BP plc · LSE:BP.

BP — Technical Presentation (September 2010)

39 slides from BP's technical presentation, September 2010

  1. Slide 1: Deepwater Horizon Investigation

    Deepwater Horizon Investigation Deepwater Horizon Accident Investigation 1

  2. Slide 2: Investigation Context

    Investigation Context ƒ Terms of Reference ƒ Investigation Team ƒ Data and Analysis ƒ Investigation Limitations Deepwater Horizon Accident Investigation 2

  3. Slide 3: Eight Barriers Were Breached

    Eight Barriers Were Breached Well integrity was not established or failed 6 7 − 1 Annulus cement barrier did not isolate hydrocarbons 3 5 − 2 Shoe track barriers did not isolate hydrocarbons Hydrocarbons entered the well undetected and Riser 4 well control was lost − 3 Negative pressure test was acc

  4. Slide 4: Introduction Technical Presentation

    Introduction Technical Presentation Deepwater Horizon Accident Investigation 4

  5. Slide 5: Well Integrity Was Not Established or Failed

    Well Integrity Was Not Established or Failed Deepwater Horizon Accident Investigation 5

  6. Slide 6: Production Casing Installation

    Production Casing Installation After drilling to total depth, casing is run to bottom in preparation for the cement job. A Choke double valve float collar is used to prevent Kill Boost backflow or ingress of fluids through the shoe track until the cement hardens and creates a permanent barrier. BOP

  7. Slide 7: Cement Job

    Cement Job Cement is pumped down casing through the float collar and up the annulus to isolate the primary reservoir sands. Choke Pull out ofKillhole April 19th 19:30 – April 20th 07:00 Boost with running tool and drill ƒ Nitrogen cement slurry chosen pipe – To achieve light weight slurry due to BOP

  8. Slide 8: Key Finding #1

    Key Finding #1 The annulus cement barrier did not isolate the reservoir hydrocarbons Cement is pumped down the Cement Slurry Placement landing string and casing into the Base Oil 16.7 ppg 6.7 ppg annulus to isolate hydrocarbon bearing sands. Spacer 14.3 ppg Riser 14.3 ppg Cap Cement Channeling Mud 1

  9. Slide 9: Cement Slurry Design Issues

    Cement Slurry Design Issues An independent lab completed over 500 tests on a representative cement slurry and reported the following: ƒ 50% quality foam at surface conditions Original Height was not stable ƒ 18.5% quality foam (downhole quality) was not stable ƒ Yield point of the Halliburton slurry

  10. Slide 10: Flow Through Shoe Track - Supporting Evidence

    Flow Through Shoe Track - Supporting Evidence Casing Key Observations for Flow Seal Shoe Through Shoe vs. Seal Assembly Failure Assembly Failure Y Mechanical Barrier Failure Mode Identified Y Y Realistic Net Pay Assumption N Y 1400 psi recorded on drill pipe during negative N test at 18:30 Y Ability

  11. Slide 11: Key Finding #2

    Key Finding #2 The shoe track mechanical barriers did not isolate the hydrocarbons Tail cement is displaced down the casing into the shoe track. The tail cement is designed to prevent flow from the annulus into the casing. The float collar valves, which provide a second barrier, Riser must close and

  12. Slide 12: Hydrocarbons Entered the Well Undetected and Well Control Was Lost

    Hydrocarbons Entered the Well Undetected and Well Control Was Lost Deepwater Horizon Accident Investigation 12

  13. Slide 13: Casing (Positive) Pressure Test

    Casing (Positive) Pressure Test 2700 psi Kill A positive pressure test verifies the integrity of the casing and seal assembly. April 20th 07:00 – 12:00 Sea Floor ƒ Casing was pressure tested to: Cement ƒ 250 psi (low) Mud ƒ 2700 psi (high) Spacer ƒ Test successful ƒ Proved integrity of blind shear r

  14. Slide 14: Negative Pressure Test

    Negative Pressure Test The negative-pressure test checks the integrity of the shoe track, casing and wellhead seal assembly. This simulates Choke Boost Kill 15:04 – 15:56 conditions during temporary Seawater pumped into abandonment when a portion of the well Boost, Choke, and Kill lines is displaced

