Kefi Gold And Copper Plc · LSE:KEFI

Kefi Gold And Copper — Conference Presentation (September 2024)

31 slides from Kefi Gold And Copper's conference presentation, September 2024

  1. Slide 1: An Early Mover in the Arabian-Nubian Shield

    An Early Mover in the Arabian-Nubian Shield Presentation September 2024 Colorado, USA kefi-goldandcopper.com

  2. Slide 2: Disclaimer

    Disclaimer ARABIAN - NUBIAN SHIE 2 kefi-goldandcopper.com Focused On Arabian- Nubian Shield

  3. Slide 3: KEFI is the Early Mover, with Discoveries & Growth Platform

    N KEFI is the Early Mover, with Discoveries & Growth Platform E T H I O P I A – L e a d P a r t n e r - 1 st B a n k a b l e P r o j e c t ▪ 2017 JV with Government - started Early Works in 2024 ▪ 144Koz pa open pit, with potential for underground mine to lift to 200Koz pa ▪ 1.7Moz high-grade gold (

  4. Slide 4: KEFI – Why Now?

    KEFI – Why Now? GOLD + COPPER ❑ Share Price has dropped 90% from 2017, due to Ethiopia internal turmoil Share Price 10% of NPV of ❑ At US$2,500/oz gold, all bank debt can be repaid in 1st production year Main Project (US$2,500/oz) ❑ Ethiopia lifted state of emergency in 2022. Now back in Top 10 grow

  5. Slide 5: Ethiopia – Why Now?

    Ethiopia – Why Now? 2018 MAJORITY RULE INTRODUCED AND NOW HAS BEEN ACCEPTED LOCALLY AND INTERNATIONALLY ▪ 2023: “Top 10 Growth Countries” status now re-established ▪ 2023: Transparent licensing introduced for exploration and mining ▪ 2024: Capital and currency controls eased, starting with KEFI “The

  6. Slide 6: Saudi Arabia – Why Now?

    Gold/Copper Deposit Saudi Arabia – Why Now? N KEFI MINERALS ETHIOPIA KEFI (G&M JV) EL KEFI (G&M JV) ELA Arabian Nubian Shield MINING INDUSTRY ENTERING : Jibal Qutman Hawiah (VHMS) ARABIAN - NUBIAN SHIE Tulu Kapi KEFI’S projects and other selected projects in the Arabian-Nubian Shield 6 kefi-goldandc

  7. Slide 7: Country Risk Map – African Gold Producers

    Country Risk Map – African Gold Producers ARABIAN - NUBIAN SHIE 7 kefi-goldandcopper.com Focused On Arabian- Nubian Shield

  8. Slide 8: Opportunities in Ethiopia and KSA Outweigh Risk

    Opportunities in Ethiopia and KSA Outweigh Risk ARABIAN - NUBIAN SHIE Hawiah: +5km of mineralized gossanous ridge. KEFI first to drill and trench. Tulu Kapi: 1M oz Reserve within 1.7M oz Resource and open. Now +30Mt at 1.7% Cu-Equiv and open. Au-equiv of 2.5M oz KEFI first to trench despite shallown

  9. Slide 9: Stakeholders meeting July 2024 at Tulu Kapi

    Stakeholders meeting July 2024 At the site of Tulu Kapi’s initial construction camp. Overlooking the planned site processing facilities and mine ARABIAN - NUBIAN SHIE School provided by KEFI Minerals Ethiopia for the Tulu Kapi community 9 kefi-goldandcopper.com Focused On Arabian- Nubian Shield

  10. Slide 10: Current Priorities

    Current Priorities Tulu Kapi Gold Project US320M CAPITAL STRUCTURE KEFI GOLD + COPPER Formal Process Underway, Comprising the following Parallel Streams: (LON: KEFI) ▪ Project Debt Finance of US$190M between 2 banks 52 Week Low - High 0.49p – 0.92p ▪ Lead Bank TDB has approved and co-lender AFC is p

