Kinder Morgan, Inc. · NYSE:KMI

Kinder Morgan — Kinder Morgan 2011 Analyst Conference

29 slides from Kinder Morgan's conference presentation, Mar 24, 2011

  1. Slide 1: Natural Gas Pipelines

    Natural Gas Pipelines Tom Martin President Natural Gas Pipeline Group

  2. Slide 2: Overview

    Overview Market Environment  Shale activity providing excellent growth opportunities  Transport spreads remain flat  Storage spreads softer in short-term  Processing margins continue to be very strong and roughly equivalent to 2010 performance Value Proposition  Strong asset base with secure ca

  3. Slide 3: Natural Gas Pipelines and Facilities

    Natural Gas Pipelines and Facilities 3

  4. Slide 4: Financial Overview

    Financial Overview ($ in millions) ‘10-‘11 2006 2007 2008 2009 2010 2011B Change EBDA (a) $501.1 $548.4 $738.9 $825.4 $932.2 $1,034.5 $102.3 Sustaining Capex (27.4) (29.9) (29.9) (22.7) (17.5) (28.8) (11.2) DCF $473.7 $518.5 $709.0 $802.7 $914.7 $1,005.7 $91.0 10% 2011 Highlights:  FEP project in f

  5. Slide 5: Contracted Capacity and Term

    Contracted Capacity and Term Contracted Avg. Term Capacity Remaining Interstate KM Interstate Gas Storage 10.7 Bcf 3 yr, 11 mo Transport 0.9 Bcf/d 4 yr, 5 mo TransColorado Transport 1.0 Bcf/d 5 yr, 2 mo Trailblazer Transport 1.0 Bcf/d 4 yr, 7 mo Transport Contracts Rockies Express Transport 1.8 Bcf/

  6. Slide 6: Asset Summaries

    KINDER/MORGAN Asset Summaries

  7. Slide 7: Rockies Express Pipeline (REX)

    Rockies Express Pipeline (REX) REX  1,679 miles of 36” and 42” pipeline  Originates in Meeker, CO and terminates in Clarington, OH  Transports Rocky Mountain production to premium Northeast markets  JV between KMP (50%), Sempra (25%) and ConocoPhillips (25%); KMP operates  Capacity = 1.8 Bcf/d

  8. Slide 8: REX Opportunities and Challenges

    REX Opportunities and Challenges Opportunities  200,000 Dth/d Meeker to Cheyenne expansion — Fully-subscribed — Leg one, in-service December 2009 — Leg two, in-service October 2010 — 40% below original cost estimate  Park & loan service  Interruptible and short haul service (ITS, PAWS)  Extensio

  9. Slide 9: Kinder Morgan Interstate Gas Transmission (KMIGT)

    Kinder Morgan Interstate Gas Transmission (KMIGT) KMIGT  4,500 miles of various diameter pipelines  Markets: — LDCs, industrials, & ag. in NE, KS, & MO — Marketers transporting to mid-continent pipelines — End users including ethanol plants  Growth — Storage — Colorado lateral  Capacity — Transp

  10. Slide 10: KMIGT Opportunities and Challenges

    KMIGT Opportunities and Challenges Opportunities  Huntsman storage expansion — 10,000 Dth/d incremental firm storage service — Started service with shipper on February 1, 2010 under long-term binding contract — Phase I construction completed December 2009 — Phase II construction completed 3rd quart

  11. Slide 11: TransColorado Gas Transmission

    TransColorado Gas Transmission TransColorado  301 miles of 22” & 24” pipeline  Originates at Greasewood, CO and terminates at Blanco, NM  Bi-directional Flow — Capacity north - 650 MDth/d — Capacity south • Phase I - 150 MDth/d • Phase II - 425 MDth/d  FERC-regulated 11

  12. Slide 12: TransColorado Opportunities and Challenges

    TransColorado Opportunities and Challenges Opportunities  Completed project with Enterprise to transport Greasewood gas directly to Enterprise plant — Project supported by long-term binding contract  Year-on-year drilling rig count and production volumes have improved in the Piceance Basin — Jan-M

  13. Slide 13: Trailblazer Pipeline

    Trailblazer Pipeline Trailblazer  436 miles of pipe  3 compressor locations with 58,000 HP  Max throughput = 0.878 Bcf/d  Low cost pipeline out of region  Long-term contracts  FERC-regulated  No rate case filing obligation until 2014 13

  14. Slide 14: Trailblazer Pipeline Update

    Trailblazer Pipeline Update  Settlement with customers deferred rate case obligation from December 2009 to January 2014  Trailblazer provided a rate reduction for most shippers in 2010 and an additional reduction beginning January 2011  Settlement reduced demand revenues for 2011 by $3.8MM (less

  15. Slide 15: Midcontinent Express Pipeline (MEP)

    Midcontinent Express Pipeline (MEP) MEP  507 miles of 42”, 36” and 30” pipe  Originates at Enogex, Bennington and terminates at Transco Station 85  Capacity: — Zone 1: 1.8 Bcf/d — Zone 2: 1.2 Bcf/d  JV between KMP (50%), Regency (49%) and Energy Transfer (1%); KMP operates  Pipeline fully-subsc

