  1. Slide 1: Boral Teven Quarry 2015 Whole of Community Meeting

    Build something great™ ® Boral Teven Quarry 2015 Whole of Community Meeting 16 July 2015

  2. Slide 2: Agenda

    Build something great™ ® Agenda Boral Teven Quarry Whole of Community Meeting 16 July 2015  Welcome and introductions  Previous Community Consultative Committee (CCC) and matters arising  30 October 2014  Confirmation of CCC representatives 2015-17 and review of Terms of Reference  Quarry opera

  3. Slide 3: Boral personnel in attendance

    Build something great™ ® Boral personnel in attendance Boral Teven Quarry Whole of Community Meeting 16 July 2015  Richard Tomkins Operations Manager (NSW Country – North), Boral Quarries (NSW/ACT)  Matt Crosthwaite Quarry Manager, Boral Teven Quarry  Rod Johnson Environment Manager (NSW/ACT), Bo

  4. Slide 4: Previous CCC meeting & matters arising

    Build something great™ ® Previous CCC meeting & matters arising Boral Teven Quarry Whole of Community Meeting 16 July 2015  Previous meeting of the Community Consultative Committee (CCC)  30 October 2014  NOTE: Presentations and meeting notes from previous meetings are available from the quarry’s

  5. Slide 5: Community Consultation Committee 2015-17

    Build something great™ ® Boral Teven Quarry Community Consultation Committee 2015-17 Paul Jackson, Stakeholder Relations Manager (Southern Region)

  6. Slide 6: CCC Terms of Reference and membership 2015-17

    Build something great™ ® CCC Terms of Reference and membership 2015-17 Boral Teven Quarry Whole of Community Meeting 16 July 2015  The CCC Terms of Reference were endorsed at our last whole-of-community meeting held in March 2013.  Included in the Terms is a commitment by Boral to conduct an ‘admi

  7. Slide 7: CCC Terms of Reference and membership 2015-17

    Build something great™ ® CCC Terms of Reference and membership 2015-17 Boral Teven Quarry Whole of Community Meeting 16 July 2015  At the whole-of-community meeting of 19 May 2011, Boral committed to:  Staging a whole-of-community meeting every 18 to 24 months for all interested residents and stak

  8. Slide 8: Quarry operations update

    Build something great™ ® Boral Teven Quarry Quarry operations update Matt Crosthwaite, Quarry Manager – Boral Teven Quarry

  9. Slide 9: Operations overview

    ® Build something great™ Operations overview Boral Teven Quarry Whole of Community meeting 16 July 2015  Current projects  Highway upgrade – Pimlico to Teven  Highway upgrade – Tintenbar to Ewingsdale  Future projects  Highway upgrade – Woolgoolga to Ballina  Local projects  Internal supply t

  10. Slide 10: Site Improvements Program

    ® Build something great™ Site Improvements Program Boral Teven Quarry Whole of Community meeting 16 July 2015 Before cladding After cladding

  11. Slide 11: Site Improvements Program

    ® Build something great™ Site Improvements Program Boral Teven Quarry Whole of Community meeting 16 July 2015 Building 2 (Looking South) Buildings 1, 2 and 3 (Looking East) 11

  12. Slide 12: Site Improvements Program

    ® Build something great™ Site Improvements Program Boral Teven Quarry Whole of Community meeting 16 July 2015  Future Improvement Projects - Continuing weed management activities - Planting of native seedlings on small earth bund above ROM pad - Development and planting of earth bund near Beacons R

  13. Slide 13: Site Improvements Program

    ® Build something great™ Site Improvements Program Boral Teven Quarry Whole of Community meeting 16 July 2015  Argillite resource access and Argillite high wall stabilization and visual improvements in the long term

  14. Slide 14: Environmental management update

    Build something great™ ® Boral Teven Quarry Environmental management update Nathan Jeffery, HSE Advisor (Northern NSW)

  15. Slide 15: Site environmental management

    ® Build something great™ Site environmental management Boral Teven Quarry Whole of Community meeting 16 July 2015  Weed Control and Rehabilitation - Dec 2014 - 50 native seedlings planted on bund along North Teven Road south of main entrance (in addition to the 30 trees planted in the same location

  16. Slide 16: Site environmental management

    ® Build something great™ Site environmental management Boral Teven Quarry Whole of Community meeting 16 July 2015 Tree planting in Vegetation Corridor (Eastern Boundary) 1216 native seedlings planted in February and March 2015 Tree planting along North Teven Road South of main entrance 50 native see

  17. Slide 17: Site environmental management

    ® Build something great™ Site environmental management Boral Teven Quarry Whole of Community meeting 16 July 2015 Tree planting along North Teven Road (NW Corner) 178 native seedlings planted in March 2015 in addition to the 330 trees and grasses planted in October 2014 17

  18. Slide 18: Site environmental management

    ® Build something great™ Site environmental management Boral Teven Quarry Whole of Community meeting 16 July 2015 Native seedlings growing really well on earth bund in Basalt pit 1550 trees and grasses planted in October 2014 Native seedlings growing well on earth bund next to haul road in Basalt pi

