  1. Slide 1: Annual General Meeting

    ANNUAL GENERAL MEETING TSX: FM; LSE: FQM

  2. Slide 2: Philip Pascall, Chairman & CEO - Annual General Meeting May 21, 2014

    Philip Pascall Chairman & CEO ANNUAL GENERAL MEETING May 21, 2014 TSX: FM; LSE: FQM

  3. Slide 3: Nominees for Election to the Board

    NOMINEES FOR ELECTION TO THE BOARD Philip Pascall Clive Newall Martin Rowley Peter St. George Andrew B. Adams Paul Brunner Michael Hanley Robert Harding Michael Martineau ANNUAL GENERAL MEETING May 21, 2014

  4. Slide 4: Our Board of Directors

    OUR BOARD OF DIRECTORS Philip Pascall Clive Newall Martin Rowley Peter St. George Andrew B. Adams Paul Brunner Michael Hanley Robert Harding Michael Martineau ANNUAL GENERAL MEETING May 21, 2014

  5. Slide 5: Philip Pascall, Chairman & CEO

    Philip Pascall Chairman & CEO ANNUAL GENERAL MEETING May 21, 2014 TSX: FM; LSE: FQM

  6. Slide 6: Clive Newall, President

    Clive Newall President ANNUAL GENERAL MEETING May 21, 2014 TSX: FM; LSE: FQM

  7. Slide 7: Cautionary Note Regarding Forward-Looking Statement

    CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENT Some of the statements contained in the following material are forward-looking statements and not statement of facts. Such statements are based on the current beliefs of management, as well as assumptions based on management information currently a

  8. Slide 8: 2013 – A Transformative & Successful Year

    2013 – A TRANSFORMATIVE & SUCCESSFUL YEAR  Successfully acquired Inmet Mining Corporation  Gained control of the Tier 1 Cobre Panama copper project  Added 3 well-run, low-cost operations  Increased copper resources by 73%  Advanced development projects  Record production at 4 mines ANNUAL GENE

  9. Slide 9: Good Operating Performance Continues into 2014: Production

    GOOD OPERATING PERFORMANCE CONTINUES INTO 2014  Production up in all products: 113,118 60,164 15,342 11,838 43% 7% 8% 22% Q1 '13 Q1'14 Q1 '13 Q1'14 Q1 '13 Q1'14 Q1 '13 Q1'14 Copper - tonnes Nickel - tonnes Gold - ounces Platinum & Palladium - ounces ANNUAL GENERAL MEETING May 21, 2014

  10. Slide 10: Good Operating Performance Continues into 2014: Cash Cost

    GOOD OPERATING PERFORMANCE CONTINUES INTO 2014  Cash cost down: 18% $4.37 9% $1.38 Q1 '13 Q1'14 Q1 '13 Q1'14 Copper - $/lb Nickel - $/lb ANNUAL GENERAL MEETING May 21, 2014

  11. Slide 11: Optimized Capital Structure & Financial Flexibility

    OPTIMIZED CAPITAL STRUCTURE & FINANCIAL FLEXIBILITY  Well-financed growth program  Cash at March 31’14 = $747.2M  Cash from operations Q1 = $370.1M  Available facilities = $1.3B  Senior Notes = $850M ANNUAL GENERAL MEETING May 21, 2014

  12. Slide 12: One of the Few Mining Companies Investing in Building Capacity

    ONE OF THE FEW MINING COMPANIES INVESTING IN BUILDING CAPACITY ANNUAL GENERAL MEETING May 21, 2014

  13. Slide 13: Copper Smelter Complex, Zambia

    COPPER SMELTER COMPLEX, ZAMBIA  CAPACITY  Phase 1 processing capacity of 1.2 Mtpa  Copper production 300,000 Tpa  Acid production 1.0 Mtpa  TARGETED COMMISSIONING  From 2H2014  ESTIMATED SAVINGS  US$340M - US$510M/year  FURTHER POTENTIAL  Phase 2 planned to increase processing capacity to

  14. Slide 14: Trident, Zambia

    TRIDENT, ZAMBIA  LONG LIFE  Estimate mine life of between 15 to 20 years  CAPACITY  Annual production up to 300,000 tonnes of copper  38,000 to 60,000 tonnes of nickel in concentrate per annum  TARGETED COMPLETION  Mid-2014  INVESTMENT  US$2 billion investment ANNUAL GENERAL MEETING May 21,

