  1. Slide 1: Chatham to Lakeshore Transmission Line Project

    hydro~ one TO OUR VIRTUAL COMMUNITY INFORMATION SESSION CHATHAM TO LAKESHORE TRANSMISSION LINE PROJECT

  2. Slide 2: Today's Agenda

    TODAY’S AGENDA • Project overview • Class Environmental Assessment process • Proposed route alternatives and route selection process • Key milestones and next steps • Live Q&A session 1

  3. Slide 3: Key Organizations

    KEY ORGANIZATIONS Building infrastructure to meet the energy needs of today and tomorrow involves a number of partners, including: Builds, owns, operates and maintains electricity transmission and distribution facilities across Ontario. Oversees planning to ensure electricity needs are met both now

  4. Slide 4: How the System Works

    hydro~ HOW THE SYSTEM one WORKS ONTARIO POWER GENERATION AND HYDRO ONE OR UCENSED TRANSMITIER PRIVATE GENERATION COMPANIES • ::::::11 •. --- Generation ::::::::::::::: 11111111111111 Slap-up Transfonner Transmission Unes 1m11i 1M!111i11i11 Transform.. Distnnution Station 115,000-500,000 volts M Stat

  5. Slide 5: Project Overview

    PROJECT OVERVIEW A safe and reliable electricity supply is essential to supporting economic growth, and as businesses and industry in southwestern Ontario continue to grow, so does the need for more electricity. To help meet this growth, Hydro One needs to build a new double circuit 230 kilovolt tra

  6. Slide 6: What Is a Class Environmental Assessment?

    WHAT IS A CLASS ENVIRONMENTAL ASSESSMENT? The Class Environmental Assessment (Class EA) for Minor Transmission Facilities sets out a planning and decision-making process for projects with predictable environmental effects that can be mitigated. KEY COMPONENTS • Consultation with Indigenous communiti

  7. Slide 7: How We Got Here

    HOW WE GOT HERE A preliminary assessment was conducted to map feasible route alternatives for the new transmission line. This involved mapping out known environmental and technical features, and identifying opportunities to parallel existing linear infrastructure and utilize existing easements, wher

  8. Slide 8: Routes We Are Studying

    ROUTES WE ARE STUDYING To view our interactive map, please visit: www.arcg.is/1PKL1n 7

  9. Slide 9: Evaluation of Routes

    EVALUATION OF ROUTES To evaluate the route alternatives, we will: • Meet with First Nations communities, community members, elected officials, and interest groups through Community Information Centres and engagement opportunities to gather feedback; • Conduct background research and detailed environ

  10. Slide 10: Example Evaluation Criteria

    EXAMPLE EVALUATION EXAMPLE EVALUATION hydro~ one CRITERIA CRITERIA Natural Socio-Economic Environment Environment • Vegetation • Residences •Water bodies or aquatic habitat •Commercial operations • Terrestrial wildlife • Existing infrastructure • Natural hazards (roads, pipelines, transmission lines

  11. Slide 11: Land Requirements

    LAND REQUIREMENTS Hydro One Real Estate coordinators have acquired temporary access from some landowners to conduct field studies as part of the Class EA process. Upon the selection of the preferred route, a Hydro One Real Estate coordinator will work with directly impacted property owners that will

  12. Slide 12: How to Get Involved

    HOW TO GET INVOLVED Your feedback is important to us and we want to hear from you. You can provide us with your feedback by: Asking a question via our virtual community information session Submitting your comments to Community.Relations@HydroOne.com or 1-877-345-6799 Attending future Community Infor

  13. Slide 13: Project Milestones

    hydro~ one PROJECT MILESTONES EARLY END OF 2021 2025 Second PropoMd Cammunily lina in·..vica ln~rmatian c..n1raancl prmm1lalion of pnil'w1ed raula Environmental ,iudi._ and preferred roufe aelection 12 I

  14. Slide 14: Live Question Period

    LIVE QUESTION PERIOD Panelists Daniel Levitan Sanjiv (Sonny) Karunakaran Vice President of Stakeholder Relations Director, Strategic Projects John Chadwick Sara Jane Souliere Manager, Environmental Services Senior Advisor, Indigenous Relations Andrew Luis Rouselle Gratela Senior Real Estate Coordina