  19. Slide 19: Environmental monitoring

    Build something great™ ® Boral Teven Quarry Environmental monitoring Nathan Jeffery, HSE Advisor (Northern NSW)

  20. Slide 20: Monitoring – Dust Deposition

    Build something great™ ® Monitoring – Dust Deposition Boral Teven Quarry Whole of Community meeting 16 July 2015 Averaging Period g/m2/montha Deposited Dustb Annual 4.00 a – Maximum total deposited dust level b – Dust is assessed as insoluble solids as defined by AS3580.10.1-1991 (AM-19) (At the nea

  21. Slide 21: Monitoring – Dust Deposition

    Build something great™ ® Monitoring – Dust Deposition Boral Teven Quarry Whole of Community meeting 16 July 2015 Annual Average Dust Deposition (Insoluble Solids) 1.27 g / m 2 / month 21

  22. Slide 22: Monitoring – Dust Deposition

    Build something great™ ® Monitoring – Dust Deposition Boral Teven Quarry Whole of Community meeting 16 July 2015 Annual Average Dust Deposition (Insoluble Solids) 1.91 g / m 2 / month 22

  23. Slide 23: Monitoring – Dust Deposition

    Build something great™ ® Monitoring – Dust Deposition Boral Teven Quarry Whole of Community meeting 16 July 2015 Annual Average Dust Deposition (Insoluble Solids) 5.71 g / m2 / month 23

  24. Slide 24: Monitoring – Dust Deposition

    Build something great™ ® Monitoring – Dust Deposition Boral Teven Quarry Whole of Community meeting 16 July 2015 Annual Average Dust Deposition (Insoluble Solids) 1.51 g / m 2 / month 24

  25. Slide 25: Monitoring – Water

    Build something great™ ® Monitoring – Water Boral Teven Quarry Whole of Community meeting 16 July 2015 Main surface water catchment dam at Boral Teven Quarry Water quality limits for Boral Teven Quarry from EPA Licence No 2261 25

  26. Slide 26: Monitoring – Blasting

    Build something great™ ® Monitoring – Blasting Boral Teven Quarry Whole of Community meeting 16 July 2015 Boral Teven Quarry Blast Limits; • Only 1 blast per day • Only blast between 9am to 4pm Monday to Friday • Vibration limits •5mm/s 95% •10mm/s 100% • Overpressure Limits • 115dB 95% • 120dB 100%

  27. Slide 27: Complaints Summary

    Build something great™ ® Complaints Summary Boral Teven Quarry Whole of Community meeting 16 July 2015  There have been two community complaints made since the meeting in October 2014 - 10/3/2015 – Residential Neighbour (S of Quarry) – Noise coming from bulldozer operating prior to 7am - Action: Al

  28. Slide 28: Re-examination of quarry consent

    Build something great™ ® Boral Teven Quarry Re-examination of quarry consent Rod Wallace, Planning & Development Manager (NSW)

  29. Slide 29: Re-examination of consent termination date

    ® Build something great™ Re-examination of consent termination date Boral Teven Quarry Whole of Community meeting 16 July 2015  Condition 24 of the 1996 development consent states:  These conditions shall be re-examined by Council and a final date for the termination of the consent determined with

  30. Slide 30: We sought your feedback on our operations

    ® Build something great™ We sought your feedback on our operations Boral Teven Quarry Whole of Community meeting 16 July 2015  The key issues raised which we could improve upon included  Operational noise  Dust emissions  Blasting  Road transport  Hours of operation  Significant capital has b

  31. Slide 31: Proposed consent re-examination and modification

    ® Build something great™ Proposed consent re-examination and modification Boral Teven Quarry Whole of Community meeting 16 July 2015  Production on Saturdays has been identified as a consistent amenity issue with neighbours.  We are proposing to cease production on Saturdays in exchange for the us

  32. Slide 32: Community activities and general business

    Build something great™ ® Boral Teven Quarry Community activities and general business Paul Jackson, Stakeholder Relations Manager (Southern Region)

  33. Slide 33: Community activities

    ® Build something great™ Community activities Boral Teven Quarry Whole of Community meeting 16 July 2015  Boral Teven Quarry has continued its program of supporting local community initiatives as part of its outreach to residents.  Continued support for the annual TinCAN Art Shows held in October

  34. Slide 34: General business

    ® Build something great™ General business Boral Teven Quarry Whole of Community meeting 16 July 2015  Items of general business  Next meeting of the Community Consultative Committee  Due by Sep-Oct 2015 (usually meet Mar and Sep)  Next whole-of-community meeting around Mar 2017  Other whole-of-

  35. Slide 35: Thank you for your attendance

    ® THANK YOU FOR YOUR ATTENDANCE ® Build something great™ Boral Teven Quarry – Whole of Community Meeting 16 July 2015

Boral — Corporate Update (July 2015) on 6ix