Anglo American Plc · LSE:AAL

Anglo American — Investor Day (December 2018)

47 slides from Anglo American's investor day presentation, Dec 11, 2018

  1. Slide 1: Investor Update

    INVESTOR UPDATE 11 December 2018 Copper – Quellaveco

  2. Slide 2: Cautionary Statement

    CAUTIONARY STATEMENT Disclaimer: This presentation has been prepared by Anglo American plc (“Anglo American”) and comprises the written materials/slides for a presentation concerning Anglo American. By attending this presentation and/or reviewing the slides you agree to be bound by the following con

  3. Slide 3: A Fundamentally Different Business vs 2012

    A FUNDAMENTALLY DIFFERENT BUSINESS VS 2012 Number of assets1 Portfolio: Focus on quality assets 47% Production Volumes2 Operations Delivery: Operating model ~10% Productivity1 Leadership & People: Efficiencies ~95% 3

  4. Slide 4: Our Asset Improvement Journey

    OUR ASSET IMPROVEMENT JOURNEY Group 2018 2013 Group 37th percentile 49th percentile Diamonds (De Beers) Copper PGMs Iron Ore Met Coal Thermal Coal Manganese Nickel Nickel & Manganese Margin curve position3 Q1 Q2 Q3 Q4 4 Source: Wood Mackenzie, CRU, De Beers internal analysis, Anglo American Platinum

  5. Slide 5: Our Leading Margin Improvement

    OUR LEADING MARGIN IMPROVEMENT Average margin curve position4 (%) 60 50 49% 12 p.p. 45% 45% 43% 40 39% 38% 37% 36% 36% 30 27% 0 Peer 1 Peer 2 Peer 3 Peer 4 Anglo 2013 2018 5 Source: Wood Mackenzie; AAP; De Beers; CRU

  6. Slide 6: Step Change in Performance and Sustainability

    STEP CHANGE IN PERFORMANCE AND SUSTAINABILITY P101 Exceeding industry best practice equipment performance Operating Model Stability and optimisation FutureSmart Mining Game-changing technology and data analytics Incremental improvement Step change 6

  7. Slide 7: Performance Update

    PERFORMANCE UPDATE Stephen Pearce De Beers – Jwaneng

  8. Slide 8: A World Class Copper Business

    A WORLD CLASS COPPER BUSINESS Portfolio strength ~1Mtpa Production ~120c/lb Future C1 unit cost (post Quellaveco) A transformed business ~660kt 2018 production guidance Q2 C1 unit cost: Lowest since 2010 with more to come… Continuing delivery ~640ktpa Average production 135-140c/lb 2019 C1 unit cost

  9. Slide 9: Continued Delivery of Improvements

    CONTINUED DELIVERY OF IMPROVEMENTS 2018 production5 2018 unit costs5 +2% -5% vs guidance, driven by Copper, PGMs & vs guidance Diamonds flat in 2019, improvements offset inflation 2019 production5 2020 production5 +3% +5% vs 2018 vs 2019 9

  10. Slide 10: Other 2018 Guidance

    OTHER 2018 GUIDANCE 2018 working capital build Corporate cash outflows Net interest ~$0.6bn ~$0.6bn ~$0.4bn in PGMs, Kumba & De Beers Treasury shares, FX translation & bond buybacks 2018 cost and volume Depreciation7 Tax rate7 improvement6,7 ~$0.4bn ~$2.8bn ~33% ~$0.2bn offset by oil/cost inflation

  11. Slide 11: Capital Allocation

    CAPITAL ALLOCATION Capital allocation framework8 Capital allocation 2016-20188 Based on H2 consensus • Attributable free cash flow of ~$10bn ~12 • Add back discretionary spend Cash flow Discretionary after capital sustaining options capital Balance sheet • Reduced net debt by ~$9bn flexibility to su

  12. Slide 12: Life Extensions Will Deliver Value; Higher Near-Term Sustaining Capex

    LIFE EXTENSIONS WILL DELIVER VALUE; HIGHER NEAR- TERM SUSTAINING CAPEX ~$2.8bn total capex, including $0.1bn growth 2018 2019-2021 pa Long term pa Total sustaining capex9 ~$2.7bn ~$3.2bn $2.8bn to $3.1bn SIB & Stripping9 ~$2.5bn ~$2.7bn Increase from previous guidance due to expanded portfolio e.g.

