Carnaby Resources Ltd. · ASX:CNB

Carnaby Resources — Investor Presentation (March 2026)

22 slides from Carnaby Resources's investor presentation, March 2026

  1. Slide 1: An Afternoon with ORDS - Copper

    An Afternoon with ORDS - Copper Investor Presentation - March 2026 PHOTO OF EAST WALL OF TREKELANO OPEN PIT

  2. Slide 2: Statements and Disclaimers

    Statements and Disclaimers Competent Persons Statement The information in this document that relates to all exploration results is based upon information compiled by Mr Robert Watkins. Mr Watkins is a Director and shareholder of the Company and a Member of the AusIMM. Mr Watkins consents to the incl

  3. Slide 3: Corporate Overview

    Corporate Overview TARGETING TO BECOME AN AUSTRALIAN COPPER AND GOLD PRODUCER IN 2026 CORPORATE STRUCTURE1 BROKER COVERAGE Shares on Issue 276.1M Share Price $0.34 Unlisted Options 5.6M Greater Duchess MRE Update Market Cap $94M SHARE PRICE PERFORMANCE1 $12.5 Placement to QIC Critical Greater Duches

  4. Slide 4: Greater Duchess Copper Gold Project

    Greater Duchess Copper Gold Project Critical mass achieved to develop a new copper gold mine in 20261,2 1 Updated Mineral • 29.2Mt @ 1.5% CuEq for 440,500t CuEq Resource Estimate 2 Maiden • 8.4Mt @ 1.9% CuEq for 164,300t CuEq Ore Reserve 3 • 12 year production profile 9.3Mt @ 1.9% CuEq • 8 years tar

  5. Slide 5: Project Development

    Project Development Photo of Inheritance pit mined by Barrick 2006-2009

  6. Slide 6: PFS Highlights

    PFS Highlights LOW CAPEX START UP UTILISING EXISTING THIRD PARTY PROCESSING1,2 • 12 year Production Target processing 9.3Mt @ 1.9% CuEq for 164,000t CuEq • 8 years targeting ~17,000t CuEq recovered pa • Maximum negative cashflow inclusive of Pre-production Capex is $24M • Ores to be processed in Mou

  7. Slide 7: Feasibility Study & Development Critical Path

    Feasibility Study & Development Critical Path1 GREATER DUCHESS BECOMING SHOVEL READY • FS in progress and targeting mid CY2026 completion • Tenders for open pit mining and haulage being sought 6 Years Open Pit 6 Years Underground • FID targeted for mid CY2026 • Project Development team being assembl

  8. Slide 8: Open Pits

    Open Pits SIX YEAR OPEN PIT MINE LIFE JUST THE START1,2 • 6 years of open pit production from six open pits • Low CAPEX start up at Trekelano where three pits will be mined from a production target of 2.3Mt @ 1.7% CuEq for 41,000t CuEq • LOM Open pit production target of 4.8Mt @ 1.7% CuEq for 81,000

  9. Slide 9: Trekelano Open Pits

    Trekelano Open Pits1,2 • Open pit mining start up at Trekelano with three open pits to be developed • Open Pit Production Target of 2.3Mt @ 1.7% CuEq for 41,000t CuEq • Located on granted Mining Leases approved for mining with bonds in place. • Enormous potential for growth through recent exploratio

  10. Slide 10: Trekelano – Inheritance Open Pit Cutback

    Trekelano – Inheritance Open Pit Cutback1,2 • Historical open pit to ~140m depth • JORC 2012 Mineral Resource Estimate: 3.0Mt @ 1.5% CuEq , 46,500t CuEq (1.2% Cu, 0.4g/t Au) • Open Pit Production Target of; 1.4Mt @ 1.8% CuEq for 24,000t CuEq (1.5% Cu, 0.4g/t Au) • Unmined drill hits under the histor

  11. Slide 11: Trekelano - Trek 2 Open Pit cutback

    Trekelano - Trek 2 Open Pit cutback1,2 • Historical open pit to ~65m depth • Ore Reserve open pit using Indicated resources only (Dark Blue pit) • Pit optimisations using Inferred resource (Light Blue pit) completed prior to new drill results • Recent drilling to convert Inferred resources to Indica