  15. Slide 15: Negative Pressure Test

    Negative Pressure Test The negative-pressure test checks the 17:52 – 18:00 integrity of the shoe track, casing and Open kill line to conduct wellhead seal assembly. This simulates Choke negative test Kill conditions during temporary Boost 16:59 – 17:08 abandonment when a portion of the well Bled 3 -

  16. Slide 16: Negative Pressure Test

    Negative Pressure Test The negative-pressure test checks the 1400 0 integrity of the shoe track, casing and psi psi 18:00 – 18:35 wellhead seal assembly. This simulates Choke Drill pipe pressure gradually Boost increased to 1400 psi conditions during temporary abandonment when a portion of the well

  17. Slide 17: Key Finding #3

    Key Finding #3 The negative pressure test was accepted although well integrity had not been established 1400 0 PSI PSI Riser Choke Kill ƒ Bleed volumes not recognized as a Boost problem BOP Sea Floor BOP ƒ Anomalous pressure on drill pipe with no Sea Floor flow from kill line Spacer Casing SOBM ƒ Te

  18. Slide 18: Well Monitoring – Driller's Console and Mudlogging unit

    Well Monitoring – Driller’s Console and Mudlogging unit ƒ Well monitoring is performed to understand if the well has losses or gains ƒ Driller is responsible for monitoring and shutting in the well ƒ The mudlogger provides monitoring support to the driller ƒ Displays and trending capability availabl

  19. Slide 19: Undetected Flowing Conditions

    Undetected Flowing Conditions Mud in the riser is displaced with seawater in preparation for temporary abandonment. Choke Kill Boost 21:08 Spacer arrived at surface April 20th 19:55 – 21:14 Shut pumps down for sheen test BOP ƒ 20:02 Resume displacement of mud with 20:02 seawater Sea Floor Annular op

  20. Slide 20: Key Finding #4

    Key Finding #4 The influx was not recognized until hydrocarbons were in the riser 2000 3000 Flow Indications Based on Real-time Data Flow indications: Flow Out (calibrated) 1800 Flow In (rig pumps) DP Press (rig pumps) 2500 ƒ #1: Drill pipe pressure 1600 increased by 100 psi, Decreasing trend should

  21. Slide 21: Key Finding #4

    Key Finding #4 The influx was not recognized until hydrocarbons were in the riser 2000 3000 Flow Indications Based on Real-time Data Flow indications: Flow Out (calibrated) 1800 Flow In (rig pumps) DP Press (rig pumps) 2500 ƒ #1: Drill pipe pressure 1600 increased by 100 psi, Decreasing trend should

  22. Slide 22: Key Finding #4

    Key Finding #4 The influx was not recognized until hydrocarbons were in the riser 2000 3000 Flow Indications Based on Real-time Data Flow indications: Flow Out (calibrated) 1800 Flow In (rig pumps) DP Press (rig pumps) 2500 ƒ #1: Drill pipe pressure 1600 increased by 100 psi, 1400 Indication #3 2000

  23. Slide 23: Key Finding #5

    Key Finding #5 Well control response actions failed to regain control of the well Influx enters riser 3000 Based on Real-time Data First indication of well control response: 49 minutes and 1000 bbls after initial influx Drill Pipe Presssure (psi) 2500 BOP Mud shoots up derrick Attempt to bleed -Dive

  24. Slide 24: Hydrocarbons Ignited on the Deepwater Horizon

    Hydrocarbons Ignited on the Deepwater Horizon Deepwater Horizon Accident Investigation 24

  25. Slide 25: Diverting to the Mud Gas Separator at about 21:42

    Diverting to the Mud Gas Separator at about 21:42 12” Vent When responding to a well control event the riser diverter is closed and fluids 6” Vacuum Breaker sent to either the mud gas separator or Bursting Disk to the overboard diverter lines. Diversion to the MGS MGS Rated to 60 psi working pressur

  26. Slide 26: Gas flow to Surface at high rate: 21:46 to 22:00

    Gas flow to Surface at high rate: 21:46 to 22:00 12” Vent When responding to a well control event the riser diverter is closed and fluids 6” Vacuum Breaker sent to either the mud gas separator or Bursting Disk to the overboard diverter lines. Hydrocarbon flow from surface MGS equipment Rotary Hose M

