Petrotal Corp. · TSX:TAL

Petrotal — Technical Presentation (May 2022)

47 slides from Petrotal's technical presentation, May 19, 2022

  1. Slide 1: FEX Energía 2022 – May 19, 2022

    ENERGIA QUE TRASCIENDE 4 ENERGIA 2022 May 19, 2022

  2. Slide 2: Geology & Reservoir

    GEOLOGY & RESERVOIR #FEXenergía

  3. Slide 3: Use of AICDs to increase the Recovery Factor in fields with a strong bottom aquifer

    Use of AICDs to increase the Recovery Factor in fields with a strong bottom aquifer: Bretana Field - Peru Antonio Zegarra Willy García #FEXenergía

  4. Slide 4: Regional Location

    REGIONAL LOCATION #FEXenergía BRETAÑA FIELD • The Marañon basin is the southern extension of a larger basin that covers the Putumayo (Colombia) and Oriente (Ecuador) • Bretana Field is a subtle structure located on the south-eastern margin of the basin

  5. Slide 5: Local Location

    LOCAL LOCATION #FEXenergía • The field it is located at the southern end of the basin • Nearby fields to the Bretana asset have robust recovery factors with similar geologic characteristics Pipeline NAUTA Bretaña Field NATURAL RESERVE NATURAL RESERVE MATSES PACAYA SAMIRIA PETROTAL Block 95

  6. Slide 6: Structure

    STRUCTURE #FEXenergía BRETAÑA STRUCTURE • The trap is induced by a reverse basement fault that does not reach the Vivian formation and defines a subtle low relief, closed on all 4 sides of an elongated structure in the NW-SE direction

  7. Slide 7: Electrical Profile

    ELECTRICAL PROFILE #FEXenergía RESERVOIR ZONE: • GROSS = 144 m • NET RESERVOIR = 135 m • Phie (avg) = 23 % • Vclay (avg) = 7 % OWC (-2609) • K core (avg) = 1000 mD. OWC (-2609) PAY ZONE: • NET PAY = 18 m • Phie (avg) = 24 % • Vclay (avg) = 7 % • Sw (avg) = 30 % • OWC @ -2609 m. CUTOFF: Phie ≥ 12 % V

  8. Slide 8: Structural Section

    STRUCTURAL SECTION #FEXenergía 00 1 1 • North-South and East-West Sections of the Vivian Formation • Peaks in GR are not correlatable, consequently barriers to vertical flow are local. A very strong bottom aquifer is confirmed • High resistivity zones are found at different levels, indicating their

  9. Slide 9: Rock and Fluid Properties

    ROCK AND FLUID PROPERTIES #FEXenergía Initial reservoir conditions: Pressure @ WOC Temperature Oil Properties Rock properties Permeability Porosity Water Saturation avg Oil Net pay ft Density Water properties Propiedades del agua Salinidad Salinity (NaCl): 82,000 ppm NaCl Specific Gravedad gravity E

  10. Slide 10: Analogies

    ANALOGIES #FEXenergía °API: 32° - 36° °API: 18° - 20° °API: 10° - 12° RF: 40% - 45% RF: 30% - 35% RF: 10% - 15% • Analogy with other fields in the Marañón basin; gravity °API and the recovery factor are considered under flank and bottom aquifers

  11. Slide 11: First Horizontal Well

    FIRST HORIZONTAL WELL #FEXenergía • Behavior of the first horizontal well drilled; It is complete with a hanger and a mesh to contain the production of sand • Interpretation of the first training test; a short radial period is observed in the derivative curve, followed by a strong response of the bo

  12. Slide 12: PTA

    PTA #FEXenergía 10H • The footprint of the bottom aquifer is observed as a constant in the pressure derivative curve in subsequently drilled wells

  13. Slide 13: Geonavigation

    GEONAVIGATION #FEXenergía IMAGE PERISCOPE EDGE (WELLS DRILLED IN 2021-2022) • Geonavigation has had to be used to maintain the trajectory of the well within the different channels • It has also served us to keep the trajectory as close to the top and avoid remnants of oil in the attic • It has been

  14. Slide 14: Completion

    | ) COMPLETION » #FEXenergia FEX

  15. Slide 15: Completion Design

    COMPLETION DESIGN #FEXenergía • Efforts are made to keep high resistivity zones separate from low resistivity zones (high saturation – high permeability) • Isolate areas without any potential, due to the danger of producing sand

  16. Slide 16: Completion Design

    COMPLETION DESIGN #FEXenergía The implementation of the AICD technology consist in the Hanger PKR installation of a set of valves throughout the productive horizontal zone of the well. The AICD through a physical Casing 7” principle of pressure change, autonomously manage to Guide restrict the entry