  11. Slide 11: Comparative Valuations

    Comparative Valuations KEFI Undervalued vs. Peers, despite High Quality Projects US$ US$ 350 African gold companies Enterprise Value per oz of production* African gold companies Enterprise Value per oz 5,000 of Measured and Indicated Resource 300 4,500 4,000 250 3,500 200 3,000 2,500 150 2,000 100 1

  12. Slide 12: KEFI Corporate Structure

    KEFI Corporate Structure KEFI Emphasis on Regional Alliances GOLD + COPPER Management 7-15%* 85-93% Public Shareholders Regional Investor/s via Notes and Bonds 25% c.85-100% GMCO KEFI Minerals Ethiopia 0-15% ARTAR Ethiopian Institutions 75% Saudi Arabia c.85-90% c.10-15% Ethiopian Government Tulu Ka

  13. Slide 13: KEFI - about to achieve overnight success – after 15 Years

    KEFI - about to achieve overnight success – after 15 Years • Both Ethiopia and Saudi Arabia have turned for the better • Both countries recognise KEFI’s longstanding focus • We have a shovel-ready project in Ethiopia and two coming in Saudi Arabia • Gold and copper price long term ARABIAN - NUBIAN S

  14. Slide 14: Tulu Kapi Overview

    Tulu Kapi Overview • Standard 2Mtpa CIL processing plant • Contract mining – truck and shovel • Open pit waste to ore ratio of 7.5 to 1 • Head grade of 2.1g/t gold • Gold recoveries of 93% • Annual gold production of c.140Koz ARABIAN - NUBIAN SHIE • 1.0Moz gold to be mined from open pit • Potential

  15. Slide 15: Hawiah - VMS Copper-Gold-Zinc-Silver

    Hawiah - VMS Copper-Gold-Zinc-Silver Top 3 base metals discovery in Saudi Arabia – working on DFS • Major greenfield discovery made in 2019 • 101,000m drilling programme since 2019 • Mineral Resource of 29Mt at 0.89% copper, 0.94% zinc, 0.67g/t gold and 10.1g/t silver • Further near-term resource ex

  16. Slide 16: Hawiah Project - Long section displaying resource classification and open pit shells

    Hawiah Project - Long section displaying resource classification and open pit shells ~ Crossroads Extension 5000m Strike > Crossroads Central Zone Camp Lode Open Pit- 11.1 Mt Underground - 17.9 Mt Resource Classification THE anoenece Facing East ep_>old GE inferres k-minerals . Caen @ Unciassifies H

  17. Slide 17: ADDENDA

    ADDENDA E: info@kefi-goldandcopper.com Kefiminerals KEFI Gold and Copper kefi-goldandcopper.com

  18. Slide 18: Tulu Kapi Gold Mine

    ARABIAN - NUBIAN SHIE • Lead bank and Lead investors have approved US$320 million finance package Tulu Kapi • Early Works commenced to prepare for finance closing October 2024 Gold Mine • Major Works to follow finance closing and target production commissioning mid-2026 18 kefi-goldandcopper.com Foc

  19. Slide 19: Tulu Kapi - 130,000m of Drilling: Still Open at Depth

    Tulu Kapi - 130,000m of Drilling: Still Open at Depth ARABIAN - NUBIAN SHIE 73,109m of Diamond drilling 49,625m of RC Drilling 4,818m of Geotechnical Drilling 6,051m of Hydrogeological Drilling 1,417m of Trenching 19 kefi-goldandcopper.com Focused On Arabian- Nubian Shield

  20. Slide 20: CSR Policy & Strategy

    CSR Policy & Strategy A Long-Term Partnership Between KEFI, Government & Community • Open communication and transparency, cooperative and collaborative engagement • Government support and guidance to help facilitate and coordinate, activate formal communication platforms • Engage community for input

