Robyg S.A. · GPW:ROB
Robyg — Q1 2021 Earnings Presentation
57 slides from Robyg's earnings presentation, May 2021

Slide 1: Financial Results Q1 2021
FINANCIAL RESULTS Q1 2021 Warsaw, May 2021

Slide 2: Agenda
AGENDA PART 01 Summary PART 02 Presales and revenue’s perspective PART 03 Financial results PART 04 Plans of ROBYG Group PART 05 Sustainable Growth PART 06 Appendices

Slide 3: Part 01 Summary
ROBYG PART 01 Summary Q1 2021

Slide 4: Summary Q1 2021
01. Summary Q1 2021 Summary Q1 2021 Operating cash flow: Revenues: Strong cash position: PLN 143 million PLN 246 million PLN 441 million (excl. purchase of new plots) 4

Slide 5: Summary Q1 2021 – units
01. Summary Q1 2021 Summary Q1 2021 Units recognized in revenue: 563 Developer agreements concluded: Units presold: 1 110 Units completed and not 888 (net after cancellations) (net after cancellations) recognized: 322 (incl. 235 presold) Units on sale which construction has not Number of units under

Slide 6: Material investings and financial activities
01. Summary Q1 2021 ROBYG Group – material investings and financial activities Total new financing: Total value of signed agreements: PLN 100 million ca. PLN 341 million NEW PLOTS NEW PLOTS FINANCING Warsaw Gdynia ROBYG S.A. – proceeds from the Total expected potential Total expected potential share

Slide 7: Land acquisition value
01. Summary Q1 2021 ROBYG Group – land acquisition value Total value of signed agreements: ca. PLN 341 million Area of plots Type of Potential of sellable Locations [ha] contracts area [sqm] 1.6 Final 17 000 Warsaw, Mokotow 2.2 Final 42 000 Gdynia 11.9 Preliminary 109 400 Warsaw 15.7 RAZEM 168 400 7

Slide 8: Part 02 Presale & revenue perspective
PART 02 Presale & revenue perspective

Slide 9: Presale structure – quarterly units
02. Presales & revenue’s perspective ROBYG Group – presale structure Presale in Q1 2021: 1 110 units (+75% 1Q21/1Q20), PLN 500 million (+95% 1Q21/1Q20) Net number of presold units (quarterly) 1110 75% 776 755 716 633 606 459 162 Q2 2019 Q3 2019 Q4 2019 Q1 2020 Q2 2020 Q3 2020 Q4 2020 Q1 2021 9

Slide 10: Presale structure – annual units
02. Presales & revenue’s perspective ROBYG Group – presale structure Presale in Q1 2021: 1 110 units (+75% 1Q21/1Q20), PLN 500 million (+95% 1Q21/1Q20) Net number of presold units (annually) 17% 3471 -27% 27% 2957 2% 10% -16% 2738 2520 2569 22% 2333 2118 2156 56% 1731 9% 1019 1113 1110 888 2011 2012

Slide 11: Presale structure by city
02. Presales & revenue’s perspective ROBYG Group – presale structure Presale in Q1 2021: 1 110 units (+75% 1Q21/1Q20), PLN 500 million (+95% 1Q21/1Q20) Wroclaw 14% 150 units Gdansk 46% 510 units Warsaw 40% 450 units 11

Slide 12: Units on offer
02. Presales & revenue’s perspective ROBYG Group – units on offer FINISHED GOODS ON OFFER: 3% 2492 2091 2021 87 * 1683 1714 94 179 42 66 2405 1997 1842 1641 1648 1Q 2020 2Q 2020 3Q 2020 4Q 2020 1Q 2021 Units under construction** Units completed * The offer is decreased by 19 commercial units which a

Slide 13: Revenue recognition
02. Presales & revenue’s perspective ROBYG Group – revenue recognition (as at 31 March 2021) Recognition potential of units in revenues Number of units recognized in revenues (quarterly) Units not presold and not recognized: 2 492 1840 Completed: 87 1453 Under construction: 1 909 Which construction

Slide 14: Coronavirus Disease (COVID-19)
02. Presales & revenue’s perspective Coronavirus Disease (COVID-19) As of the date of these presentation the Group has been conducting its regular operating activity with no significant disruptions. Due to the high level of uncertainty, the Management is currently unable to assess the further influe

Slide 15: Units to be completed in 2020-2022
02. Presales & revenue’s perspective Number of units to be completed in 2020-2021 and also (contracted) until 31 March 2021 Note: Due to uncertainty pertained to the spreading of Coronavirus disease (COVID-19), Total & Presold 2020 2021 2022 estimation of the completed investments may materially cha

