  1. Slide 1: Hastings Project Process Development – Past and Present

    Hastings Project Process Development – Past and Present For personal use only • Mackowski, S. (Hastings Rare Metals Ltd, Level 9, 50 Margaret Street, Sydney, NSW 2000) • Collier, D., Soldenhoff, K. and Griffith, C. (Australian Nuclear Science and Technology Organisation, New Illawarra Road, Lucas He

  2. Slide 2: Agenda

    For personal use only  Project location and history  Historical process development  Mineralogy  Sulphation bake/leach + materials handling  Primary separation – Zr/Nb & REE & impurity rejection  Downstream processing – Zr, Nb & REE concentrates Hastings Project Process Development – Past and

  3. Slide 3: Largest heavy rare earth project in Australia

     Largest heavy rare earth project For personal use only in Australia (>35% HREO:TREO)  Resources for +25y @ 1 Mt/a  ~10,000 t REO + RMO/a projected  Past process development/initial piloting  Favourable infrastructure Hastings Project Process Development – Past and Present – Critical Minerals 2

  4. Slide 4: +25y mine life with existing resources

     +25y mine life with existing resources (@ 1 Mt/a) For personal use only  36.2 Mt Indicated and Inferred JORC resources at 0.21% TREO (0.18% HREO) including 0.35% Nb2O5 and 0.89% ZrO2 (comprises 27.1+9.1 Mt) Hastings Project Process Development – Past and Present – Critical Minerals 2013

  5. Slide 5: Open cut scenario

    For personal use only  Open cut scenario  Minimal over-burden Longitudinal section from the east Surface  Consistent grade  Extended ore body N&S  Open to N&S and at depth Surface HREO GRADE Viewed from the south Hastings Project Process Development – Past and Present – Critical Minerals 2013

  6. Slide 6: Historical process development: Warren Springs Laboratory

    For personal use only  Warren Springs Laboratory (WSL) - 1987–1990 conducted as the “Brockman Project” for West Coast Holdings  Process Development work included:  Mineralogy  Beneficiation  Grinding assessment  Definition of bake/leach flow sheet  Mini-plant of bake/leach trials  ANSTO role

  7. Slide 7: Pilot-plant, batch test work and potential approaches

    For personal use only Pilot-plant Batch Test Work Potential Approaches Defined Hastings Project Process Development – Past and Present – Critical Minerals 2013

  8. Slide 8: Ore mineralogy studies 2011–2013

    For personal use only  Multiple ore mineralogy studies (2011 – 2013) using QEMSCAN/SEM/XRD  Predominant gangue - quartz, muscovite and albite  REE mainly associated with columbite and ‘gel-zircon’  Nb/Zr associated with columbite & titanian samarskite  Complex, multi-phase assemblages comprisin

  9. Slide 9: Ore mineralogy: valuable minerals

    Ore Mineral Chemical Formula For personal use only (~wt%) Columbite FeNb2O6 0.3 Titanian Samarskite-Y YFe3+(Nb,Ti)2O8 minor Cerianite-Ce (Ce4+,Th)O2 minor REE Minerals (Ce,La,Nd,Y,Yb,Nb)(PO4/oxide) 0.2  Fine grain size  Beneficiation  Diverse reactivities Hastings Project Process Development – Pa

  10. Slide 10: Ore mineralogy: gangue minerals

    For personal use only  ↑muscovite – historical focus as Al project  Bake/leach flow sheet handles ↑Si Ore Mineral Chemical Formula (~wt%) Quartz SiO2 45 Muscovite KAl2(Si3Al)O10(OH,F)2 25 Alkali Feldspar KAlSi3O8 4 Biotite K(Mg,Fe)3[AlSi3O10(OH,F)2] 3 Fluorite CaF2 3 Albite NaAlSi3O8 11 Hornblende

  11. Slide 11: Major Australian projects: rare earth distribution

    For personal use only  Major Australian projects  Different RE distribution*  Reflects HRE mineralisation *Boynton, V.W. (1985) Chapter 3. Cosmochemistry of the rare earth elements: Meteorite studies, In Rare Earth Element Geochemistry (P. Henderson, ed.), (Developments in Geochemistry 2), pp. 11

  12. Slide 12: ANSTO test work programs 2011–2013

    For personal use only  Number of test work programs undertaken and completed by ANSTO Minerals from 2011 – 2013 examining:  Critical assessment of historical lab and piloting data  Mineralogy and ore variability  Optimisation of H2SO4 bake/leach  Identification of target areas for improvement 

  13. Slide 13: Bake/leach test work

    For personal use only 417 kg/t 560 kg/t 590 kg/t 619 kg/t 762 kg/t Post Bake Fluidised Bed Reactor Rotary Kiln Agglomeration Hastings Project Process Development – Past and Present – Critical Minerals 2013

  14. Slide 14: Redefined flow sheet and bake/leach optimisation

     Redefined flow sheet to reflect emphasis For personal use only on REE and Zr/Nb not Al (‘Brockman’ focus)  Optimisation of H2SO4 bake/leach Bake Grind – P80 ≤20 µm Acid addition – 750 kg/t Temperature – 275oC Duration – 1 h Leach Density – ≤3 L/kg ore Temperature – 80oC Duration – 1 h Hastings Pr

  15. Slide 15: Extraction results and mineralogy influence

    For personal use only  Locked-in gel zircon and niobates prevail  Possible further scope for grind optimisation  Muscovite dissolution  Clear influence of mineralogy Hastings Project Process Development – Past and Present – Critical Minerals 2013

  16. Slide 16: Solvent extraction: impurity rejection

    For personal use only Defined by optimisation results  Al/Fe rejection KEY in SX  Co-extraction of RE  Critical assessment of approach in context of downstream processing Hastings Project Process Development – Past and Present – Critical Minerals 2013

  17. Slide 17: Solvent extraction: iron reduction and loading

     FeIII reduction in PLS via FeO or SO2 feasible For personal use only  Loading of Zr/Nb AND REE not appropriate Hastings Project Process Development – Past and Present – Critical Minerals 2013

  18. Slide 18: Two Stage solvent extraction

     Development of ‘Two Stage’ SX For personal use only  No ‘trade-offs’ w.r.t. Zr/Nb vs RE  Achieves ‘bulk’ impurity rejection  Compliments downstream approaches  Optimisation studies on-going Hastings Project Process Development – Past and Present – Critical Minerals 2013

  19. Slide 19: Targets for ongoing process development

     Targets for on-going process development programs: For personal use only → Complete definition of Zr/Nb SX → Better define Zr/Nb downstream processing → Critically assess alternative to Y+REE SX → Better define Y+REE downstream processing Hastings Project Process Development – Past and Present – C

  20. Slide 20: Conclusions

    For personal use only  Complex mineralogy – challenging process development  Opportunities remain for optimisation of front-end (ore → PLS)  SX (Primene JMT) appropriate for Zr/Nb + Al/Fe rejection  ‘Two Stage’ SX current baseline approach  Alternative Y+REE primary separations worthy of invest

  21. Slide 21: Hastings Project Process Development

    For personal use only Hastings Project Process Development – Past and Present – Critical Minerals 2013