  15. Slide 15: Cobre Panama, Panama

    COBRE PANAMA, PANAMA  LONG LIFE  Estimated mine life of over 30 years  CAPACITY  Average annual life-of-mine copper production of 320,000 tonnes  Significant gold, silver and molybdenum by-products  TARGETED COMPLETION  Commissioning in late 2017  INVESTMENT  US$6.4 billion investment  ANN

  16. Slide 16: Growth Supported by High-Quality, Stable Operations

    GROWTH SUPPORTED BY HIGH-QUALITY, STABLE OPERATIONS ANNUAL GENERAL MEETING May 21, 2014

  17. Slide 17: Kansanshi Cu-Au Mine, Zambia

    KANSANSHI CU-AU MINE, ZAMBIA  Started operations in 2005  Current estimated mine life of 17 years  2013 Performance  271 kt of copper  167 kozs of gold  $1.38/lb copper C1 cash cost  2014 Outlook  255 to 270 kt of copper  145 to 160 kozs of gold  Workforce = ~1,937 ANNUAL GENERAL MEETING M

  18. Slide 18: Las Cruces Cu Mine, Spain

    LAS CRUCES CU MINE, SPAIN  Started operations in 2010  Current estimated mine life of 9 years  2013 Performance  69 Kt of copper  $1.14/lb copper C1 cash cost  2014 Outlook  69 to 72 kt of copper  Workforce = ~254 ANNUAL GENERAL MEETING May 21, 2014

  19. Slide 19: Guelb Moghrein Cu-Au Mine, Mauritania

    GUELB MOGHREIN CU-AU MINE, MAURITANIA  Started operations in 2006  Current estimated mine life of 8 years  2013 Performance  38 kt tonnes of copper  58 kozs of gold  $1.58/lb copper C1 cash cost  2014 Outlook  36 to 39 kt of copper  55 to 60 k ozs of gold  Workforce = ~1,170  Magnetite pl

  20. Slide 20: Ravensthorpe Ni Mine, Australia

    RAVENSTHORPE NI MINE, AUSTRALIA  Started operations in 2011  Current estimated mine life of 30 years  2013 Performance  38 kt of nickel  $4.99/lb C1 cash cost  2014 Outlook  33 to 37 kt of nickel  Workforce = ~428 ANNUAL GENERAL MEETING May 21, 2014

  21. Slide 21: Kevitsa Ni-Cu-PGE Mine, Finland

    KEVITSA NI-CU-PGE MINE, FINLAND  Started operations in 2012  Current estimated mine life of 29 years  2013 Performance  15 kt of copper  $1.68/lb copper C1 cash cost  9 kt of nickel  $5.24/lb nickel C1 cash cost  2014 Outlook  17 to 19 kt of copper  9 to 10 kt of nickel  Workforce = ~337

  22. Slide 22: Çayeli Cu-Zn Mine, Turkey

    ÇAYELI CU-ZN MINE, TURKEY  Current estimated mine life of 6 years with potential for an additional 3 years  2013 Performance  32 kt of copper  43 kt of zinc  $0.76/lb copper C1 cash cost  2014 Outlook  27 to 29 kt of copper  38 to 42 kt of zinc  Workforce = ~520 ANNUAL GENERAL MEETING May 2

  23. Slide 23: Pyhäsalmi Cu-Zn Mine, Finland

    PYHÄSALMI CU-ZN MINE, FINLAND  One of the most efficient underground mines in the world  Current estimated mine life of 6 years  2013 Performance  15 kt of copper  22 kt of zinc  $0.14/lb copper C1 cash cost  2014 Outlook  14 to 15 kt of copper  21 to 23 kt of zinc  Workforce = ~228 ANNUAL

  24. Slide 24: A Copper-Focused, Global Company

    Revenues A COPPER-FOCUSED, GLOBAL COMPANY Zinc Other Gold 2% Signifiant Nickel and Gold Production 3% 6% Operations and Projects in 8 countries Nickel High-Quality, Stable, Efficient Operations 16% Strong Liquidity & Cash Flow Industry-Leading Growth Unique Core Strength of In-House Project De

  25. Slide 25: Philip Pascall, Chairman & CEO

    Philip Pascall Chairman & CEO ANNUAL GENERAL MEETING May 21, 2014 TSX: FM; LSE: FQM

  26. Slide 26: Annual General Meeting

    ANNUAL GENERAL MEETING TSX: FM; LSE: FQM