  13. Slide 13: Attractive High Returning Options Driving Growth

    ATTRACTIVE HIGH RETURNING OPTIONS DRIVING GROWTH CAPEX 2019 growth capex9 $0.6bn to $0.9bn driven by Quellaveco and technology projects Disciplined capital allocation framework drives project selection11 Anglo American share: Quellaveco (Copper) $2.5bn to $2.7bn12 +180ktpa from 2022 ~4 year payback

  14. Slide 14: Growth Optionality – Positioned for a Changing World

    GROWTH OPTIONALITY – POSITIONED FOR A CHANGING WORLD An Electrified A Greener A Richer World World World ~1Mt copper    ~37Mct diamonds (De Beers)  ~5Moz PGMs     Our high grade products suited to modern steel production ~70Mt high grade iron ore ~30Mt premium coking coal  ~30Mt export ther

  15. Slide 15: Continued Delivery of Improvements to Drive Margins Higher

    CONTINUED DELIVERY OF IMPROVEMENTS TO DRIVE MARGINS HIGHER Mining EBITDA margin13 (%) 5-10pp +5-10pp Margin13 uplift through $3-4bn of cost & volume improvement6 (2018-2022), including $0.5bn in 2019 46-50 +11pp • Operational Efficiency including P101 (1-5 years) 41 • Innovation and Technology (3-5

  16. Slide 16: Project Update

    PROJECT UPDATE Mark Cutifani Copper - Quellaveco

  17. Slide 17: Minas-Rio Restart on Schedule

    MINAS-RIO RESTART ON SCHEDULE  • Clean-up work complete  • Pipeline scan complete  • Results verified by two independent expert teams  • 4km of pipeline replaced as a precaution  • One of three required approvals for start up received  Restored area post pipeline spill • Additional monitoring

  18. Slide 18: Quellaveco on Track

    QUELLAVECO ON TRACK Construction Contracts and Procurement Engineering and Workforce • Asana River diversion complete • All awards on track: • Advanced engineering progress: ~60% contracted; ~60% complete • Earthworks and concrete ~50% procurement complete meaningfully progressed • ~6,000 workers on

  19. Slide 19: Building on Firm Foundations

    BUILDING ON FIRM FOUNDATIONS Mark Cutifani Copper - Los Bronces

  20. Slide 20: Leading Returns for the Long Term

    LEADING RETURNS FOR THE LONG TERM H1 2018 Long term ROCE17 19% 20%+ Asset life18 30 yrs 30 yrs 20

  21. Slide 21: Sustainability at the Heart of Our Business

    SUSTAINABILITY AT THE HEART OF OUR BUSINESS Trusted corporate leader Thriving communities OPERATIONAL FEWER ACCESS TO $ EFFICIENCY SURPRISES RESOURCES GROWING RETURNS Improved Positioned as Additional Healthy productivity and development partner opportunities environment resource efficiency More con

  22. Slide 22: Investment Proposition

    INVESTMENT PROPOSITION “Leading capabilities actively improving a world-class asset base to drive sustainable, competitive returns” Assets Capabilities Returns Focus on quality Operating Model Capital discipline Long life Innovation & Sustainability leader Dividend payout ratio Low-cost growth optio

  23. Slide 23: Footnotes

    FOOTNOTES 1. 2012-2018 estimate. Includes benefits of portfolio upgrading. 9. Cash expenditure on property, plant and equipment including related 2. 2012-2018 estimate. Copper equivalent is calculated using long-term consensus derivatives, net of proceeds from disposal of property, plant and equipme

