VIZCACHITAS MINERAL RESOURCES (effective d a t e 5 June 2019) Measured and Indicated Copper Resource of 1.28 billion tonnes at a copper grade of 0 . 4 0 % and a copper equivalent grade of 0 . 4 5 % Measured a n d indicated: Measured and Indicated Copper Resource increased 3 1 . 2 % 11.2 billion

  23. Slide 23: Copper Market

    COPPER MARKET /33 C o p p e r value chain – A widening market deficit is looming The widening market deficit in the copper sector will put further pressure on price Copper Supply and Demand (million tonnes) Source : Hannam Partners

  24. Slide 24: Copper outlook significantly impacted by battery demand

    The outlook for c o p p e r will b e significantly /34 i m p a c te d by battery d e m a n d EVs will drive a modest According to supply-demand deficit Hannam, an EV needs between 2021-2024, then c.80kgs of copper, this is c.4 from 2025 demand will times more than a Cumulative copper demand from ele