Kinder Morgan, Inc. · NYSE:KMI

Kinder Morgan — Corporate Update (April 2023)

25 slides from Kinder Morgan's corporate update, Apr 19, 2023

  1. Slide 1: Southern Natural Gas Company 2023 Outage Review

    Southern Natural Gas Company 2023 Outage Review April 19, 2023

  2. Slide 2: Welcome

    Southern Natural Gas Company, L.L.C. Welcome

  3. Slide 3: Agenda

    Agenda • Review of current and upcoming notable Outages – April/May/June/July • Unscheduled outages • North System • South System • South Louisiana System • EEC 2023 • The next outage meeting will be on May 17th at 1:30 CST • Contacts 3

  4. Slide 4: Disclaimers

    Disclaimers • Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. • Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas

  5. Slide 5: Color Key for Maps

    Color Key for Maps • Yellow – Restrictions are possible – With extended duration, restrictions could be necessary from time to time – Lower than normal pressures may be experienced – Meter(s) affected are noted with (PIN #) • Red – Restrictions are probable 5

  6. Slide 6: Southern Natural Gas Pipeline

    Southern Natural Gas Pipeline Chattanooga Rome Hartwell SC Muldon North System GA MS McConnells Tarrant Bell Mills Atlanta Aiken Pell City DeArmanville Louisville Wrens Providence Ocmulgee Pickens Reform Ellerslie Hall Gate Bear Creek Onward Auburn Thomaston Elba Rankin Selma Elmore Holy Trinity Bie

  7. Slide 7: Southern Natural Gas Pipeline Unscheduled Outage Update

    Southern Natural Gas Pipeline Unscheduled Outage Update Chattanooga Unscheduled unit outage at Wrens Rome Seg.560 Cap. Of 680 Mdth/d impacted 102 Mdth/d Hartwell SC Muldon North System RTS 6-26-26 GA MS McConnells Tarrant Bell Mills Atlanta Aiken Reform DeArmanville Providence Pell City Hall Gate Wr

  8. Slide 8: SNG North System Pigging Review April/May/June/July

    SNG North System Pigging Review April/May/June/July Chattanooga Pigging on 2ndNML Huntsville 4-25-23 to 4-27-23 Pro. 15016-east of Rome McConnells AL Pigging on NML Pigging on 2ndNML Muldon Storage Atlanta 5-8-23 to 5-10-23 Tarrant Bell Mills 6-20-23 to 6-22-23 7-11-23 to 7-13-23 MS Pro.5350-Pickens

  9. Slide 9: SNG North System Pigging April thru July Cont.

    SNG North System Pigging April thru July Cont. Chattanooga Pigging on TCILL Huntsville 7-25-23 to 7-26-23 Rome Pro.14781-west of Tarrant AL Muldon Storage Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArmanville Providence Louisville Pickens GA Onward Bear Creek Storage AL Logansport B

  10. Slide 10: SNG North System Maint. Review April/May/June/July

    SNG North System Maint. Review April/May/June/July Cedartown Chattanooga tap line Muldon unit maintenance pipeline Maintenance 1-30-23 to 7-31-23 6-5-23 to 6-30-23 Huntsville Inj. Cap. Reduced by 70 Mdth/d Rome AL Muldon Storage Atlanta Bear Creek Shut-in test Tarrant Bell Mills 4-18-23 to 9 AM on 4

  11. Slide 11: SNG North System Maint. Review April thru July cont.

    SNG North System Maint. Review April thru July cont. Chattanooga Branch line Chattanooga Pipeline maintenance 7-17-23Huntsville to 8-4-23 South of Rome Pro. 26297 Rome AL Muldon Storage Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArmanville Providence Louisville Pickens GA Onward Bea

  12. Slide 12: SNG South System Pigging Review April/May/June/July

    SNG South System Pigging Review April/May/June/July MS Pigging on SML 6-13-23 to 6-22-23 Hartwell Pro. 6180 east of Wrens Aiken Atlanta Wrens Pigging on WSL Pigging on SM2ndLL GA 7-6-23 to 7-13-23 5-26-23 Pro. 11269 south of Wrens Pro. 5731-East of Elmore Ocmulgee AL Ellerslie Hallgate Auburn Thomas

  13. Slide 13: SNG South System Maint. Review April/May/June/July

    SNG South System Maint. Review April/May/June/July Pipeline maint. SMLL MS 4-17-23 to 5-4-23 SMLL Pipeline remediation Seg. 460 capacity of 1,995 6-5-23 to 6-12-23 PL. Maint. relocation WSL Seg. 560 capacity of 719 Hartwell Mdth/d impacted 30 Mdth/d 4-26-23 to 5-5-23 Pro. 2303 West of Auburn Mdth/d

