Civmec — Q3 FY25 Earnings Presentation

16 slides from Civmec's earnings presentation, May 8, 2025

  1. Slide 1: Investor Presentation Q3 FY25

    Investor Presentation Q3 FY25 ASX:CVL SGX:P9D

  2. Slide 2: Delivering for Australia since 2009

    Delivering for Australia since 2009 Civmec is a multidisciplinary services provider to the energy, resources, infrastructure, marine and defence sectors, delivering Australian projects for more than 15 years. Constructed new Delivered Perth Port Hedland Opened 29,300m2 Officially opened head Acquire

  3. Slide 3: Civmec snapshot

    Civmec snapshot Australian company A$432.2m listed on ASX & SGX market cap (as at 02/05/2025) 508,528,000 Redomiciled shares on issue to Australia (as at 02/05/2025) in September 2024 58.7% shares on ASX (as at 02/05/2025) 4 major facilities Henderson, WA Newcastle, NSW Gladstone, QLD 41.3% Port Hed

  4. Slide 4: Q3 FY25 operational update

    Q3 FY25 operational update • A$285 million of recent contract awards take the current order book over A$760 million, with current tendered works totalling A$13.2 billion (excluding naval prospects). • Civmec’s unique OEM balanced machine offering provides access to A$2.8 billion pipeline of new and

  5. Slide 5: Q3 FY25 financial update

    Q3 FY25 financial update A$ million Q3 FY25 9M FY25 2.5c interim dividend paid 11 April 2025. Revenue $158.5 $661.3 Since FY18, Civmec has paid A$105.5m to investors in dividends, equivalent to 20.9 cents per share. EBITDA $19.2 $72.1 EBITDA Margin 12.1% 10.9% A$285m increase to order book in Q3 FY2

  6. Slide 6: Strategic facility locations in key activity hubs

    Strategic facility locations in key activity hubs Port Hedland Gladstone • Newly constructed 5,000m2 Port Hedland • Located on 34,000m2 land, with facility on 50,000m2 of land 25 12 20 NT workshop/offices 11 26 • Supporting port and process 33 34 32 29 27 38 • Client engagement resulting in plant ma

  7. Slide 7: Continued growth in the OEM division

    Continued growth in the OEM division • Contract awarded for a new shiploader project for Port Waratah Coal Services (Port Waratah), including the design, fabrication, preassembly, shipping and installation of a new shiploader at the Kooragang Terminal. The project will create 100 specialised jobs. •

  8. Slide 8: Continued growth in maintenance

    Continued growth in maintenance • Secured in excess of A$40 million of maintenance work during Q3 FY25, including a separate refurbishment works contract for Port Waratah for an existing shiploader at Kooragang Terminal. • Under a separate contract, the Port Waratah maintenance project will be deliv

  9. Slide 9: Energy update and outlook

    Energy update and outlook • Recent completed works include Scarborough subsea structures, A$43.5 billion of opportunities 2025 – 2028* J-IC subsea spools, JDP3 manifold and mudmat, and wet parking frame structures for Woodside. 14 12.9B 12.8B 12 • Civmec also succesfully completed the J-IC manifold

  10. Slide 10: Resources update and outlook

    Resources update and outlook • Reached a significant milestone at Western Range by achieving the first ore milestone on time, marking a crucial step in the project’s development and demonstrating Civmec’s capability to deliver complex resources projects successfully. • Civmec has secured a contract

  11. Slide 11: Infrastructure, marine and defence update and outlook

    Infrastructure, marine and defence update and outlook • Site delivery phase of 2,500 tonnes of steel girders for the Molonglo A$145.2 billion of opportunities 2025 – 2028* River Bridge Crossing in Canberra is now in progress. 45 42.3B 41.2B • Naval shipbuilding activities have recommenced with the c

  12. Slide 12: Future opportunities naval shipbuilding and defence

    Future opportunities naval shipbuilding and defence Fremantle Port • Multi-billion-dollar Australian Government investment announced to expand the Henderson precinct and Fleet Base West, with Civmec well positioned Henderson to support infrastructure construction, and future naval shipbuilding. Civm

  13. Slide 13: ESG and company updates

    ESG and company updates • Further to the installation and commissioning of a 600kW solar PV • Engineers Australia lunch attended for International Women’s Day 2025. system at Newcastle, we completed a feasibility study and consultation with local authorities to install additional systems at our faci

  14. Slide 14: Appendix FY25 key projects

    Appendix FY25 key projects 5. OneSubsea 29. IBJV 37. Queensland 43. BMD Constructions Julimar Development Iron Bridge – punchlist Alumina Limited Molonglo River Bridge Project Phase 3 (JDP3) – works Mechanical Crossing fabrication Marble Bar, WA maintenance works Newcastle, NSW Henderson, WA to supp

  15. Slide 15: www.civmec.com.au

    Civmec Investor Relations P: +61 8 9437 6288 www.civmec.com.au E: investor@civmec.com.au | Engineering Success Civmec Investor Presentation | Q3 FY25 Page 15

  16. Slide 16: Disclaimer

    Disclaimer This presentation has been prepared by the management of Civmec Limited (the Company) for the benefit of brokers, analysts, and investors and not as any specific advice to any particular party or person. The information is based on publicly available information, internally developed data