Fortescue Ltd · ASX:FMG
Fortescue — Fortescue Metals Group — Global Iron Ore & Steel Forecast Conference 2020
22 slides from Fortescue's conference presentation, Dec 1, 2020

Slide 1: Presentation – Global Iron Ore & Steel Forecast Conference
1 December 2020 The Companies Officer Australian Securities Exchange Ltd Level 40, Central Park 152-158 St Georges Terrace Perth WA 6000 Dear Madam or Sir PRESENTATION – GLOBAL IRON ORE & STEEL FORECAST CONFERENCE Fortescue Metals Group Ltd (ASX: FMG) advises that Greg Lilleyman, Chief Operating Off

Slide 2: World class operations, infrastructure and marketing delivering value
World class operations, infrastructure and marketing delivering value Greg Lilleyman, Chief Operating Officer 1

Slide 3: Forward Looking Statements Disclaimer
Forward Important Notice The purpose of this presentation is to provide general information about Fortescue Metals Group Ltd (“Fortescue”). It is not recommended that any person makes any investment decision in relation Looking to Fortescue based on this presentation. This presentation contains cert

Slide 4: World class company
World class Global force | Thriving communities company Long term Balance sheet sustainability strength Target 30 to 40% Wholly Industry owned, fully leading cost Vision integrated supply chain position and Values Secure and reliable supplier Growth and of iron ore Enhanced development returns to sh

Slide 5: Safety and unique culture
Safety and unique culture 2.1 TRIFR at 30 September 2020 COVID-19 Prioritising health and safety of the Fortescue family Projects Embedding our safety culture across multiple sites 4

Slide 6: Strong start to FY21 with record first quarter operating performance
Strong start to FY21 with record first Q1 FY21 quarter operating performance highlights 2.1 TRIFR 44.3 mt shipped 13% improvement 5% higher than Q1FY20 US $12.74 /wmt US $106 /dmt C1 cost Average realised price 89% of average Platts 62% CFR Index US $1.0bn >10 mt sold Net cash FMG Trading Shanghai s

Slide 7: Deliberate strategy for dynamic future growth
Deliberate strategy for Fully integrated dynamic future growth supply chain Structure of business Operations and marketing Product strategy Majority over 60% Fe Investing in growth Underpinned by innovation 6

Slide 8: Marketing
Integrated operations and marketing strategy to maximise Marketing value Direct customer engagement driving deep market insights Reliable supplier and optimised product mix that meets customers’ needs Aligning delivery with customers’ requirements and opening new channels 7

Slide 9: Strong demand for iron ore in China supported by increased imports
Strong demand for iron ore in China supported by increased imports Sustained growth in China’s crude steel production China monthly crude steel output (mt) China monthly iron ore imports (mt) 100 120 95 110 90 85 100 80 90 75 80 70 65 70 60 60 55 50 50 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Slide 10: Iron ore price
Fortescue’s average realised price of US$79/dmt Iron ore in FY20 increased by 21 per cent on the prior year price Iron ore prices, CFR China (US$/dmt) 140 130 120 110 100 90 80 70 60 50 40 Jan-19 Apr-19 Jul-19 Oct-19 Jan-20 Apr-20 Jul-20 Oct-20 Platts 62% CFR Index Fortescue Blend (portside) Super S

Slide 11: Delivering on our product strategy
Delivering on our product strategy Enhancing Fortescue’s product portfolio Competitive positioning across all product segments Flexibility to optimise margins through iron ore market cycles Highest grade Australian product, with global scale production 10

Slide 12: Investing in growth
Executing on growth, product and Investing in growth decarbonisation strategy Eliwana US$1.325 – US$1.375 billion investment 30mtpa processing and 143km rail Iron Bridge US$2.6 billion investment 22mtpa 67% Fe magnetite concentrate product Pilbara Energy Connect US$700 million investment Solar-gas h

Slide 13: Eliwana Mine and Rail Project
Eliwana Mine and Rail Project 30 mtpa First ore progressing on schedule 60.1% Fe Underpinning production of West Pilbara Fines US$45 per tonne Industry leading capital intensity Ore Processing Facility Close to completion and commissioning 12

Slide 14: Eliwana progress
Eliwana progress On schedule for first ore on train in December 2020 Ore processing facility Eliwana rail bridge 13

Slide 15: Iron Bridge Magnetite project
Iron Bridge Magnetite project 22 mtpa Production, with first ore on ship in mid-CY22 67% Fe High grade, low impurity concentrate product US$2.6bn Stage 2 investment, low capital intensity >88% Bulk earthworks complete 14

Slide 16: Iron Bridge progress
Iron Bridge progress Construction on schedule Ore processing facility site Rendering – Ore processing facility 15

Slide 17: Energy infrastructure
Energy infrastructure US$800 million investment with our business partners will deliver 25 to 30 per cent of stationary energy from solar power 16

Slide 18: Energy infrastructure
Energy infrastructure Industry leading emissions reduction goal, to achieve net zero operational emissions by 2040, underpinned by practical initiatives Chichester solar gas Pilbara Energy Connect Hydrogen hybrid project US$100 million investment by US$250 million Pilbara Reduce carbon emissio

Slide 19: Key strategic focus
Key strategic focus Underpinned by balance sheet strength Long term sustainability Growth and development Enhanced returns to shareholders 18

Slide 20: FY21 guidance
FY21 guidance 175 – 180mt Iron ore shipments US$13.00 – US$13.50/wmt C1 costs based on assumed exchange rate of AUD:USD 0.70 US$3.0 – US$3.4 billion Capital expenditure 19

Slide 21: Our Purpose
Our Purpose Thriving communities | Global force Fortescue’s Values BE IRAE

Slide 22: Fortescue
a Fortescue w Fortescue © www.fmgl.com.au W FortescueNews
Source: company website
More decks from Fortescue Ltd
Shareholder Meeting (October 2026)45 slides · Oct 28, 2026
FY2026 Earnings Presentation34 slides · Aug 20, 2026
BofA Securities Global Metals, Mining and Steel Conference 202612 slides · May 12, 2026
H1 FY26 Earnings Presentation36 slides · Feb 25, 2026
Shareholder Meeting (October 2025)31 slides · Oct 31, 2025
FY2025 Earnings Presentation36 slides · Aug 26, 2025