Lomiko Metals Inc.

Lomiko Metals — Investor Presentation (July 2023)

40 slides from Lomiko Metals's investor presentation, July 2023

  1. Slide 1: Developing a strategic stockpile of critical mineral graphite and lithium properties

    Developing a strategic stockpile of critical mineral graphite and lithium properties in Quebec for a North American climate success story July 2023

  2. Slide 2: Disclaimer

    DISCLAIMER This presentation is not a prospectus, offering memorandum or an advertisement and is being provided for information purposes only and does not constitute or form part of, and should not be construed as, an offer or invitation to sell or any solicitation of any offer to purchase or subscr

  3. Slide 3: Land Acknowledgement

    Land Acknowledgement We would like to begin by acknowledging that the land/projects where we operate are located within the traditional land of the Algonquin Anishnaabeg and Cree Eeyou Istchee Peoples. Our vision is to embrace Indigenous people and Indigenous values within our projects to develop a

  4. Slide 4: A people-first critical minerals operator of choice in Quebec

    A people-first critical minerals operator of choice in Quebec Strategic Stockpile of Graphite ✓ 3.0mt of in situ Indicated Scale Opportunity in graphite and 0.7mt of Inferred Lithium at La Loutre - PEA stage and Leading with ✓ Earning 49% moving to PFS Vision and Values ownership in Bourier ✓ Except

  5. Slide 5: Lithium exploration on massive claim package on Nemaska lithium corridor

    Lithium exploration on massive claim package on Nemaska lithium corridor Bourier Property 5

  6. Slide 6: Most prospective graphite belt in North America

    Most prospective graphite belt in North America La Loutre and Laurentides claims • Completed 1,518-line kilometers of heliborne geophysical surveys completed over the six Grenville graphite properties, with 55 targets identified • 268 claims in total on 6 early-stage projects covering 15,639 hectare

  7. Slide 7: 97 graphite mines needed to fuel the EV revolution

    97 graphite mines needed to fuel the EV revolution How many mines do we need? • Benchmark forecasts how many mines need to be built in the short time frame to keep up with exceptional volumes of demand needed for key raw materials expected by 2035 • La Loutre is positioning itself for success as a r

  8. Slide 8: $400bn global investment in Li-ion battery value chain

    $400bn global investment in Li-ion battery value chain How many mines do we need? • Benchmark forecasts how many mines need to be built in the short time frame to keep up with exceptional volumes of demand needed for key raw materials expected by 2035 • La Loutre is positioning itself for success as

  9. Slide 9: Graphite shortfall starting in 2023, shortfall to increase to 8Mt by 2040

    Graphite shortfall starting in 2023 Shortfall to increase to 8Mt by 2040 Projected Anode Demand (Mt) Graphite Market Balance - Projected Demand and Supply (Mt) 12,000,000 9,000,000 8,000,000 DEMAND IS EXPECTED TO 10,000,000 EXCEED SUPPLY BY 2023 – 7,000,000 AND CONTINUE BEYOND 6,000,000 8,000,000 La

  10. Slide 10: Battery metals catalysts in 2023

    Battery metals catalysts in 2023 Canada and US Canadian critical minerals are considered domestic in US US IRA (Inflation Reduction Act): 80% of all raw materials produced or recycled in North America New demand The world's top automakers are planning to spend nearly US$1.2 trillion through 2030 - 2

  11. Slide 11: Lomiko can provide 10% of North American graphite

    Lomiko can provide 10% of North American graphite A massive increase in battery plant capacity - most to start production from 2025-2030 • A wave of new planned electric vehicle battery plants will increase North America’s battery manufacturing capacity from 55 GWh/year in 2021 to nearly 1,000 GWh/y

  12. Slide 12: EVs powered by batteries with La Loutre graphite = 315,000 EVs every year

    EVs powered by batteries with La Loutre graphite = 315,000 EVs every year Benchmark of avoided emissions (kt CO2e/year) Mine 100,000 tonnes per year of 616 natural graphite starting in 2027 Replacing ~150,000 ICE vehicles reduces carbon emissions equal to shutting down one natural gas power plant ~1

  13. Slide 13: La Loutre carbon intensity 10X better than current graphite producers

    La Loutre carbon intensity 10X better than current graphite producers ESTIMATE Lomiko Scope 1 and 2 intensity benchmarked to other graphite miners (Kt CO2e/ 100,000 t graphite) 200 200 Benchmarking 188 against graphite China currently accounts mining peers is 150 for over 70% of graphite mining and