  24. Slide 24: Appendix

    APPENDIX De Beers - Forevermark

  25. Slide 25: Safety, Health & Environment

    SAFETY, HEALTH & ENVIRONMENT Safety Health Environment Group TRCFR Fatalities Occupational health – new cases Major incidents (Level 3-4) 15 203 30 4.98 173 11 155 4.14 9 108 15 6 6 96 5.49 5 74 3.78 3.46 6 5 2.63 4 2 2013 2014 2015 2016 2017 YTD 2013 2014 2015 2016 2017 YTD 2013 2014 2015 2016 2017

  26. Slide 26: Production Outlook

    PRODUCTION OUTLOOK Units 2017 2018F 2019F 2020F 2021F (new guidance) Diamonds1 Mct 33.5 35-36 31-33 33-35 35-37 (previously 34-36) (previously ~32) (previously ~32) Copper2 Kt 579 ~660 ~630-660 ~620-680 ~590-650 (previously 630-660) (previously 600-660) (previously 600-660) Platinum3 Moz 2.4 2.45-2.

  27. Slide 27: 2018 Unit Costs Guidance Beat; Improvement Offsets Inflation in 2019

    2018 UNIT COSTS GUIDANCE BEAT; IMPROVEMENT OFFSETS INFLATION IN 2019 De Beers (US$/ct)1 Copper (C1 USc/lb) PGMs (US$/Pt oz)2 Kumba (FOB US$/t) 63 ~65 ~65 147 ~140 135-140 1,443 ~1,550 <1,600 31 ~35 ~35 2017 2018F 2019F 2017 2018F 2019F 2017 2018F 2019F 2017 2018F 2019F Minas-Rio (FOB US$/t)3 Met Coa

  28. Slide 28: New Accounting Standard for Leases

    NEW ACCOUNTING STANDARD FOR LEASES • Leases mainly corporate offices and jewellery stores; very limited mining equipment • Previously accounted for ‘off-balance sheet’ with lease costs taken to P&L New accounting from 2019 • Lease commitments brought onto the balance sheet, increasing net debt by: ~

  29. Slide 29: Operating Model, Technology and Innovation

    OPERATING MODEL, TECHNOLOGY AND INNOVATION

  30. Slide 30: Anglo American Operating Model: A Differentiated Approach

    ANGLO AMERICAN OPERATING MODEL: A DIFFERENTIATED APPROACH Apply a manufacturing approach to Work that is planned, scheduled and mining, through organised and efficient properly resourced is safer and delivers planning and execution of work consistently and at a lower cost Further improvements implem

  31. Slide 31: Innovation Is Needed to Ensure Sustainability

    INNOVATION IS NEEDED TO ENSURE SUSTAINABILITY Then Now Future state 1900 2018 What is required to produce 40kg of copper 24t waste 6m3 water 1t waste 3m3 water 1t ore 10 KWhr 8t ore 160 KWhr 40kg 4% Cu 0.02 Km2 0.5% Cu 100 Km2 31

  32. Slide 32: P101: Focused on the Key Value Drivers

    P101: FOCUSED ON THE KEY VALUE DRIVERS Mine Plant Drill Blast Load & haul Crush Mill Float & filter Percentage of 2018F direct cost base, Los Bronces = c.5% cost base >45Mtpa +10% > 94% > 89% Shovel Throughput Operating time Recoveries performance increase 32

  33. Slide 33: A Number of Game Changing Technologies

    A NUMBER OF GAME CHANGING TECHNOLOGIES >50% Reduction in water intensity Coarse Particle Recovery Dry Disposal >50% Reduction in energy intensity Advanced Shock-break Precision Classify Fragmentation 33

  34. Slide 34: Coarse Particle Recovery: Improved Recoveries

    COARSE PARTICLE RECOVERY: IMPROVED RECOVERIES Drill Blast Load & haul Crush Mill Float & filter • Flotation process changed to allow for larger diameter material Technology • Ore is liberated and recovered at a higher grade • Significant increase in throughput Benefits • Solidified disposal material

  35. Slide 35: Coarse Particle Recovery: In Copper

    COARSE PARTICLE RECOVERY: IN COPPER Drill Blast Load & haul Crush Mill Float & filter >10% >20% Increase in Operating Decrease in water and Free Cash Flow energy intensity 35