Slide 16: Units to be completed in 2021
02. Presales & revenue’s perspective Number of units to be completed in 2021* Gdansk Warsaw Wroclaw Total no. of units to be Total no. of units to be Total no. of units to be Project Project Project completed in 2021 completed in 2021 completed in 2021 Lawendowe Wzgórze / Osiedle Życzliwa 442 143 Ja

Slide 17: Units to be completed in 2022
02. Presales & revenue’s perspective Number of units to be completed in 2022* Gdansk Warsaw Wroclaw Total no. of units to be Total no. of units to be Total no. of units to be Project Project Project completed in 2022 completed in 2022 completed in 2022 Lawendowe Wzgórze / Osiedle Życzliwa 130 300 Ja

Slide 18: Part 03 Financial results
ROBYG PART Financial results

Slide 19: Estimated financial results
03. Estimated financial results Estimated financial results (PLNk) Q1 2021 Q1 2020 Change Revenues 244 995 177 863 37.7% Cost of sales (171 228) (134 241) 27.6% Gross profit on sales 73 767 43 622 69.1% Selling and marketing expenses (8 192) (6 658) 23.0% Administrative expenses (11 324) (9 452) 19.

Slide 20: Estimated financial condition
03. Estimated financial results Estimated financial condition (PLNk) Q1 2021 Q1 2020 Change 2020 Total assets, including: 2 671 928 2 700 155 (1.0%) 2 573 916 Non-current assets, including: 503 988 381 813 32.0% 498 993 Investment properties and investment properties under 345 022 243 121 41.9% 339

Slide 21: Estimated statement of cash flow
03. Estimated financial results Estimated statement of cash flow (PLNk) Q1 2021 Q1 2020 Net cash flows from operating activities, including: 82 795 (63 844) Expenditures for the purchase of new plots (60 211) (149 691) Net cash flows from investing activities (2 172) (25 980) Expenditures for the pu

Slide 22: Debt financing
03. Estimated financial results Debt financing Nominal value and maturity of bank credit facilities and bonds as at March 31st, 2021 (PLNm). DEBT – Aging <1 year 1-2 years 2-3 years 3-4 years 4-5 years Over 5 years Total BANK CREDIT FACILITIES 0.01 5.42 0.06 0.00 0.00 0.00 5.49 BONDS 45.30 300.00 60

Slide 23: Leverage and collections
03. Estimated financial results Leverage and collections as at March 31st, 2021 * Net debt ratio= net debt ** / equity ** Net debt = interest bearing liabilities + derivatives + guarantees granted – intercompany loans – cash and cash equivalents – amounts kept on individual Net debt ratio_1* = 0.11

Slide 24: Dividend
03. Dividend Dividend Dividend for 2020: Management Board recommends retaining the standalone net profit of ROBYG S.A. for the year ended 31 December 2020 as reserve capital. Dividend for 2019: The Ordinary General Meeting of ROBYG S.A. retained the standalone net profit of ROBYG S.A. for the year e

Slide 25: Part 04 Plans of ROBYG Group
ROBYG a =) Oo Se O 9 [aa] O ce = o} wn <c & a

Slide 26: Strategic goals
04. Plans of ROBYG Group Strategic goals Number of presold units in 2021 ca. 3.500 units Increase of the net profit Maintaining the margins Maintaining the adequate level of the land bank Expansion of activities in Wroclaw and Poznan 26

Slide 27: Total land bank
04. Plans of ROBYG Group Total land bank 19 420 units + 2 492 units on offer = 21 912 units Gdansk / Gdynia Warsaw Wroclaw Poznan District Number of units % District Number of units % District Number of units % District Number of units % Nowy Port 1 045 16% Mokotów / Czerniaków 1 130 13% Krzyki 590

Slide 28: Commercial potential
04. Plans of ROBYG Group Commercial potential = 88 000 sqm of usable area Commercial potential = 88 000 sqm of usable area GDANSK WROCLAW POZNAN 18 000 35 000 35 000 TOTAL: 88 000 sqm 28

Slide 29: Part 05 Sustainable growth
PART 05 Sustainable growth ROBYG FOR SOCIETY AND ENVIRONMENT

Slide 30: Mission, philosophy, actions
05. SUSTANABLE GROWTH FOR SOCIETY AND ENVIRONMENT MISSION PHILOSOPHY ACTIONS “Our mission is to inspire others to work CARE together, to fulfil the vision of a sustainable The protection of natural resources and care for the environment are very important to us, hence world for our common, better fu