  17. Slide 17: Well Surveillance

    WELL SURVEILLANCE #FEXenergía Well Head: Multibowl ” x 13-3/8” x 9- Sand Monitoring 5/8”x 4-1/ ” OD, 3M psi Sensor Clampon Tubing 4-1/2, 12.6 ppf Maintaining a good well monitoring system is essential 6,000 5,500 5,000 13-3/8” 1321 m, 1° 4,500 68#/FT K55 ESP J12000N 44 stages 4,000 Intake @ 1,510 m

  18. Slide 18: Results

    RESULTS #FEXenergía

  19. Slide 19: Results

    RESULTS #FEXenergía Significant increase in Oil production ~1.3 MMBLS more recovery Days since first production Conventional Horizontal Well Vertical/Deviated Wells AICD Horizontal Wells (avg) Bretaña avg

  20. Slide 20: Results

    RESULTS #FEXenergía More Oil production with less Water production ~2.0 MMBLS less water Accumulated Water, Mbls Conventional Horizontal Well Vertical/Deviated Wells AICD Horizontal Wells (avg) Bretaña avg

  21. Slide 21: Conclusions

    | ) CONCLUSIONS » #FEXenergia FEX

  22. Slide 22: Benefits

    BENEFITS #FEXenergía Significant reduction in water production of up to 2.0 MMblsH2O/well with the consequent reduction in energy use and tCO2e emissions MW 6 Source: energy report 28.02.2022 2,000 Accumulated Oil, Mbls 1,800 5 1,600 1,400 4 1,200 1,000 3 800 2 600 ~50% by 400 water 1 injection 200

  23. Slide 23: Benefits

    BENEFITS #FEXenergía 1. With the use of AICD's, a much higher oil recovery is observed over time and with less water production. The projection shows a tendency to increase the recovery factor 2. The payout of wells with AICD technology is much faster 3. Less water is produced, therefore significant

  24. Slide 24: Benefits – Target

    BENEFITS #FEXenergía Target Reduce carbon footprint in block 95 operations Reduction of 40% of greenhouse gases by the year 2030

  25. Slide 25: Drilling

    DRILLING Manuel Casiano #FEXenergía

  26. Slide 26: Drilling optimization and high DLS generation by using BHA with power drive archer

    Drilling optimization and high DLS generation by using BHA with power drive archer in 8 ½” hole section for horizontal Wells, Field Bretaña – Block 95 – Perú Manuel Casiano #FEXenergía

  27. Slide 27: Agenda

    AGENDA #FEXenergía • Location – Block 95 • Structural map and offset well profiles • Well design and initial BHA program • Challenges • Initial drilling days and normalized days - ½” hole section • PetroTal requirements • Use of technology and performance • Final drilling days and normalized days -

  28. Slide 28: Location – Block 95

    LOCATION – BLOCK 95 #FEXenergía • Block 95 – PetroTal (Dic 2017) • Field Bretaña – Loreto - Perú • Access: river & air (helicopter) • 12 drilled wells (PetroTal) • 60% horizontal wells & 40% directional wells LOTE 95 • Current Oil production: >16,000 BOPD • Drilling development project (Oil well pro

  29. Slide 29: Location – Block 95

    LOCATION – BLOCK 95 #FEXenergía

  30. Slide 30: Structural Map & Offset Well Profiles

    D: STRUCTURAL MAP & OFFSET WELL PROFILES # F E X e n e r g í a 1 H 14H 1 H 9HS 1 6H 5H 4H 4 3D WD 3WDS 1 D 1 7D 1 D 4WD 1 DS C 11H 8H 1 H 13H D M DRILLED WELL P1 LOCATION P2 LOCATION P3 LOCATION S1 5H

  31. Slide 31: Well Design and Initial BHA Program

    WELL DESIGN AND INITIAL BHA PROGRAM # F E X e n e r g í a BHA # 01: Rotary BHA with 17” tricone bit BHA # 02: Rotary BHA with 16” PDC bit BHA # 03: HA with DH + WD y 16” PD bit BHA # 04: HA with Power Drive + WD and 12 ¼” PD bit BHA # 05: HA with DH + WD and 8 ½” PD bit BHA # 06: BHA with Power Driv

  32. Slide 32: Problematic

    PROBLEMATIC #FEXenergía TYPICAL WELL DESIGN – 8 ½” HOLE SECTION 8 ½” LE SE . R LL G MES BHA with DHM (BH: 1.5°) AVG ROP: 18 m/hr • Use of 2 types of BHA´s (Surface trip) • Re logging times (correlate landing point) BHA with Power drive X6 AVG ROP: 20 m/hr RISKS • Involuntary Sidetrack. • Exposure ti

