  1. Slide 1: Delivering the world’s next major nickel sulphide mine

    Delivering the world’s next major nickel sulphide mine A fully-permitted Tier-1 nickel project moving towards financing and construction | September 2026

  2. Slide 2: Disclaimer

    Disclaimer ► This presentation does not constitute investment advice. Neither this presentation nor the information contained in it constitutes an offer, invitation, solicitation or recommendation in relation to the purchase or sale of shares in any jurisdiction. This presentation does not take into

  3. Slide 3: Investment Highlights

    Investment Highlights Delivering the world’s next major nickel sulphide mine Tier-1 Asset Development-Ready 1.2Mt contained nickel Mining Lease granted Long-life open pit operation – initial 15-year life Environmental approvals secured First quartile operating costs and strong margins National

  4. Slide 4: Progress Checklist Timeline

    Progress Checklist Jaguar is now entering the financing and execution phase August 2025 October 2025 October 2025 March 2026 March 2026 $23m capital Maiden US$450m, LOI received for Timeline raising to propel Jaguar Nickel Acquisition of 5-year nickel offtake US$190m in funding Jaguar towards Projec

  5. Slide 5: Brazil – Highly Favourable Mining Jurisdiction

    Brazil – Highly Favourable Mining Jurisdiction Active Government support for Critical Minerals GOVERNMENT SUPPORT MINING CULTURE ROAD MAP TO MINING Well-established mining regulation Strong support from Brazil Well-established mining region with and tenement system with Jaguar Government for critica

  6. Slide 6: Brazil’s Carajás Mineral Province

    Brazil’s Carajás Mineral Province A world-class global mining province – “land of the giants” The Carajás contains one of the world’s largest known concentrations of large-tonnage world-class mineral deposits 6

  7. Slide 7: Board and Capital Structure

    Board and Capital Structure (ASX:CTM, OTCQX: CTTZF) Highly Experienced Board 574m A$298m An experienced leadership team, clean corporate structure Shares on issue and strong balance sheet with a clear pathway to value Market cap at A$0.52 growth as project development advances. 73% Top-20 holders 33

  8. Slide 8: Jaguar Nickel Project – Key Project Highlights

    Jaguar Nickel Project – Key Project Highlights Large-scale, long-life project moving to FID 1.2Mt Nickel (Contained) 15-year life US$735M NPV (Post Tax basis, US$9/lb Ni Price) First quartile costs 34% IRR (Post Tax basis, US$9/lb Ni Price) 22.6ktpa Ni production Low-carbon nickel (Avg production fi

  9. Slide 9: Jaguar – A World-Class Nickel Deposit

    Jaguar – A World-Class Nickel Deposit Tier-1 Resource with further exceptional growth potential JORC MRE: 138.2Mt @ 0.87% Ni for 1.20 million tonnes of contained nickel Refer to slide 21 for underlying data references 9

  10. Slide 10: Jaguar – Upside and Growth Opportunities

    Jaguar – Upside and Growth Opportunities Improvement opportunities to be pursued after FID ► Resources of 21.5Mt at 1.46% Ni for 313kt of contained nickel metal below the current pits ► Of this, 15.5Mt at 1.50% Ni for 233kt of contained nickel is classified as Measured and Indicated categories ► Int

  11. Slide 11: Jaguar – Mining Operations

    Jaguar – Mining Operations Globally significant project delivering 22.6ktpa of Ni over first 7 years ► Low capital intensity, with pre-production CAPEX of US$380 million ► JORC Reserve – 52.0Mt @ 0.78% Ni for 406,100t Ni metal ► Open pit mining by local mining contractor; Tailings facilities built f

  12. Slide 12: Jaguar – Financial Metrics

    Jaguar – Financial Metrics Strong free cash flow of US$169m pa (A$264m) over first seven years US$3.34/lb LOM C1 Cash Costs (payable basis) US$4.43/lb LOM AISC (payable basis) * US$1.62b Total Free Cash Flow Capital Payback 1.8 years * Project cash flows at US$9/lb 12

  13. Slide 13: Jaguar – Positioned for a Nickel Price Recovery

    Jaguar – Positioned for a Nickel Price Recovery LME Nickel Price Centaurus hasn’t been waiting for the cycle to turn – it has continued to significantly de-risk Jaguar ahead of a potential nickel market recovery Jaguar Acquired 13

  14. Slide 14: Jaguar – Offtake and Financing Process Gaining Momentum

    Jaguar – Offtake and Financing Process Gaining Momentum Initial Binding Offtake Agreement Secured Offtake ► Maiden nickel Offtake Agreement secured with Glencore AG ► Covers supply of 20,000tpa of high-grade nickel concentrate (~6,400 tpa of nickel in concentrate) ► Average one-third of Jaguar’s for

  15. Slide 15: Jaguar – Pre-Development Activities Accelerating

    Jaguar – Pre-Development Activities Accelerating Activities accelerating on multiple fronts ahead of FID ENGINEERING ► Basic Engineering completed. Detailed design underway on multiple fronts INFRASTRUCTURE ► Initial road improvement and site establishment work underway POWER CONNECTION ► High-volta

  16. Slide 16: Boi Novo Copper-Gold Project

    Boi Novo Copper-Gold Project Emerging copper- gold discovery in the Carajás 16

  17. Slide 17: Boi Novo Project – Copper-Gold Exploration

    Boi Novo Project – Copper-Gold Exploration The Carajás is the world’s premier IOCG address ► 75 km2 Project footprint recently expanded with acquisition of Rio Novo tenure ► Drilling at Boi Novo intersected semi-massive sulphide zones, intersections include: ► 36.7m at 1.58% Cu and 0.05g/t Au ► 5.5m

  18. Slide 18: Key Investment Takeaways

    Key Investment Takeaways • Tier-1 scale - 1.2Mt contained nickel MRE, long-life open-pit operation. • Development-ready - fully permitted, power secured and site establishment underway. • Low-cost - First-quartile costs; 1.8-year payback and strong free cash flows • Funding is the Near-Term Catalyst

  19. Slide 19: Delivering the world’s next major nickel sulphide mine

    Delivering the world’s next major nickel sulphide mine A fully-permitted Tier-1 nickel project moving towards financing and construction Roger Fitzhardinge General Manager – Exploration & Growth : +61 8 6424 8420 : office@centaurus.com.au : Centaurus Metals : @CentaurusMetals

  20. Slide 20: Jaguar Nickel Sulphide Project Resource and Reserve

    Jaguar Nickel Sulphide Project August 2024 Mineral Resource Estimate & May 2025 Ore Reserve Estimate Grade Contained Metal (Tonnes) Classification* Mt Ni % Cu % Co ppm Ni Cu Co Measured 14.8 1.06 0.07 388 156,100 10,200 5,900 Indicated 97.8 0.84 0.06 246 822,800 61,100 24,000 Measured & Indicated 11

  21. Slide 21: Nickel Sulphide Deposit Comparison Data and References

    Centaurus Data and references for comparison of pre-mined resources of global nickel sulphide Deposits and Camps Current Resource MI&I - Ni Metal Historic Prodn (h) Pre-Mined Resource MI&I Camp / Deposit Country Company Stage Resource Date Measured (f) Indicated Inferred Total Mt Ni in-situ Mt Ore %