    2 This Press Release contains forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995, Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934.These forward looking statements are based on our current expectations

  3. Slide 3: 2010 Highlights

    Slide 3: 2010 Highlights

    Reserve Growth of 119% (YE 2009 vs. YE 2008) 27.5 Mmbo Proved Oil in Corvina 10.0 Mmbo Proved Oil in Albacora Exploration Success at Albacora A-14XD online and testing with EWT through mid January 2011 Corvina’s Appraisal Continues/Reduced Drilling Costs BPZ Marine Receives Certification to the ISO

  4. Slide 4: Management team

    Slide 4: Management team

    Richard Spies, Chief Operating Officer Over 30 years experience in large scale projects with major oil and gas operators Amoco, Pan American Energy (a BP subsidiary), and BP Russia. Frederic Briens, Chief of Strategy and Technology Brings over 20 years experience in international projects with major

  5. Slide 5: Focus on Improving Operations

    Slide 5: Focus on Improving Operations

    5 Focus on Improving Operations

  6. Slide 6: New Technologies & World Class Contractors

    Slide 6: New Technologies & World Class Contractors

    Technologies FPSO–First in Peru Casing Drilling–First in Peru Annular Pressure While Drilling Compact Shuttle Logging Pipe Conveyed Logging Service Companies Schlumberger Weatherford Engineering & Construction Universal Pegasus Maintenance Wood Group 6 New Technologies & World Class Contractors

  7. Slide 7: Improving Drilling Costs

    Slide 7: Improving Drilling Costs

    7 Improving Drilling Costs 136 Days Days to Drill & Complete 77 Days $11.6M Drilling Costs $8.3M First 5 Corvina Wells Last 3 Corvina Wells $9.2M Completion Costs/Testing ***CX11-23D not included $3.2M in averages. $28.3M Total Well Costs $13.8M

  8. Slide 8: Developing Our First Two Oil Fields

    Slide 8: Developing Our First Two Oil Fields

    8 Developing Our First Two Oil Fields

  9. Slide 9: SEC Proved Oil Reserves—Corvina & Albacora

    Slide 9: SEC Proved Oil Reserves—Corvina & Albacora

    9 Mmbo Albacora Reserves Estimated by Netherland Sewell & Associates, LLP 11.9 Mmbo 17 Mmbo 37.5 Mmbo 0 5 10 15 20 25 30 35 40 YE 2007 YE 2008 YE 2009 Corvina SEC Proved Oil Reserves—Corvina & Albacora

  10. Slide 10: NSAI Estimated OOIP and Reserves

    Slide 10: NSAI Estimated OOIP and Reserves

    10 NSAI Estimated 2007, 2008, 2009 OOIP and Reserves YE 2009 Includes Albacora Mmbo 0 50 100 150 200 250 300 350 400 Potential Oil in Place 3P Reserves 2007 2008 2009 Potential Oil Reserves of 126.1 Mmbo

  11. Slide 11: Taking Corvina to Commercial Production

    Slide 11: Taking Corvina to Commercial Production

    11 Drilling the CX11-23D, the 10th well from the CX-11 platform Including the 23D, the CX-11 platform will have 8 oil wells, 1 dual oil/gas well, and 1 gas well Transition to commercial production by November 30, 2010 Compression equipment is in Peru; while processing equipment is already being inst

  12. Slide 12: Albacora Highlights

    Slide 12: Albacora Highlights

    12 Albacora Highlights Seven wells drilled to date (six by other operators). Four have produced oil - 14XD 8-X-2 discovery well tested oil, gas and non-associated rich gas A-14XD well under production test (began Dec 2009), granted six month EWT through mid January 2011 Only one set of sands being a

  13. Slide 13: Roadmap to 2012

    Slide 13: Roadmap to 2012

    Corvina Exit 2010 with commercial production in the 4,000-5,000 Bopd range Work-over some existing wells to optimize production Install new CX-15 platform by YE 2011 Albacora Drill A-18D with completion estimated in December, with six months of testing Exit 2010 with approximately 2,000-4,000 Bopd u

  14. Slide 14: ...And Our First Gas Field That Anchors the Gas Strategy

    Slide 14: ...And Our First Gas Field That Anchors the Gas Strategy

    14 ...And Our First Gas Field That Anchors the Gas Strategy

  15. Slide 15: Corvina Gas: Critical Milestone for Enterprise Value

    Slide 15: Corvina Gas: Critical Milestone for Enterprise Value

    Critical Milestone for BPZ Energy’s Enterprise Value Facilitates sale and booking of BPZ’s gas reserves Wells are already drilled and ready to produce Corvina gas Provides Operational Enhancements Reduces BPZ’s annual unit production costs ($/boe) Provides flexibility for associated gas (sale versus

  16. Slide 16: The Mancora Gas Play

    Slide 16: The Mancora Gas Play

    The Mancora Gas Play (MGP) starts in Block Z-1 and runs through Blocks XXIII and XIX Target is the Mancora Formation at varying depths from 3K to 12K feet Began 2D seismic---mapping 295 Km (July 2010) Planned 3D seismic--- mapping 366 Sq Km (4Q2010-1Q2011) 16 Gas MGP Resources (BCF) + East Corvina R

  17. Slide 17: Gas to Power—the anchor project

    Slide 17: Gas to Power—the anchor project

    Gas to Power—the anchor project Initial GtP demand 24 Mmcfd Government Sponsored Northern Gas P/L Gasifying Northern Peru Talara-Refinery Talara-Power Paita-Urea Bayovar-Phosphates Bayovar-Petrochem Trujillo-Power Chimbote-Steel Demand Expected to Grow Exponentially Prospective Resources in the MGP

  18. Slide 18: ... Building a Balanced Asset Base

    Slide 18: ... Building a Balanced Asset Base

    18 ... Building a Balanced Asset Base

  19. Slide 19: Searching for Oil Offshore and Onshore

    Slide 19: Searching for Oil Offshore and Onshore

    19 Block Z-1 3D Seismic in 2011 Delfin Step Out to 39-X-1 Mero Lead Leads A & B in 500’- 1,000’ Water Block XIX Pampa La Gallina prospect Oil in Heath Formation Three other mapped locations Block XXII Multiple Plays in Multiple Targets Adjacent to Existing Oil Fields 2D Seismic 4Q2010-1Q2011 Searchi

  20. Slide 20: Corporate Social Responsibility

    Slide 20: Corporate Social Responsibility

    20 Corporate Social Responsibility

  21. Slide 21: The Social Investment in Our Children

    Slide 21: The Social Investment in Our Children

    21 The Social Investment in Our Children

  22. Slide 22: Additional Information

    Slide 22: Additional Information

    Number of Shares: 115 Million Shares Outstanding 145 Million Shares Fully Diluted (includes Feb 2010 Convertible Notes due March 2015) Share Ownership: Management 15% Institutional Ownership 60% Largest Holders: International Finance Corporation Centennial Energy Partners Soros Fund Management SPO P

  23. Slide 23: Thank You

    Slide 23: Thank You

    Thank You a BPZ Resources, Inc. = Developing Energy - Providing Opportunities 23, | & 8 Fae

Source: SEC EDGAR · 8-K filed Aug 27, 2010