  12. Slide 12: Lady Fanny And Burke & Wills Open Pits

    Lady Fanny And Burke & Wills Open Pits1,2 • Two new open pits to be developed • Production target of; 1.3Mt @ 1.7% CuEq for 22,000t CuEq • High grade sulphides from a few metres below surface • Open at depth and along strike Note 1: Refer to ASX releases dated 16 March 2026. Note 2: Refer to Slide 2

  13. Slide 13: Underground

    Underground NINE YEAR UNDERGROLUND MINE LIFE1,2 • Open pit mining transitions to Underground at Mount Hope Central and Nil Desperandum in Year 4 of the LOM schedule • LOM Underground Production Target of 4.5Mt @ 2.2% CuEq for 98,000t CuEq from Mount Hope Central and Nil Desperandum • Mount Hope Cent

  14. Slide 14: Exploration

    Exploration Photo of Trek 1 Extension Discovery Drilling September 2025

  15. Slide 15: Near Mine Exploration Upside

    Near Mine Exploration Upside1,2 • Carnaby has consolidated ownership of Greater Duchess Region and now owns 100% of its Mineral Resources; • Pipeline of advanced prospects to continue to deliver high grade discoveries • 440,500t CuEq contained @ 1.5% CuEq in the greater Duchess Mineral Resource Esti

  16. Slide 16: Trek 1 High Grade Extension

    Trek 1 High Grade Extension • JORC 2012 Mineral Resource Estimate: 1.5Mt @ 2.0% CuEq, 30,200t CuEq1,2 (1.7% Cu, 0.4g/t Au) • Trek 1 Underground mined continuously from 1911 to 1943 producing 188kt @ 10.9% Cu, 2.0g/t Au • 400m extension discovery, drill results include: • 7m @ 9.3% CuEq • 6m @ 7.1% C

  17. Slide 17: Mount Hope Near Mine

    Mount Hope Near Mine Exceptional Exploration Upside1,2 • Mount Hope Corridor • First drill hole September 2022 Jude • 11.2Mt @ 1.7% CuEq for 196,000t CuEq discovered to date • JV allowing corridor / ML boundary exploration to begin • Mohawk Corridor • VTEM survey in 2024 lit up the >4km mineralised

  18. Slide 18: Regional Exploration Upside

    Regional Exploration Upside New frontier at Magna Lynn Southern Corridor1,2 1 Initial discoveries led • Magna Lynn Basalt stratigraphic / structural to new corridor geological ideas 2 Historical • New target Iron Sulphide Copper Gold (ISCG) in Models missed magnetically quieter rocks. the mark 3 Min

  19. Slide 19: Investment Highlights

    Investment Highlights Mineral Resource Estimate 29.2Mt @ 1.5% CuEq for 440,500t CuEq1,2 Critical Mass Reached Ore Reserve Estimate 8.4Mt @ 1.9% CuEq for 164,300t CuEq1,2 • Binding Tolling and Offtake Agreements Processing Solution & with Glencore International AG. Development Pathway • FS and FID ta

  20. Slide 20: Office Contact

    Office Contact 78 Churchill Avenue P +61 8 6500 3236 SUBIACO WA 6008 E info@carnabyresources.com.au

  21. Slide 21: Appendix 1 - Mineral Resource Inventory

    Appendix 1 Carnaby Resources Limited Greater Duchess Copper Project - Cu Equivalent Cut-off Mineral Resource Inventory as at 27 January 2026 Indicated Inferred Total COG Deposit Tonnes Cu Au CuEq Cu Au CuEq Tonnes Cu Au CuEq Cu Au CuEq Tonnes Cu Au CuEq Cu Au CuEq CuEq% Mt % g/t % Tonnes Ounces Tonn

  22. Slide 22: Appendix 2 - Ore Reserve Estimate

    Appendix 2 Greater Duchess Copper Gold Project Ore Reserve Estimate as at 16 March 2026 Tonnes Cu Au CuEq Cu Au CuEq Category Asset Mt % g/t % kt koz kt Proved Open Pit - - - - - - - Proved Proved Underground - - - - - - - Proved Total - - - - - - - Inheritance 1.2 1.5 0.4 1.8 18.8 15.3 22.8 Trekela

Carnaby Resources — Investor Presentation (March 2026) on 6ix