Endeavour Silver Corp. · TSX:EDR
Endeavour Silver — Technical Presentation (November 2026)
17 slides from Endeavour Silver's technical presentation, Nov 20, 2026
Slide 1: Pitarrilla Feasibility Study
Pitarrilla Feasibility Study A DVA N CI N G TOWA R D A C O N ST R U CT I O N D E C I S I O N NOVEMBER 20, 2026 TSX: EDR | NYSE: EXK edrsilver.com
Slide 2: Cautionary Note
Cautionary Note This presentation contains “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within applicable Canadian securities legislation. Such forward-looking statements and information herein
Slide 3: Non-IFRS Financial Measures
Non-IFRS Financial Measures The Company presents cash costs, mine-site all-in sustaining costs (AISC), EBITDA, free cash flow and capital measures in addition to conventional IFRS measures. These measures do not have standardized meanings under IFRS and may not be comparable with similarly described
Slide 4: Low-Cost Production Supporting Long-Term Growth
Low-Cost Production Supporting Long-Term Growth(1) 18-year planned mine life 4,000 tonnes per day (LOM) (tpd) design capacity Underground mine Large-scale, 100% producing silver-lead-zinc owned silver project concentrate Located in mining positive Low-cost mine with state of Durango, Mexico attracti
Slide 5: 18-Year Underground Operation with Substantial Silver Exposure
18-Year Underground Operation with Substantial Silver Exposure (1) $736M 16.37% 7.5 Moz After-tax NPV at 5% After-tax IRR Average annual silver equivalent (AgEq)(2) production 73% $585M $2,443M Revenue from silver Initial capital Operating cashflow Upside potential: Resource conversion, metallurgica
Slide 6: Feasibility Study Highlights
Feasibility Study Highlights (1) Planned average annual production of ~5.4 Moz of silver, 13 kt of Production lead, 29 kt of zinc and 7.5 Moz silver equivalent(2) Water use/discharge, explosives, land-use change, underground Permits mining, processing and development in place. Tailings Storage Facil
Slide 7: Underground Mine Plan Supports Capital Efficiency
Underground Mine Plan Supports Capital Efficiency (1) ~4,000 tpd Planned capacity from a mechanized, ramp-access underground mine ~16.7 km Total development 5.4 km 11.3 km Initial years Sustaining Mining Approach Primarily long-hole stoping, supplemented by development in ore. TSX: EDR | NYSE: EXK 7
Slide 8: Targeting Sulphide Mineralization
Targeting Sulphide Mineralization (1) Pitarrilla Cross Section Manto Pitarrilla • Underground exploration ramp lying directly above the manto • The mine plan is expected to target sulphide mineralization at • Cross cuts developed for underground drilling targeting veins to depth Manto Pitarrilla and
Slide 9: 18-Year Processing and AgEq Production
18-Year Processing and AgEq Production (1) 133.41 g/t 0.96% 2.27% 184.06 g/t LOM Ag Grade LOM Pb Grade LOM Zn Grade LOM AgEq(2) Grade Silver-equivalent production (million oz AgEq) 2.0 10.0 Tonnes processed (million tonnes) 1.6 8.0 1.2 6.0 0.8 4.0 0.4 2.0 Mine year 0.0 0.0 1 2 3 4 5 6 7 8 9 10 11 12
Slide 10: Processing Flowsheet
Processing Flowsheet (1) Estimated life-of-mine recoveries 91% 96% 91% Ag Pb Zn Concentrates Thicken and filter to remove water Crushing Stockpile SAG mill Ball mill Flotation Break ore into Store crushed Primary Grind ore into Separate valuable smaller pieces ore grinding fine particles minerals fr
Slide 11: Operating Cost Profile
Operating Cost Profile(1) LOM Operating Costs Mining $44.37 $ Million Process $30.97 Mining Costs $1,190 Process Costs $777 G&A $10.25 G&A Costs $268 TC/RCs $8.87 Direct Operating Costs $2,235 Royalty - NSR $2.91 Treatment and Refining Charges (TC/RCs) $222 Royalty - Government $1.77 Royalty - Third
Slide 12: Resilient Project Economics Across Range of Price Scenarios
Resilient Project Economics Across Range of Price Scenarios (1) After-Tax NPV (5%) and IRR Sensitivity to Silver Price Silver Price (US$/oz) After-tax IRR 1500 $1,205 $30 7.00% $1,049 $35 9.62% After-Tax NPV (5%) 1000 $893 $40 12.03% $736 $580 $45 14.26% 500 $423 $50* 16.37% $266 $55 18.39% $109 0 $
Slide 13: Advancing Engineering and Outstanding Approvals
Advancing Engineering and Outstanding Approvals(1) IN PLACE UNDERWAY OUTSTANDING • Water use and discharge • Detailed engineering • Finalize and file NI 43-101 within 45 days • Explosives • Procurement planning and optimization • TSF approval • Land-use change • Underground mining and development Co
Slide 14: Opportunities to Enhance Value
Opportunities to Enhance Value (1) Resource Conversion and Mine-Life Extension Metallurgical Evaluation • Upgrade Inferred Resources through targeted drilling to expand • 18.4 Mt of transition zone resources are excluded from the feasibility future mine plans. study mine plan. • Current plan uses a
Slide 15: Q&A
Q&A Plant Site Tailings Site Underground mine producing silver-lead-zinc concentrate Located in mining positive state of Durango, Mexico TSX: EDR | NYSE: EXK 15 ¹ See “Technical Disclosures”
Slide 16: Mineral Reserves and Resources
Mineral Reserves and Resources (1) Pitarrilla Deposit In-Pit (oxide) and Underground Below-Pit (Transition and Sulphide) Mineral Resource Estimate, Effective Date November 1, 2025 Cut-Off Resource Grade Contained Metal Domain/Area MTonnes (AgEq) Class Ag (g/t) Pb (%) Zn (%) AgEq (g/t) Ag (Moz) Pb (M
Slide 17: Technical Disclosures and Cautionary Statements
Technical Disclosures and Cautionary Statements The Mineral Resource Estimate was prepared by the following qualified persons. Allan Armitage, Ph.D., P.Geo., of SGS Geological Services. Dr. Armitage completed site visits to the Project on April 14 and 15, 2024, September 23 and 24, 2025 and again on