Slide 31: Our projects
05. SUSTAINABLE GROWTH OUR PROJECTS We design and construct our buildings with care for the environment and the comfort of users. Solutions that we use across our projects include: GREEN AREAS RESIDENTS’ AMENITIES BUILT FOR PEOPLE When designing our housing estates, we plan green areas in a responsi

Slide 32: Our projects – green solutions
05. SUSTAINABLE GROWTH OUR PROJECTS 52 ha - total amount 600 km - fibre optic 2000 sq.m. - photovoltaic 35 floors - number of green areas in the currently provided panels installed of floors with rain gardens running projects Green roofs in 41 floors, total 40 000 - LED luminaires Triple pane window

Slide 33: Social responsibility and pandemic support
05. SUSTAINABLE GROWTH For us, corporate social responsibility is an opportunity to build a better future. We have supported numerous foundations and projects, such as: „Trzeba Marzyć” Foundation and the Pomeranian Hospice for Children, 2nd. Family Run Time for Sight, The Marathon Foundation for the

Slide 34: Local contractors, employees, transparency
05. SUSTAINABLE GROWTH SUPPORT FOR LOCAL CONTRACTORS AND PRODUCERS FOR THE SAKE OF OUR EMPLOYEES We want to support local companies and our neighbours. We want to build not only housing estates We care about the safety of our employees. We provide them with ergonomic workplaces, and but also relatio

Slide 35: Commitment to sustainable growth
05. SUSTAINABLE GROWTH All of us at Robyg acknowledge how important sustainable growth is for the envirnomnent and society. So far we have done a lot, but we treat this is a journey that will involve over time. Thus, we are committed to continuing our work to constantly improve our performance and d

Slide 36: Part 06 Appendices
ROBYG PART Appendices

Slide 37: ROBYG - Team
06. Appendices ROBYG - Team Oscar Kazanelson Zbigniew Wojciech Okoński Chairman of the Supervisory Board President of the Board 37

Slide 38: ROBYG - Team
06. Appendices ROBYG - Team Eyal Keltsh Artur Ceglarz Wojciech Gruza Vice-President of the Board, COO Vice-President of the Board, Vice-President of the Board, Business Development Head of Legal Department 38

Slide 39: Ownership structure
06. Appendices Ownership structure As at the date of this presentation, Bricks Acqusition Limited holds 100% of ROBYG S.A. shares. Goldman Sachs Group, Inc indirectly holds majority of shares in Bricks Acquisition Limited. 39

Slide 40: Investments under construction (1)
06. Appendices Description of investments – under construction (1) Lawendowe Wzgórza / Osiedle Kamerlne Osiedle Kameralne II Stacja Nowy Gdansk City: Gdansk City: Warsaw City: Warsaw District: Jasień District: Bemowo District: Bemowo No. of stages: ca. 34 No. of stages: 5 No. of stages: 3 Stages com

Slide 41: Investments under construction (2)
06. Appendices Description of investments – under construction (2) Nowa Letnica Young City 2 City: Gdansk City: Warsaw District: Letnica District: Bemowo No. of stages: 15 No. of stages: 6 Stages completed: 10 Stages completed: 1 Stages under construction: 3 Stages under construction: 1 No. of units

Slide 42: Investments under construction (3)
06. Appendices Description of investments – under construction (3) Zajezdnia Wrzeszcz City Sfera Modern City City: Gdansk City: Warsaw City: Warsaw District: Wrzeszcz District: Włochy District: Bemowo No. of stages: 14 No. of stages: 13 No. of stages: 9 Stages completed: 10 Stages completed: 2 Stage

Slide 43: Investments under construction (4)
06. Appendices Description of investments – under construction (4) Jagodno Osiedle Życzliwa Praga Nadmotławie Estate City: Wroclaw City: Warsaw City: Gdansk District: Krzyki District: Tarchomin District: Śródmieście No. of stages: 9 No. of stages: 7 No. of stages: 12 Stages under construction: 5 Sta

Slide 44: Investments under construction (5)
06. Appendices Description of investments – under construction (5) Moment Park Południe Apartamenty Królewskie City: Gdansk City: Gdansk City: Warsaw District: Ujeścisko District: Łostowice District: Wilanów No. of stages: 2 No. of stages: 9 No. of stages: 2 Stages completed: 1 Stages completed: 3 S

Slide 45: Investments under construction (6)
06. Appendices Description of investments – under construction (6) Więcej Mój Ursus Lagom City: Gdansk City: Warsaw City: Gdansk District: Łostowice District: Ursus District: Ujeścisko No. of stages: 2 No. of stages: 8 No. of stages: 1 Stages under construction: 1 Stages under construction*: 5 Stage