  21. Slide 21: Independent Experts Sign Off

    Independent Experts Sign Off Tulu Kapi Signed Off by Leading Experts for the International Syndicate Security Due Diligence Financial Model ARABIAN - NUBIAN SHIE Environment & Social Definitive Feasibility Study Resources & Reserves 21 kefi-goldandcopper.com Focused On Arabian- Nubian Shield

  22. Slide 22: Saudi Arabia

    ARABIAN - NUBIAN SHIE Saudi Arabia Two advanced projects and large regional portfolio 22 kefi-goldandcopper.com Focused On Arabian- Nubian Shield

  23. Slide 23: GMCO JV

    GMCO JV ~1,000km² License Package • GMCO holds Exploration Licences (“EL’s”) via (ARTAR) covering ~1,000 km2 and further applications (ELA’s) • All licences being transferred into GMCO for ease of project financing • Teams mobilised onto 14 new EL’s, three times what GMCO was granted in previous ARA

  24. Slide 24: Jibal Qutman - Near Surface, Orogenic Gold

    Jibal Qutman - Near Surface, Orogenic Gold) ~270Km² Licence Package Including 0.7Moz Resource as basis for the current DFS • A GMCO discovery on which work was suspended in 2016 during a regulatory overhaul and the site was re-accessed in late 2022 New Asfingia • Mining Licence Area initially planne

  25. Slide 25: CORPORATE

    CORPORATE E: info@kefi-goldandcopper.com Kefiminerals KEFI Gold and Copper kefi-goldandcopper.com

  26. Slide 26: KEFI Board of Directors

    KEFI Board of Directors Experienced Industry Specialists for the Region Harry Anagnostaras-Adams John Leach Addis Alemayehou Alistair Clark Richard Robinson Executive Chair – B. Comm, MBA, Finance Director – BA Non-Executive – representative with Non-Executive Non-Executive – Chair of Fellow of Aust

  27. Slide 27: Management Team - Executive Directors Plus...

    Management Team - Executive Directors Plus... Eddy Solbrandt – Chief Operating Officer Robert Williams - Corporate Development & Eddy began his career in the mining industry in 1986 and has Technical Studies since worked in open cut and underground metalliferous mines, Rob began his career in mining

  28. Slide 28: Strong Project Economics for Tulu Kapi

    Strong Project Economics for Tulu Kapi TK Stats 100% Basis Open Pit + Start Underground Mine Open Pit Only and plant at nameplate but stay at nameplate Gold Price (US$/oz) 2,300 2,050 1,800 2,300 2,050 1,800 1,550 Production Statistics Tonnes Processed T 000 18,400 18400 18,400 15,395 15,395 15,395

  29. Slide 29: Tulu Kapi Mineral Resources & Ore Reserves

    Tulu Kapi Mineral Resources & Ore Reserves Resources - 1.72Moz of contained gold at 2.65g/t Resource Area Tonnes Gold Contained Gold Category (millions) (g/t) (Moz) Indicated Above 17.7 2.49 1.42 1,400m RL Inferred 1.3 2.05 0.08 Sub-Total 19.0 2.46 1.5 Indicated Below 1.1 5.63 0.20 1,400 RL Inferred

  30. Slide 30: AMAK – listed in Saudi Arabia

    AMAK – listed in Saudi Arabia Metrics vs GMCO . Illustrates the Saudi Mining Boom AMAK has similar but smaller deposits and has a Market Cap of US$1.6bn AMAK GMCO Copper-Gold Mine/Project Al Masane UG Hawiah OP + UG Mineral Resources 8.6Mt @ 1.0% Cu, 5.0% Zn, 1.0g/t Au, 38g/t Ag² 29Mt @ 0.89% Cu, 0.

  31. Slide 31: THANK YOU

    THANK YOU E: info@kefi-goldandcopper.com Kefiminerals KEFI Gold and Copper kefi-goldandcopper.com

KEFI Gold and Copper — Conference Presentation (September 2024) on 6ix