  33. Slide 33: Initial Drilling Days – 8 1/2" Hole Section

    INITIAL DRILLING DAYS – 8 ½” H T N #FEXenergía % USAGE WELLS POWER DHM DRIVE BN-4H 78.1 21.9 BN-5H 52.5 47.5 BN-6H 35.2 64.8 BN-8H 36.3 63.7

  34. Slide 34: Normalized Days – 8 1/2" Hole Section

    NORMALIZED DAYS – 8 ½” H T N #FEXenergía

  35. Slide 35: PetroTal Requirements

    PETROTAL REQUIREMENTS #FEXenergía REQUIREMENTS • Drilling 8 ½” hole section (build and land the well) with only one BHA and capacity to generate DLS higher than 5°/30m • Increase depth interval for 8 ½” hole section for future wells with complex trajectory profiles TECHNOLGY SUGGESTED • Power drive

  36. Slide 36: Use of Technology and Performance

    USE OF TECHNOLOGY AND PERFORMANCE #FEXenergía WELL PLAN (BN-10H) MD Incl Azim True TVD TVDSS VSEC DLS BR TR Comments (m) (°) (°) (m) (m) (m) (°/30m) (°/30m) (°/30m) 9 5/8" Casing 2600.00 32.35 353.14 2283.21 2168.27 1134.27 0.00 0.00 0.00 KOP 2810.00 32.35 353.14 2460.61 2345.67 1245.39 0.00 0.00 0.

  37. Slide 37: Final Drilling Days – 8 1/2" Hole Section

    FINAL DRILLING DAYS – 8 ½” H T N #FEXenergía % USAGE WELLS POWER DHM DRIVE BN-4H 78.1 21.9 BN-5H 52.5 47.5 BN-6H 35.2 64.8 BN-8H 36.3 63.7 BN-9H-ST1 0.0 100.0 BN-10H 0.0 100.0 DHM & Power drive X6 Power drive Archer

  38. Slide 38: Normalized Days – 8 1/2" Hole Section

    NORMALIZED DAYS – 8 ½” H T N #FEXenergía DHM & Power drive X6 Power drive Archer

  39. Slide 39: Drilling Optimization – 8 1/2" Hole Section

    DRILLING OPTIMIZATION– 8 ½” H T N #FEXenergía SAVED DAYS AND MONEY • Depth Interval of 550 m 8 1/2" HOLE SECTION - 550 m • Well BN-8H (Use of two BHA´s) • Best normalized drilling days - 8 ½” hole DAILY DRILLING COST (USD) 235,000 section - 3.7 days DRILLING DAYS EFFICIENCY 2.1 AMOUNT (USD) 493,500

  40. Slide 40: Well Design and Final BHA Program

    WELL DESIGN AND FINAL BHA PROGRAM # F E X e n e r g í a

  41. Slide 41: Conclusions and Recommendations

    CONCLUSIONS AND RECOMMENDATIONS # F E X e n e r g í a CONCLUSIONS • Performance of power drive archer shows 2.1 days less per well compared to the use of two BHA´s generating a net saved amount of 418 MUSD per well • For a regular drilling campaign (5 horizontal wells per year), it represents a redu

  42. Slide 42: Disclaimers

    Disclaimers #FEXenergía

  43. Slide 43: Forward-Looking Information

    BENEFITS Forward-Looking Information Certain information included in this presentation constitutes forward-looking information under applicable securities legislation. Forward-looking information typically contains statements with words such as “anticipate”, “believe”, “expect”, “plan”, “intend”, “e

  44. Slide 44: Oil and Gas Advisories

    BENEFITS Oil and Gas Advisories Crude Oil. All references to “oil” or “crude oil” production, revenue or sales mean “heavy crude oil” as defined in National Instrument 51-101 – Standards of Disclosure for Oil and Gas Activities (“NI 51-101”). Brent refers to Intercontinental Exchange “ICE” Brent. Re

  45. Slide 45: Analogous Information

    BENEFITS Analogous Information. Certain information in this document may constitute "analogous information" as defined in NI 51-101, including, but not limited to, information relating to areas, wells and/or operations that are in geographical proximity to or on- trend with lands held by PetroTal an

  46. Slide 46: Non-GAAP Financial Measures, Oil and Gas Metrics and KPIs

    BENEFITS Non-GAAP Financial Measures, Oil and Gas Metrics and Other Key Performance Indicators This presentation may contain certain financial measures, as described below, which do not have standardized meanings prescribed by generally accepted accounting principles (“GAAP”). In addition, this pres

  47. Slide 47: Energia que trasciende

    ENERGIA QUE TRASCIENDE xX ENERGIA 2022

PetroTal — Technical Presentation (May 2022) on 6ix