  14. Slide 14: www.lomiko.com TSXV: LMR OTC: LMRMF FRANKFURT: DH8C

    www.lomiko.com TSXV: LMR OTC: LMRMF FRANKFURT: DH8C 14

  15. Slide 15: Environmental and water studies completed

    Environmental and water studies completed Studies completed ✓ Completed 13,000m+ of drilling at La Loutre with exceptional results ✓ Completed NI-43-101 mineral Resource for La Loutre ✓ Completed 12 months of environmental baseline studies ✓ Completed pre-feasibility metallurgical test program – opt

  16. Slide 16: La Loutre graphite project close to infrastructure with great geological setting

    La Loutre graphite project close to infrastructure with great geological setting • Preliminary Economic Assessment ("PEA") - 2021 • Completed updated NI-43-101 resource April 2023 • Completed PFS level Metallurgical testing February La Loutre Graphite Project 2023 • Completed Spherical graphite test

  17. Slide 17: La Loutre: PEA establishes a critical path ahead for improvements and de-risking

    La Loutre: PEA establishes a critical path ahead for improvements and project de-risking PEA details Carmin Zone • Two known deposits currently being explored: EV Zone and Battery Zone • LOM plant production of 21.8 Mtonnes of mill feed at EV Zone 6.78% Cg diluted Battery Zone • Graphite concentrate

  18. Slide 18: La Loutre: Carmin Acquisition

    La Loutre: Carmin Acquisition Carmin Carmin Acquisition – historic PFS Zone A The original historical estimate contemplated certain assumptions where the mineral resources are stated as Proven and Probable resources for Sites A and B. • Site A: total 1.55 Mt at 10.0% Cg Proven: 1.47 Mt at 10.29% Cg

  19. Slide 19: La Loutre: PEA Layout – great base to build on

    La Loutre: PEA Layout – great base to build on Mine layout and costs – PEA • Waste rock and tailings co-disposed • Efficient site water management with WASTE ROCK & no wet tailings EV ZONE CODISPOSAL PILE • Pits sequenced to maximize the returns starting from North – EV Pits to South – Battery Pits

  20. Slide 20: La Loutre EV Zone plan view

    La Loutre EV Zone plan view • Completed 53 drill holes or 9,025 meters Section 1-1 • South-east and north-east end of the EV Zone remain open to the south and east Section 2-2 20

  21. Slide 21: La Loutre Battery Zone plan view

    La Loutre Battery Zone plan view • Completed 26 holes in Battery South for a total Section 1-1 of 4,076 m • Open on the South End Section 2-2 21

  22. Slide 22: La Loutre Updated Resource Estimate: 184% Increase in Indicated Tonnage

    La Loutre Update Resource Estimate: Achieving 184% Increase in Tonnage in the Indicated Mineral Resources La Loutre Resource Estimate (Effective Date: March 31, 2023) - PFS Source: InnovExplo March 2023 2023 MRE 2021 MRE Deposit EV Battery TOTAL EV Battery TOTAL Cut-off (%) Cg 1.5 1.5 1.5 1.5 1.5 1.

  23. Slide 23: La Loutre Graphite – PFS level testing size distribution

    La Loutre Graphite – PFS level testing size distribution Graphite usage is dependent on the flake size • Developed and optimized PFS level flotation plant flowsheet -LCT testing achieved 94.7% recovery and 98.6% Cg grade! • Reconciled grades for LCT testing equal to 99.1%Cg! • Bigger flakes includin

  24. Slide 24: La Loutre metallurgical program – 99.99% purified graphite in SPG & next steps

    La Loutre metallurgical program – 99.99% purified graphite content in LL SPG & next steps ✓ Completed PFS level met testing and optimized flow sheet Completed value-added testing with ProGraphite –micronization, spheroidization and purification: ✓ Proved that La Loutre material is suitable for Spher

  25. Slide 25: La Loutre 2023 catalysts subject to financing

    La Loutre 2023 catalysts subject to financing +7-8 months from securing financing Q3/Q4 2023 Q2/Q3 2023 Pre-feasibility Battery Study Q1/Q2 2023 Concentrate Trials to anode Feb 2022 MRE & tests and Updated SPG Technical creation Report NI- purification Metallurgical 43-101 testing and flotation test

  26. Slide 26: Corporate budget requirements for La Loutre

    Corporate budget requirements for La Loutre The regional exploration program and Bourier work is being funded with Canadian Flow-Through financing PLANNED COMPLETED To PFS for La Loutre Cost ($M) Phase 1 at La Loutre Cost ($M) Mining Plan $0.3 Resource Drilling $3.5 Mining Geotechnical $0.9 Resource

  27. Slide 27: Lomiko advantage: Concentrate grade and NPV/Capex multiple

    Lomiko advantage: Concentrate grade and NPV/Capex multiple • Updating the Lomiko PEA for USD $1,500/t target graphite selling price • The La Loutre project combines high-grade concentrate with compelling economics of a post-tax IRR of 43%, post-tax NPV of $520M, and an NPV/Capex multiple of 2.2x Pro