Slide 46: Investments under construction (7)
06. Appendices Description of investments – under construction (7) Willa Nad Potokiem Wojszyckie Alejki Uroczysko City: Wroclaw City: Wroclaw City: Wroclaw District: Fabryczna District: Krzyki District: Psie Pole No. of stages: 1 No. of stages: 3 No. of stages: 2 Stages under construction: 1 Stages

Slide 47: Investments under construction (8)
06. Appendices Description of investments – under construction (8) Praga Deco Młode Stogi Porto City: Warszawa City: Gdansk City: Gdańsk District: Praga Południe District: Stogi District: Nowy Port No. of stages: 1 No. of stages: 2 No. of stages: 10 Stages under construction: 1 Stages under construc

Slide 48: Investments under construction (9)
06. Appendices Description of investments – under construction (9) Szumilas City: Gdańsk (Kowale) No. of stages: 1 Stages under construction: 1 No. of units: ca. 930 units Total sellable area: ca. 47,4k sqm Start of construction: Q1 2021 Planned completion date: Q2 2027 48

Slide 49: Investments completed (1)
06. Appendices Description of investments – completed (1) Szczęśliwy Dom Osiedle Zdrowa Nowa Rezydencja Królowej Marysieńki City: Warsaw City: Warsaw City: Warsaw District: Ochota District: Wilanów District: Wilanów No. of stages: 3 No. of stages: 5 No. of stages: 10 No. of units: 304 units No. of u

Slide 50: Investments completed (2)
06. Appendices Description of investments – completed (2) City Apartments Osiedle Królewskie Albatross Towers City: Warsaw City: Warsaw City: Gdansk District: Żoliborz District: Wilanów District: Przymorze No. of stages: 6 No. of stages: 6 No. of stages: 5 No. of units: 1 190 units No. of units: 640

Slide 51: Investments completed (3)
06. Appendices Description of investments – completed (3) Królewski Park Park Wola Residence Modern Żoliborz City: Warsaw City: Warsaw City: Warsaw District: Wilanów District: Wola District: Żoliborz No. of stages: 6 No. of stages: 1 No. of stages: 1 No. of units: 528 units No. of units: 317 units N

Slide 52: Investments completed (4)
06. Appendices Description of investments – completed (4) Young City Młody Wilanów Mila Baltica City: Warsaw City: Warsaw City: Gdansk District: Bemowo District: Wilanów District: Zaspa No. of stages: 9 No. of stages: 3 No. of stages: 2 No. of units: 1 302 units No. of units: 257 units No. of units:

Slide 53: Investments completed (5)
06. Appendices Description of investments – completed (5) Apartamenty Villa Nobile Słoneczna Morena MoreNova City: Warsaw City: Gdańsk City: Gdansk District: Wilanów District: Piecki-Migowo District: Piecki-Migowo No. of stages: 3 No. of stages: 22 No. of stages: 3 No. of units: 637 units No. of uni

Slide 54: Investments completed (6)
06. Appendices Description of investments – completed (6) Ogrody Wilanów Green Mokotów Stacja Nowy Ursus City: Warsaw City: Warsaw City: Warsaw District: Wilanów District: Mokotów District: Ursus No. of stages: 3 No. of stages: 9 No. of stages: 5 No. of units: 221 units No. of units: 673 units No. o

Slide 55: Investments completed (7)
06. Appendices Description of investments – completed (7) Forum Wola Praga Arte Leśna Przystań City: Warsaw City: Warsaw City: Wroclaw District: Wola District: Praga Południe District: Psie Pole No. of stages: 4 No. of stages: 1 No. of stages: 1 No. of units: ca. 880 units No. of units: ca. 250 unit

Slide 56: Summary Q1 2021
Summary Q1 2021 Number of signed developer agreements: 1 110 (net after cancellations) Please contact us: Investor Relations ROBYG S.A. ri@robyg.com.pl Number of concluded development agreements: 888 (22) 419 11 00 Number of recognized in revenues: 563 Units on offer: 2 492 (out of which 3% finished

Slide 57: Disclaimer
Disclaimer ROBYG S.A. endeavours to ensure that the information in the presentation is complete and up-to-date, however, we do not make any guarantees in this respect. ROBYG S.A accepts no liability for the any errors and inaccuracies of this presentation. This presentation has been prepared solely
Source: company website
More decks from Robyg S.A.
H1 2026 Earnings Presentation63 slides · September 2026
H1 2026 Earnings Presentation63 slides · September 2026
Investor Presentation (August 2026)57 slides · August 2026
Q1 2026 Earnings Presentation64 slides · June 2026
Investor Presentation (May 2026)113 slides · May 2026
FY2025 Earnings Presentation63 slides · March 2026