  16. Slide 16: MEP Expansion Progress and Commercial Opportunities

    MEP Expansion Progress and Commercial Opportunities  Expansions fully in-service mid-year 2010 and below budget — Zone 1 400 MDth/d • 100 MDth/d – May 1, 2010 (pre-approved capacity) • 300 MDth/d – June 1, 2010 (expansion capacity) — Zone 2 200 MDth/d – June 2010  Zone 2 expandability (up to 300 M

  17. Slide 17: Kinder Morgan Louisiana Pipeline (KMLP)

    Kinder Morgan Louisiana Pipeline (KMLP) KMLP  133 miles of 42” pipe  Originates at Cheniere Sabine pass LNG and interconnects with 12 interstate pipelines  Two storage fields connected to pipeline  Capacity: 3.2 Bcf/d  Pipeline fully-subscribed with 20-year contacts  FERC-regulated 17

  18. Slide 18: Kinder Morgan Louisiana Pipeline Commercial Opportunities

    Kinder Morgan Louisiana Pipeline Commercial Opportunities  Multiple interconnections – with additional facilities, may capture opportunities between major interstate pipelines and storage  Potential interconnections with other LNG terminals  Opportunity to transport supply for LNG export  Opport

  19. Slide 19: Fayetteville Express Pipeline (FEP)

    Fayetteville Express Pipeline (FEP) FEP  185 miles of 42” pipe  One compressor station with 72,000 HP  Capacity: 2.0 Bcf/d  15 receipt points (producer specific)  4 delivery meters  JV between KMP (50%) and Energy Transfer (50%); Energy Transfer operates  1.85 Bcf/d capacity under long-term c

  20. Slide 20: FEP Update

    FEP Update  Pipeline, meter and compression construction completed; clean-up, right-of-way restoration and minor facilities work such as painting continue — 2.0 Bcf/d of initial pipeline capacity — Project costs projected at $0.98 billion, substantially less than original estimate of $1.26 billion

  21. Slide 21: Natural Gas Pipeline Company of America (NGPL)

    KMI (20% Ownership) Natural Gas Pipeline Company of America (NGPL) NGPL  Pipeline miles: 9,200  KM-operated  Market area deliverability: 5.0 Bcf/d  Storage working gas capacity: 278 Bcf (8 fields)  Direct or one-pipe-away access to most major U.S. and Canadian supply basins west of the Mississi

  22. Slide 22: KinderHawk Field Services (KHFS)

    KinderHawk Field Services (KHFS) KHFS 50/50 joint venture with PetroHawk in northwest Louisiana  Gathering and treating services for Haynesville/Bossier Shale  365.5 miles of pipe installed to date  Over 2 Bcf/d of capacity  Well-positioned to access over 20 Tcf of gas  2,160 GPM of treating ca

  23. Slide 23: KinderHawk Field Services Commercial Opportunities

    KinderHawk Field Services Commercial Opportunities  PetroHawk gathering agreement — Life of lease dedication — Agreed upon gathering and treating rates — Increasing minimum volume commitment for 5 years  Third party agreements — Secured new third party gas gathering and treating transactions in 20

  24. Slide 24: Texas Intrastate Pipelines

    Texas Intrastate Pipelines Texas Intrastates  6,000 miles of pipeline  Over 5 Bcf/d capacity (5.5 Bcf/d peak day)  145 Bcf of storage  Access to 685 MMcf/d processing capacity  180 MMcf/d CO2 treating capacity  Combination of fee-for- service, and purchase / sale activity  Texas Railroad Comm

  25. Slide 25: Texas Intrastate Pipelines Key Attributes

    Texas Intrastate Pipelines Key Attributes  Well-positioned assets — Built to serve Houston / Beaumont area -- largest natural gas market in the world — Connected to essentially all major gas consumers in the area — Gas supply available from major basins across Texas and both Texas LNG terminals — C

  26. Slide 26: Texas Intrastate Pipelines Growth Opportunities

    Texas Intrastate Pipelines Growth Opportunities Large asset footprint provides real and continued opportunities for expansion capital investment  Eagle Ford Shale — Eagle Ford gathering JV with Copano for rich gas — KM 100% on lean gas opportunities  Other pipe conversions to rich gas service — Mc

  27. Slide 27: Eagle Ford Gathering JV

    Eagle Ford Gathering JV Eagle Ford Gathering JV 50/50 Joint Venture with Copano in S. Tx  Total KM capex approximately $136MM Supply Lateral  Approximately 111 miles of 30” and 24” pipeline under construction – expected in-service 3Q 2011  Capacity expanded from 375,000 to 600,000 MMBtu/d  Gas s

  28. Slide 28: Growth Opportunities in 2011, 2012 and Beyond

    Growth Opportunities in 2011, 2012 and Beyond 2011  Full-year effect of new projects and acquisitions — FEP, KinderHawk  New growth continues with expansions, Eagle Ford and Dayton Storage to be placed fully in service 2012 and beyond - long term / future growth  Shale gas — TX Intrastates – Eagl

  29. Slide 29: Kinder Morgan

    KINDER/MORGAN

Kinder Morgan — Kinder Morgan 2011 Analyst Conference on 6ix