  14. Slide 14: SNG South System Maint. Cont. April/May/June/July

    SNG South System Maint. Cont. April/May/June/July MS SML Pipeline remediation 6-13-23 to 6-17-23 Seg. 560 capacity of 719 Hartwell Pipeline maint. Pressure test Mdth/d impacted 60 SM3rdLL Aiken Mdth/d Atlanta 5-5-23 to 5-20-23 Pro. 13886 Ocmulgee to Wrens SESH maintenance Seg. 430 capacity of 2,283

  15. Slide 15: SNG South Louisiana System Pigging Review April/May/June/July

    SNG South Louisiana System Pigging Review April/May/June/July Gwinville Pearl River Pigging on FGLL 7-24-23 to 7-28-23 Pro. 18672-north of Pearl River MS LA Franklinton Pigging on FGL 4-25-23 to 4-26-23 Pro. 30904-north of Franklinton West Leg White Castle Toca East Leg Shadyside Compressor Station

  16. Slide 16: SNG South Louisiana System Maint. Review April/May/June/July

    SNG South Louisiana System Maint. Review April/May/June/July Gwinville Pearl River PL. Maint. on FGL 5-30-23 to 6-6-23 PL. Maint. Pressure test on North of Franklinton WCFLL Seg. 360 cap. Of 1,124 5-9-23 to 6-20-23 MS Mdth/d impacted 50 Mdth/d LA Seg. 350 capacity of 701 Franklinton 3 Mdth/d impacte

  17. Slide 17: EEC line April/May/June/July

    EEC line April/May/June/July Chattanooga Rome Hartwell SC Muldon North System Bell Mills GA MS McConnells Tarrant Atlanta Aiken Reform DeArmanville Providence Pell City Hall Gate Wrens Louisville Ocmulgee Pickens Ellerslie Bear Creek Onward Auburn Thomaston Logansport Elba Rankin Bay Springs Selma E

  18. Slide 18: SNG North System Pigging Review remainder of year

    SNG North System Pigging Review remainder of year Chattanooga Huntsville Rome AL Muldon Storage Atlanta Pigging on LL Tarrant Bell Mills 9-19-23 to 9-27-23 MS McConnells Pell City Pro.18556-east of Logansport Reform DeArmanville Providence Louisville Pickens GA Onward Bear Creek Storage AL Loganspor

  19. Slide 19: SNG North System Maint. Review remainder of year

    SNG North System Maint. Review remainder of year Chattanooga Muldon Shut-in test Huntsville 10-3-23 to 10-9-23 Bear Creek Shut-in test Restrictions first into ISS then Rome 10-17-23 to 9 AM 10-24-23 Restrictions first into ISS then CSS-not to exceed 36% of CSS AL DIQ /DWQ Hokes Bluff line Pipeline C

  20. Slide 20: SNG South System Pigging Review Remainder of the year

    SNG South System Pigging Review Remainder of the year MS Hartwell Aiken Atlanta Pigging on SM2ndLL 9-12-23 to 9-16-23 Pro. 6315 east of Elmore GA Wrens Ocmulgee Hallgate AL Ellerslie Auburn Thomaston Elba Selma Elmore Gallion Riceboro York Holy Trinity Pigging on Brunswick line Enterprise 8-1-23 to

  21. Slide 21: SNG South System Maint. Review Remainder of the year

    SNG South System Maint. Review Remainder of the year MS SMLL Pipeline replacement 9-25-23 to 10-4-23 Hartwell Seg. 480 capacity of 1,816 Aiken Mdth/d impacted 85 Atlanta Mdth/d Wrens Pro. 30224 west of Ellerslie GA Ocmulgee Hallgate AL Ellerslie Auburn Thomaston Elba Gallion Selma Elmore PL. Maint.

  22. Slide 22: SNG South Louisiana System Maint. review Remainder of year

    SNG South Louisiana System Maint. review Remainder of year Gwinville Pearl River Unit panel upgrades at Franklinton 8-14-23 to 11-10-23 MS LA Franklinton West Leg White Castle Toca East Leg Shadyside Compressor Station Southern will be conducting other general Storage Field maintenance during this p

  23. Slide 23: EEC line 2023 remainder of the year

    EEC line 2023 remainder of the year Chattanooga Rome Hartwell SC Muldon North System Bell Mills GA MS McConnells Tarrant Atlanta Aiken Reform DeArmanville Providence Pell City Hall Gate Wrens Louisville Ocmulgee Pickens Ellerslie Bear Creek Onward Auburn Thomaston Logansport Elba Rankin Bay Springs

  24. Slide 24: Gas Control Contacts

    Gas Control Contacts Reese Hart – Manager – (713) – 420 – 4774 (office) – (832) – 248-2937 (cell) – Maurice_hartIII@kindermorgan.com Kal Dankovich – Outage Coordinator – (205) – 533 – 4795 (cell) – kalman_dankovich@kindermorgan.com Jimmy Reese – Lead Controller – (205) – 577 – 3204 (cell) – jimmy_re

  25. Slide 25: Questions?

    Questions? 25

Kinder Morgan — Corporate Update (April 2023) on 6ix