  36. Slide 36: Bulk Sorting: Less Waste to Concentrator

    BULK SORTING: LESS WASTE TO CONCENTRATOR Drill Blast Load & haul Crush Mill Float & filter • Uses sensors to determine ore content prior to processing Technology • Gangue is removed using natural heterogeneity of ore bodies • Provides immediate grade assays • Unlocks production capacity by rejecting

  37. Slide 37: Bulk Sorting: In Copper

    BULK SORTING: IN COPPER Drill Blast Load & haul Crush Mill Float & filter >10% Decrease in water and energy intensity 37

  38. Slide 38: Copper Site Visit

    AngloAmerican COPPER SITE VISIT Lg

  39. Slide 39: A Uniquely Positioned Copper Business

    A UNIQUELY POSITIONED COPPER BUSINESS A step change in volumes… …an improved cost position Copper production (kt) (13) C1 unit costs (c/lb) 1,400 1,200 1,000 800 2014 2018F 600 2025 400 200 0 2020 2025 2030 2035 Q1 Q2 Q3 Q4 El Soldado Quellaveco Los Bronces Sakatti Collahuasi 39

  40. Slide 40: World Class Assets

    WORLD CLASS ASSETS Los Bronces Collahuasi 52mt Contained Copper Resources(5) 3rd Largest endowment in the world • 2018 forecast production: ~365kt • 48mt of contained copper in Exclusive Mineral Resources and • Significant future growth optionality 30mt in ore reserves(5) • Contained copper in miner

  41. Slide 41: Quellaveco – A World Class Copper Project

    QUELLAVECO – A WORLD CLASS COPPER PROJECT Attractive returns Focus on execution Successfully syndicated Low cost with significant Strong local support and all Extending a long-standing potential key permits in place relationship, confirms asset’s value IRR Payback Consideration > 15% 4 years $600m R

  42. Slide 42: Quellaveco Financial Modelling

    QUELLAVECO FINANCIAL MODELLING Ownership Anglo American 60%, Mitsubishi 40% Accounting treatment Fully consolidated with a 40% minority interest. Shareholder loans from minority shareholder to be consolidated in Anglo American Group net debt. Project capex (nominal) $5.0-5.3 billion (100% basis - An

  43. Slide 43: Quellaveco Accounting

    QUELLAVECO ACCOUNTING • Anglo American consolidates 100% of Quellaveco’s P&L and Balance Sheet • Mitsubishi’s 40% share is shown as a non-controlling interest • After the initial $0.8bn equity injection by Mitsubishi, the project will be funded 60:40 through shareholder debt • Group net debt by the

  44. Slide 44: Los Bronces – Significant Growth Optionality

    LOS BRONCES – SIGNIFICANT GROWTH OPTIONALITY Current state Growth options Future state Production (2018F) • Abundant high grade ore Production Los Bronces ~365 ktpa Underground • Mine life extension to 2065 400-500ktpa • Permit submission in Q1 2019 C1 Cost (2018F) • Reduced mine interference C1 Cos

  45. Slide 45: Collahuasi – Plant Expansion Options

    COLLAHUASI – PLANT EXPANSION OPTIONS Number of expansion options available • 170ktpd 1,100 Copper production (kt) (100%) Existing licence allows throughput of up to 170ktpd, from existing levels of 155-160ktpd prior to 2020 1,000 900 • 210ktpd 800 Investigating options to expand concentrator through

  46. Slide 46: Longer-Term Growth Options

    LONGER-TERM GROWTH OPTIONS Sakatti Los Bronces District • Located in Finnish Lapland, in an established • Located adjacent to proven production assets mining district, close to infrastructure • Synergies with existing infrastructure • Smaller high grade ore body • Attractive mineralisation • Pre-fea

  47. Slide 47: Investor Relations

    INVESTOR RELATIONS Paul Galloway paul.galloway@angloamerican.com Tel: +44 (0)20 7968 8718 Robert Greenberg robert.greenberg@angloamerican.com Tel: +44 (0)20 7968 2124