Slide 1: J.P. Morgan Midwest Utilities & Midstream 1x1 Forum
J.P. Morgan Midwest Utilities & Midstream 1x1 Forum March 28, 2024 Ammons compressor station – Appalachia Gathering System phase 2 expansion
Slide 2: Safe Harbor Statement
New slide Safe Harbor Statement This presentation contains statements which, to the extent they are not statements of historical or present fact, constitute “forward-looking statements” under the securities laws. These forward-looking statements are intended to provide management’s current expectati
Slide 3: DT Midstream Investment Thesis
DT Midstream Investment Thesis Pure play natural gas Premium shareholder Strong organic growth Balance sheet strength midstream portfolio returns ~65% pipeline segment1; Distinctive Adjusted Sizeable project backlog Line-of-sight to investment highest in sector2 EBITDA4 growth of 10%5 grade credit r
Slide 4: Pure Play Natural Gas Midstream Portfolio
Pure Play Natural Gas Midstream Portfolio Integrated pipeline platform in leading gas basins serving growing markets Pipelines connect world-class basins to high-quality markets • ~900 miles of FERC-regulated interstate pipelines that have interconnections with multiple interstate pipelines and util
Slide 5: Delivering Distinctive and Predictable Growth
Delivering Distinctive and Predictable Growth Track record of strong growth Historical Adjusted EBITDA1 Relative Growth (Millions) 2020-2023 Adjusted EBITDA CAGR2 9% 9% CAGR $924 $841 $778 $720 4% 2020 2021 2022 2023 Peer average3 ✓ Well positioned assets and take-or-pay contract structures consiste
Slide 6: Diversified Asset Base Anchored by Strong Pipeline Segment
Diversified Asset Base Anchored by Strong Pipeline Segment Highest natural gas pipeline asset contribution in sector1 Business mix (% of total 2023 Adjusted EBITDA2) Highly contracted asset portfolio supports Millennium NEXUS 11% Pipeline stable cash flows 63% 13% Ohio Utica LEAP • Average portfolio
Slide 7: High Quality Cash Flows and Customers
High Quality Cash Flows and Customers Cash flows are underpinned by take-or-pay contracts and high credit quality customers Total revenue contribution Customer credit (% of 2023 contribution1) (% of 2023 contribution) ~90% ~85% Demand / MVC or Investment grade and flowing gas2 “Rising star3” Non-inv
Slide 8: Positioned to Serve In-flight LNG Export Demand
Positioned to Serve In-flight LNG Export Demand LNG growth of ~7 Bcf/d within LEAP’s corridor is not subject to DOE permit approvals LNG demand that LEAP can serve Forecasted US LNG export capacity growth1 DOE DOE (bcf/d) LNG project Bcf/d LNG project Bcf/d approval2 approval2 Operational Pre-FID Sa
Slide 9: New Haynesville Takeaway Capacity is Needed to Meet LNG Demand
New Haynesville Takeaway Capacity is Needed to Meet LNG Demand LEAP offers lower-risk, capital efficient expansion opportunity, proving timely access to LNG demand Forecasted Louisiana Gulf Coast area LNG capacity growth1 vs announced Haynesville takeaway expansions2 (Cumulative growth from 2023, bc
Slide 10: Strong Long-term Production Outlook in Both Basins
Strong Long-term Production Outlook in Both Basins Haynesville and Appalachia production are expected to experience significant growth over the next decade Historical production Production forecast (bcf/d) Haynesville Appalachia (bcf/d) Haynesville Appalachia 60 +18 bcf/d 67 50 40 27 49 30 15 20 10
Slide 11: Continuing Our Track Record of Distinctive Growth
Continuing Our Track Record of Distinctive Growth Targeting long-term Adjusted EBITDA growth of 5-7% Adjusted EBITDA1 (millions) 5-7% long-term +6% growth rate $980 - $1,040 Differentiated growth drivers $930 - $980 $1.3 billion organic growth project backlog Tangible energy transition projects
Slide 12: Committed Growth Investment Summary
Committed Growth Investment Summary Continue to advance short-cycle growth investments Expected Project in-service dates Haynesville LEAP pipeline expansion – phase 2 In-service Pipeline Haynesville LEAP Gillis Access interconnect Q2 2024 Haynesville LEAP pipeline expansion – phase 3 Q3 2024 Appalac
Slide 13: Sizeable Organic Project Backlog
Sizeable Organic Project Backlog Balanced opportunity set across all business segments Pipeline Gathering Project Contribution Status Project Contribution Status LEAP phase 1 expansion Aug. 2023 In-service Blue Union gathering / treating expansion Dec. 2023 In-service LEAP phase 2 expansion Dec. 202
Slide 14: Increasing LEAP Expansion Potential
