Slide 1: Air Quality Management
ArcelorMittal South Africa Limited Air Quality Management Siegi Spänig 25 November 2014
Slide 2: Overview of Operations
ArcelorMittal South Africa Overview of Operations • Flat Steel Products • Vanderbijlpark Works – 3.2 Mtpa* Pretoria Johannesburg • Saldanha Works – 1.25 Mtpa* Vanderbijlpark Vereeniging • Long Steel Products Newcastle • Newcastle Works – 1.9 Mtpa* • Vereeniging Works – 0.4 Mtpa* Durban South • Coke
Slide 3: Current Status
Current Status • Two facilities located in VTAPA of which Vanderbijlpark is the most challenging • No postponement applications submitted to date, but there are challenges regarding 2020 standards • Three production facilities at Vanderbijlpark taken out of operation due to compliance challenges and
Slide 4: AMSA Particulate emissions from point sources (kg/tonne LS)
AMSA Particulate emissions from point sources (kg/tonne LS)
Slide 5: Vanderbijlpark Works SO2 emissions
Vanderbijlpark Works SO2 emissions In absolute terms and in kg per ton of Liquid Steel Specific emissions increased due to: • Increased S-content in raw materials • Changes in process configuration
Slide 6: Vanderbijlpark Works
-_ ArcelorMittal Vanderbijlpark Works
Slide 7: Vaal Triangle Airshed Priority Area: Emission Reduction Strategy and Interventions
VAAL TRIANGLE AIRSHED PRIORITY AREA EMISSION REDUCTION STRATEGY AND INTERVENTIONS
Slide 8: Vaal Triangle Airshed Priority Area: Emission Reduction Strategy and Interventions
VAAL TRIANGLE AIRSHED PRIORITY AREA EMISSION REDUCTION STRATEGY AND INTERVENTIONS
Slide 9: Vaal Triangle Airshed Priority Area: Additional Emission Reduction Interventions
VAAL TRIANGLE AIRSHED PRIORITY AREA ADDITIONAL EMISSION REDUCTION INTERVENTIONS
Slide 10: Vanderbijlpark Works Dust emission reduction
Vanderbijlpark Works Dust emission reduction
Slide 11: Point Source/Fugitive emissions vs Liquid Steel Production
Vanderbijlpark Works Point Source/Fugitive emissions vs Liquid Steel Production
Slide 12: Sinter Baghouse at AM Vanderbijlpark Works
Sinter Baghouse at AM Vanderbijlpark Works Installation completed in 2012 at a cost of R260 million.
Slide 13: Total cost of the bag house calculates to R 87.7m
Total cost of the bag house calculates to R 87.7m
Slide 14: Rehabilitation of Old waste disposal site
Rehabilitation of Old waste disposal site
Slide 15: Tip Station upgrade - sprays
“<— ArcelorMittal Tip Station upgrade - sprays
Slide 16: Vanderbijlpark Works - Open area rehabilitation - fugitive dust reduction
Vanderbijlpark Works - Open area rehabilitation ex - fugitive dust reduction ArcelorMittal Dust suppression trials 1 foads wathin the works. The purpose betind the [vias was to evaluate the performance of the applied therefore has iveited companies specialising in dust suppression to conduct trials
Slide 17: Vanderbijlpark Works - Open area rehabilitation - fugitive dust reduction
Vanderbijlpark Works - Open area rehabilitation Cin - fugitive dust reduction ArcelorMittal Open areas Before Before Before Before Before After After After After After
Slide 18: Rehabilitation in progress
Rehabilitation in progress
Slide 19: Dam 10 current status
Dam 10 current status 18
Slide 20: Dust Extraction System at Vereeniging Works
Dust Extraction System at Vereeniging Works Before (March 2007) After (January 2010) Completed in 2010 at a cost of R 230M
Slide 21: Newcastle Works
<= ArcelorMittal Newcastle Works
Slide 22: Saldanha Works
Saldanha Works “— ArcelorMittal
Slide 23: AMSA CO2 emissions
AMSA CO2 emissions In absolute terms and in t CO2 / t Liquid Steel
Slide 24: Questions?
Questions? Thank you!
Slide 25: ArcelorMittal
“_< ArcelorMittal