Slide 1: Adelaide Wind Project Community Liaison Committee
Adelaide Wind Project Community Liaison Committee October 23, 2014
Slide 2: Agenda
Adelaide Wind Project Community Liaison Committee Agenda • Safety Moment (Holly Davidson) • Project Team Review • Contact Information • Project Map and Transportation Plan • Project Schedule • Construction Details 2
Slide 3: Safety Moment - Winter driving and black ice
Adelaide Wind Project Community Liaison Committee Safety Moment - Winter driving and black ice • Black ice is a thin layer of transparent ice that forms when the temperature is around the freezing point. • It sometimes makes the road look slightly wet. • Black ice can sneak up on you, so pay attenti
Slide 4: Opportunity and Anticipate
Opportunity Anticipate • Black ice can be the cause of many winter driving accidents. • The best way to avoid an accident is to anticipate the road conditions and adapt to changing conditions. • Clues to anticipate black ice: – Ice build-up on my mirror arms, antenna, or the top corners of my windsh
Slide 5: Action: What to do
Action What to do • Allow additional time – Slow down – Allow for extra time to safety travel to you destination • Don’t use cruise control in slippery conditions • Drive at a safe following distance – The distance traveled from the point you perceive a need to stop, to the point where the vehicle a
Slide 6: Recommendations: Tires are important
Recommendations Tires are important! • Winter tires – Have special tread compounds that use one or more of the following features to deliver improved traction. ▪ "Soft stud" tread fibers "bite" like metal studs yet are quiet and do not harm the road. ▪ Special compounds retain their flexibility even
Slide 7: Project Team
Adelaide Wind Project Community Liaison Committee Project Team: • Suncor • Development Team is responsible for site development, permitting and regulatory compliance • Major Projects Group is responsible for managing detailed engineering and construction • Operations Group is responsible for long te
Slide 8: On Site Contact Information
Adelaide Wind Project Community Liaison Committee On Site Contact Information 8
Slide 9: Adelaide Wind Project – Construction Arrangement
Adelaide Wind Project – Construction Arrangement Direct Contract Suncor AMEC Supervision Contract Graham Eptcon Site Site Civil Turbine Collection Substation Works Erection System 9
Slide 10: Site Map
Adelaide Wind Project Community Liaison Committee - Site Map 10
Slide 11: Project Schedule
Adelaide Wind Project Community Liaison Committee Project Schedule Jan • All civil work (access roads, foundations, etc.,) is approx. 100% complete • Turbine component deliveries will be competed by end of Oct • Turbine installation is underway with target completion by mid-Nov • Collection system i
Slide 12: Project Schedule
Adelaide Wind Project Community Liaison Committee Project Schedule Jan Civil Works Electrical Works Turbine Supply Main Component Transportation Turbine Installation 12
Slide 13: Construction Activities
Adelaide Wind Project Community Liaison Committee Construction Activities • First few activities were creating entrances off of road right of ways Jan 13
Slide 14: Construction Activities
Adelaide Wind Project Community Liaison Committee Construction Activities • Access Roads and turbine foundations were next Jan 14
Slide 15: Access Road
Adelaide Wind Project Community Liaison Committee Access Road Jan 15
Slide 16: Turbine Foundation
Adelaide Wind Project Community Liaison Committee Turbine Foundation Jan 16
Slide 17: Collection System Installation
Adelaide Wind Project Community Liaison Committee Collection System Installation Jan 17
Slide 18: Collection System Installation
Adelaide Wind Project Community Liaison Committee Collection System Installation Jan 18
Slide 19: Pipeline Crossings
Adelaide Wind Project Community Liaison Committee Pipeline Crossings • The project had 2 crossings of pipelines (Enbridge gas and Huron Water Jan Supply) • Permission was obtained to drill pipes under the crossings, this occurred during collection system install. Collection System Crossing 19
Slide 20: Turbine Installation
Adelaide Wind Project Community Liaison Committee Turbine Installation Jan 20
Slide 21: Turbine Transportation
Adelaide Wind Project Community Liaison Committee Turbine Transportation Jan 21
Slide 22: Turbine Installation
Adelaide Wind Project Community Liaison Committee Turbine Installation Jan 22
Slide 23: Site Reclamation
Adelaide Wind Project Community Liaison Committee Site Reclamation Jan 23