Increasing LEAP Expansion Potential Market fundamentals driving greater demand for Haynesville to Gulf Coast pipeline capacity DTM assets LNG facilities DTM treating plants Operational Phase 3 LEAP expansion on track and on budget to Electric compression Under development increase capacity from 1.7
Slide 15: Louisiana Carbon Capture and Sequestration
Louisiana Carbon Capture and Sequestration Disciplined approach to CCS project Project timeline Methodical project development approach Capital deployment Q4 ✓ Class VI well permit filing Disciplined storage site selection and stakeholder engagement 2022 ✓ Conducted 3D seismic survey ✓ Proximity to
Slide 16: Louisiana Carbon Capture and Sequestration
Louisiana Carbon Capture and Sequestration Disciplined approach to CCS project Illustrative Carbon Capture and Sequestration process Phase 1 Phase 2 Natural gas Equipment captures CO2 treating facility from treating plants Capture equipment, Capture equipment, Scope CO2 pipeline, CO2 pipeline, CO2 c
Slide 17: Ohio Utica System Initial Trunkline Construction Completed
Ohio Utica System Initial Trunkline Construction Completed Overall construction progressing ahead of schedule Emerging associated gas resource development area • Initial gathering backbone buildout of >200 MMcf/d capacity – Expected DTM investment1 of ~$100 million for 2023-2024 Direct access – ~5x
Slide 18: DTM Assets are Strategically Connected to Growing Demand
DTM Assets are Strategically Connected to Growing Demand LEAP offers 3.5 Bcf/d of direct connectivity to LNG markets Adding new connectivity to Haynesville system to support existing DOE approved LNG projects • Current interconnect capacity of 2.5 Bcf/d to operating LNG terminals • Building new 1 Bc
Slide 19: Disciplined Capital Investment
Disciplined Capital Investment Self-funding highly accretive organic growth projects Growth capex (millions) Committed Pre-FID 2023 original guidance Flexible, short-cycle, capital investments • Total committed capex of ~$300 million over 2024/2025 • Advancing numerous accretive organic projects tow
Slide 20: Strong balance sheet, free of near-term debt maturities
Strong balance sheet, free of near-term debt maturities Expecting investment grade credit rating in 2024 Debt maturity profile ($ billions) Long-term debt Undrawn revolver capacity Drawn revolver balance $1.1 ~$0.9 billion liquidity $1.0 $1.0 3.6x / 4.1x on-balance sheet / proportional leverage1 $0.
Slide 21: Executing a Leading ESG Program
Executing a Leading ESG Program Second highest MSCI rating among midstream peers Environmental • Continuing to advance CCS opportunity in Louisiana • Advancing hydrogen development opportunities with strategic partnership • Transitioning to net zero GHG emissions by 2050, including a 30% reduction b
Slide 22: Committed to Strong Governance Practices
Committed to Strong Governance Practices Best-in-class governance practices DT Midstream Board Composition • Structured as C-Corp with separate CEO and Chairman • Long-term incentive plans tied to total shareholder return targets Robert Skaggs, Jr. Stephen Baker • Board committee focused on ESG init
Slide 23: Appendix
Appendix 23
Slide 24: 2024/2025 Guidance Summary
2024/2025 Guidance Summary (millions, except EPS) Guidance 2024 Adjusted EBITDA1 $930 - $980 2024 Operating Earnings2 $335 - $375 2024 Operating EPS2 $3.43 - $3.83 2024 Distributable Cash Flow3 $640 - $700 2024 Capital Expenditures4 $330 - $415 Growth Capital $300 - $375 Maintenance Capital $30 - $4
Slide 25: Joint Venture Debt Details
Joint Venture Debt Details Annual debt paydown at Millennium and Vector DTM proportionate share End of year debt balances Interest expense Asset Weighted average (DTM ownership %) 2023 2024 2025 2023 2024 2025 interest rate1 Maturity NEXUS Pipeline Bullets, 2028 $371 $371 $371 $14 $21 $21 5.68% (50%
Slide 26: Non-GAAP Definitions
New slide Non-GAAP Definitions Adjusted EBITDA and Distributable Cash Flow (DCF) are non-GAAP measures Adjusted EBITDA is defined as GAAP net income attributable to DT Midstream before expenses for interest, taxes, depreciation and amortization, and loss from financing activities, further adjusted t
Slide 27: Non-GAAP Definitions
New slide Non-GAAP Definitions Operating Earnings and Operating Earnings per share are non-GAAP measures Use of Operating Earnings Information – Operating Earnings exclude non-recurring items, certain mark-to-market adjustments and discontinued operations. DT Midstream management believes that Opera
Slide 28: Non-GAAP Reconciliations