  28. Slide 28: Lomiko advantage: High quality project with low capital requirements

    Lomiko advantage: High quality project with low capital requirements combined with high-grade graphite concentrate Project Location Africa/Europe North America Source: Company filings 28

  29. Slide 29: PEA: La Loutre delivers 97.4kt/year over a 15-year mine life

    PEA: The La Loutre project delivers 97.4kt/year over a 15-year mine life – PEA only, expansion possible Lomiko – La Loutre Operating Graphite Mines Source: Company filings 29

  30. Slide 30: La Loutre long term development timeline

    La Loutre long term development timeline Q4 2027 Q1/Q2 2023 Production MRE –NI-43-101 Q1 2024 Q4 2024 Mineral Resource PFS – Pre- Estimate Feasibility Study Q1/Q2 2025 Centre of Excellence FS – Feasibility Q3/Q4 2025 Pilot Plant Study Permits & Q2 2026 of Construction Construction Centre of Decision

  31. Slide 31: Lithium exploration on massive claim package on Nemaska lithium corridor

    Lithium exploration on massive claim package on Nemaska lithium corridor Bourier • Option to earn in 70% with Critical Elements, first trigger: 49% • 203 claims for a total ground position of 10,252.20 hectares (102 km2) that boasts other lithium deposits and known lithium mineralization • Bourier c

  32. Slide 32: Bourier lithium project: highly prospective region

    Bourier lithium project: highly prospective region Bourier Adjacent Properties: ⮚ Galaxy Resources ⮚ Nemaska Lithium ⮚ Critical Elements 1. Rose Tantalum Project FS stage 2. Lemare Property: ▪ New Discovery – March 21m @ 2.65% Li2O 41.5m @ 1.71% Li2O 23m @ 1.61% Li2O CELC is starting drilling campai

  33. Slide 33: Bourier lithium project

    Bourier lithium project Bourier 2021 Field Work Summary ▪ The analytical results feature high- grade values for zinc and tungsten and anomalies in lithium-tantalum- cesium and gold ▪ The lithium-tantalum-cesium anomalies represent an unprecedented discovery and spans along a 2.5 km long NE- trending

  34. Slide 34: Bourier lithium project identifies exploration targets with Li anomalies

    Bourier lithium project identifies exploration targets with Li anomalies 2021 Exploration Results Bourier Exploration Program 2022 -2023 ▪ Completed field program in July with Critical Elements and GoldSpot AI ▪ Collected over 1000 soil samples and over 400 rock samples, mapped over 350 outcrops ▪ F

  35. Slide 35: Capital Structure

    Capital Structure As at July 11, 2023 Shares Issued & Outstanding 351.1M Market Cap $10.5M Options 24.3M Cash* $2.1M Warrants 94.3M Debt $- Share Units (PSU/RSU/DSU) 13.1M Total Enterprise Value $8.4M * Cash balance from interim financials – April 30, 2023 Fully Diluted 482.8M Management & Insider O

  36. Slide 36: Comparable company analysis demonstrates value creation potential

    Comparable company analysis demonstrates value creation potential July 11, 2023 Market Cap Measured Indicated Inferred EV/Resource Price/Book Symbol Price Company Name Shares O/S Cash TEV ($M) (Mt) (Mt) (Mt) (M&I) (mrq) TSXV:NOU 4.050 Nouveau Monde Graphite Inc 60.7 48.8 269.8 245.9 28.5 101.8 23.0

  37. Slide 37: Sharing our values

    Sharing our values Lomiko’s PEA establishes it will contribute over $130m in wages to the local community and $240m in taxes. We believe we are on the vanguard of change: • Diverse leadership: 50% of directors are women and 2 of 3 Executive Officers are female • Committed to Call to Action #92 of th

  38. Slide 38: Diverse leadership & Experienced team, board and advisors

    Diverse leadership & Experienced team, board and advisors MANAGEMENT TEAM BOARD OF DIRECTORS STRATEGIC ADVISORS Belinda Labatte, CEO, CFA, MBA, ICD.D A. Paul Gill, Executive Chair Normand Champigny, CEO 20 years experience in capital markets. Fluent in Current positions: Executive Chair at Lomiko Me

  39. Slide 39: For more information

    For more information info@lomiko.com Follow us @lomikometals on socials l l l f l

  40. Slide 40: North American Estimated Battery Production by State

    North American Estimated Battery Production by State Source:DoE 40

Lomiko Metals — Investor Presentation (July 2023) on 6ix