  27. Slide 27: Gas Dispersion across the Deepwater Horizon 21:46 to 21:50 hrs

    Gas Dispersion across the Deepwater Horizon 21:46 to 21:50 hrs Animation of Gas Dispersion Upper Explosive Limit Lower Explosive Limit 3D View Cut Section Through Derrick Towards Aft Deepwater Horizon Accident Investigation 27

  28. Slide 28: Secondary protective systems did not prevent ignition

    Secondary protective systems did not prevent ignition Secondary protective systems are designed to reduce the potential consequence of an event once the 3D view primary protective systems have failed. Fwd Aft Secondary Protective Systems ƒ Gas cloud reached the supply air intakes for engine rooms 3,

  29. Slide 29: Key Finding #6

    Key Finding #6 Diversion to the mud gas separator resulted in gas venting onto the 12” Vent rig 6” Vacuum Breaker When responding to a well control event Bursting Disk the riser diverter is closed and fluids are sent to either the mud gas separator or to the overboard diverter lines. MGS Rotary Hose

  30. Slide 30: Key Finding #7

    Key Finding #7 The fire and gas system did not prevent hydrocarbon ignition Gas Dispersion at 4 minutes Secondary protective systems are designed to reduce the potential (Upper Explosive Limit) consequence of an event once the primary protective systems have Aft failed. ƒ Gas dispersion beyond elect

  31. Slide 31: Emergency Well Control System Did Not Seal the Well

    Emergency Well Control System Did Not Seal the Well Deepwater Horizon Accident Investigation 31

  32. Slide 32: Blowout Preventer (BOP)

    Blowout Preventer (BOP) BOP Control Panel Surface HPU & Accumulators Flex Joint LMRP Upper Annular Lower Annular Stripping Element Mux Cable Hydraulic Conduit LMRP Accumulators Blind Shear Ram Blue Yellow Control Control Casing Shear Ram Pod Pod (Non Sealing) Upper VBR Lower Stack Middle VBR Accumul

  33. Slide 33: BOP Response (Before the Explosions)

    BOP Response (Before the Explosions) BOP is designed to seal the wellbore and April 20th shear casing or drill pipe if necessary. 21:38 – Hydrocarbons enter the riser April 20th ƒ 21:41 annular BOP closed but appears Activation of Upper Annular Lower Annular BOP not to have sealed the annulus Lower

  34. Slide 34: BOP Response (Impact of Explosions)

    BOP Response (Impact of Explosions) MUX cables provide electronic communication and electrical power to the BOP control pods. April 20th ƒ Damage to MUX cables and hydraulic line Upper Annular – Opening of annular BOP Lower Annular Annular BOP Stripping Element gradually opens ƒ Rig drifted off loca

  35. Slide 35: BOP Response (After the Explosions)

    BOP Response (After the Explosions) There are several emergency methods of activating the BSR to seal the well. April 20th ƒ EDS attempts failed to activate BSR Upper Annular ƒ AMF sequence likely failed to activate BSR Lower Annular April 21st – 22nd Stripping Element BSR activated by ƒ ROV hot sta

  36. Slide 36: Key Finding #8

    Key Finding #8 The BOP emergency mode did not seal the well Explosions & Fire: The AMF provides an automatic Loss of communication means of closing the BSR without Loss of electrical power crew intervention. Loss of hydraulics ƒ EDS function was inoperable due to Damaged Hydraulic Conduit damage to

  37. Slide 37: Summary of Findings and Recommendations

    Summary of Findings and Recommendations Deepwater Horizon Accident Investigation 37

  38. Slide 38: Recommendations

    Recommendations 25 Recommendations Specific to the 8 Key Findings BP Drilling Operating Practice and Management Systems ƒ Engineering Technical Practices and Procedures ƒ Further Enhance Deepwater Capability and Proficiency ƒ Strengthen Rig Audit Action Closeout and Verification ƒ Introduce Integrit

  39. Slide 39: Summary of Key Findings

    Summary of Key Findings Well integrity was not established or failed 6 7 − 1 Annulus cement barrier did not isolate hydrocarbons 3 5 − 2 Shoe track barriers did not isolate hydrocarbons Hydrocarbons entered the well undetected and Riser 4 well control was lost − 3 Negative pressure test was accepted

BP — Technical Presentation (September 2010) on 6ix