Aker Bp Asa · OSL:AKRBP
Aker Bp Asa — Det norske oljeselskap — Q1 2015 Earnings Presentation
22 slides from Aker Bp Asa's earnings presentation, May 6, 2015
Slide 1: Q1 2015 Results
Q1 Sa 6 MAY 2015 @ .) DET NORSKE OLJESELSKAP e KARL JOHNNY HERSVIK, CEO ALEXANDER KRANE, CFO
Slide 2: Highlights
DET NORSKE Highlights Finance Q1 EBITDA USD 256 million, EPS 0.01 (USD) DETNOR02 loan agreement amended USD 500 million RCF fully underwritten Contemplating USD 300 million subordinated bond issue Operations Total production of 64.9 mboepd in Q1 2015 Production commenced on Bøyla in
Slide 3: Financials
Financials 2 Q1 2015 DETNORSKE
Slide 4: Statement of income
FINANCIALS Statement of income Income statement (USD mill) Q1 2015 Q1 2014 FY 2014 Revenues 324 26 464 Production costs 39 7 67 Other operating expenses 14 1 49 EBITDAX 271 18 365 Exploration expenses 15 20 158 EBITDA 256 -2 208 Depreciation 122 15 160 Impairment losses 53 27 346 Operating profit/lo
Slide 5: Statement of financial position
FINANCIALS Statement of financial position Assets Equity and Liabilities (USD mill) 31.03.15 31.03.14 (USD mill) 31.03.15 31.03.14 Goodwill 1 134 54 Equity 654 530 Other intangible assets 940 367 Other provisions for liabilities incl. P&A 498 145 (long) Property, plant and equipment 2 679 591 Deferr
Slide 6: Amending current debt instruments
FINANCIALS Amending current debt instruments Net debt of USD 2 billion Outstanding debt of USD 2.4 billion (bonds and bank debt) at the end of Q1 2015 Cash, cash equivalents and undrawn credit of about USD 1.0 billion at the end of Q1 2015 DETNOR02 (2013/2020) NOK 1.9 billion bond Amended
Slide 7: Further diversifying the capital structure
FINANCIALS Further diversifying the capital structure Debt capital structure Overview 3.85 New USD 500 million RCF fully underwritten by bank consortium 0.50 RCF - undrawn Four-year tenor and 1+1 extension option 2.95 Utilization fee of 1.5% and margin of 4%, stepping 0.90 RBL - undrawn up by
Slide 8: Production
f Production ie & Q1 2015 DETNORSKE
Slide 9: Net production
PRODUCTION Net production Net production (boepd) Q1 production Q1 2015 production of 64.9 mboepd Production availability was 96.4%, above target Realized oil price of USD 58/bbl New wells and work-overs Bøyla put on stream in January, and had an average production of 8,300 boepd (net) in
Slide 10: Continuing to develop the Alvheim area
PRODUCTION Continuing to develop the Alvheim area Alvheim area Near-term wells on Alvheim Kneler 1: Planned to commence production around year-end BoaKamNorth: Planned to commence drilling in Q4 2015 and to come on stream mid 2016 Viper Kobra: Development project ongoing, will come on stream
Slide 11: Development Projects
Development Projects Q1 2015
Slide 12: Development on track
IVAR AASEN (~35%*) Development on track 2012 2013 2014 2015 2016 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 Concept selection FEED studies PDO approval Unitisation Agreement Construction of jacket Construction of topside Construction of LQ Maersk Interceptor to Norway Drilling of geo-pilots Jacket lifted into pl
Slide 13: First geo-pilots in line with expectations
IVAR AASEN (~35%*) First geo-pilots in line with expectations Drilling of the geo-pilots in Ivar Aasen commenced in January First geo-pilots were broadly in line with expectations Provided valuable information for the placement of production wells Drilling of pilot wells will be concluded by
Slide 14: Jacket ready for installation
IVAR AASEN (~35%*) Jacket ready for installation Jacket completed in January 2015 On time and on cost with no major incidents Jacket has arrived in Rotterdam Will remain in Rotterdam until the installation on the Ivar Aasen field The Thialf vessel will install the jacket The Wei-Li vesse
Slide 15: Topside construction about 60% completed
IVAR AASEN (~35%*) Topside construction about 60% completed Topside on schedule Detailed engineering in its final stage Key equipment packages arrived on site as planned Start commissioning this autumn Mechanical complete by year-end 2015 Sail-away during spring 2016 * 34.78% in PL 01B/2
Slide 16: PDO submitted, contracts being awarded
JOHAN SVERDRUP (11.89%, preliminary working interest) PDO submitted, contracts being awarded PDO submitted in February 2015 Production start-up: Q4 2019 Volumes: 1.7-3.0bn boe (~80% from Phase 1) Capex: NOK 117bn in Phase 1, NOK 170-220bn in total First contracts have been awarded Aker S
Slide 17: Exploration
Exploration Q1 2015
Slide 18: 2015 drilling activity
EXPLORATION & APPRAISAL 2015 drilling activity 2015 Drilling schedule 2015 wells in the North Sea License Prospect Share mmboe Rig Timing PL Krafla North & Transocean 25 % - Q4 14/Q1 15 272/035 Main Leader Maersk PL 001B Løvstakken 35% - Q1 15 Interceptor PL 627 Skirne East 20 % 50-171 Leiv Eiriksso
Slide 19: Outlook
Outlook ad Ql 2015 DETNORSKE
Slide 20: Identified 2015 reductions exceed USD 100m
COST EFFICIENCY PROGRAMME Identified 2015 reductions exceed USD 100m Cost efficiency programme progressing well Measures identified currently exceed USD 100 million 35 people offered redundancy packages or early retirement packages Will continue to improve supply chain and optimize work proc
Slide 21: Summary and outlook
OUTLOOK Summary and outlook Financial Finalize the USD 300 million subordinated bond issue and the USD 500 million RCF Continue to optimize the capital structure of the company going forward Development projects Ivar Aasen progressing according to plan Johan Sverdrup PDO submitted, unit
Slide 22: Det norske
a DETNORSKE www.detnor.no
Det norske oljeselskap — Q1 2015 Earnings Presentation on 6ix