    September 2014 Presentation on the Waterberg Region Mining & infrastructure developments – an update on our prospects for growth

  2. Slide 2: Presentation Outline

    Slide 2: Presentation Outline

    PRESENTATION OUTLINE • Exxaro in brief • Coal market overview • About the Waterberg • Concluding remarks & discussion

  3. Slide 3: Exxaro's Group Strategy

    Slide 3: Exxaro's Group Strategy

    EXXARO’S GROUP STRATEGY 3 NON-CONTROLLED OWNER-CONTROLLED OPERATIONS OPERATIONS Coal Ferrous Energy • 19,98% in SIOC • Second largest coal • Mayoko Project • Underground coal • 44,18% in Tronox producer in RSA • AlloyStream™ gasification • 26% in Black • Three tied operations project Mountain • Six

  4. Slide 4: Exxaro Growth Portfolio

    Slide 4: Exxaro Growth Portfolio

    EXXARO GROWTH PORTFOLIO 4 2H14 • TCSA acquisition • GMEP ramp-up continues • Grootegeluk backfill phase 1 • Tshikondeni closure • Thabametsi mine phase 1 BFS* • Semi-coke BFS for two retorts • NCC disposal • Mayoko mining convention extension • FerroAlloys expansion 2015 • Belfast construction • Iny

  5. Slide 5: Overview of the Coal Market

    Slide 5: Overview of the Coal Market

    OVERVIEW OF THE COAL MARKET 5 Domestic market • Stable but not growing materially • Exxaro well positioned in all chosen market segments i.e. Power Generation, Metals, Reductants and Domestic Steam Coal • Exxaro’s Value-in-Use knowledge for the Metals and Reductants market is a strong differentiator

  6. Slide 6: Exxaro in the Waterberg

    Slide 6: Exxaro in the Waterberg

    EXXARO IN THE WATERBERG 6 South Africa Why is the Waterberg Eskom important? Exxaro Brownfields expansions How will we unlock value in the Greenfields potential Waterberg? Downstream opportunities Sustaining capi tal What needs to be done to make Internal enabling this happen? External enabling Powe

  7. Slide 7: Why Is the Waterberg Important?

    Slide 7: Why Is the Waterberg Important?

    WHY IS THE WATERBERG IMPORTANT? 7 To SOUTH AFRICA • Economic significance: o largest remaining coal resource o catalyst to the unlocking of the northern mineral belt (SIP1) and o location for electricity generation (SIP 9) • Social – 1st major post-apartheid new urban centre To ESKOM • Security of c

  8. Slide 8: Exxaro Coal

    Slide 8: Exxaro Coal

    EXXARO COAL Exxaro Coal is well positioned in the South African coal market, and currently has the largest resource base and is the third largest producer of coal companies operating in the region 8 2012 South African coal production 250 16.0, 7% Exxaro Coal was the third largest coal producer in 20

  9. Slide 9: Current Mpumalanga Operating BUs and Life Extension Projects

    Slide 9: Current Mpumalanga Operating BUs and Life Extension Projects

    CURRENT MPUMALANGA OPERATING BUs AND LIFE EXTENSION PROJECTS 9 Mafube (JV) Arnot Tshikondeni Current Operations: Current Operations: Current Operations: 2 years 19 years 2 months Life Ex: NGD (+15 years) Power station life: 9-14 years Inyanda NBC Current Operations: Current Operations: 8 months 4 ye

  10. Slide 10: Future Mpumalanga Operating BUs and Life Extension Projects

    Slide 10: Future Mpumalanga Operating BUs and Life Extension Projects

    FUTURE MPUMALANGA OPERATING BUs AND LIFE EXTENSION PROJECTS 10 Mafube (JV) Arnot Tshikondeni Current Operations: Current Operations: Current Operations: 2 years 19 years 2 months Life Ex: NGD (+15 years) Power station life: 9-14 years Inyanda NBC Current Operations: Current Operations: 8 months 4 ye

  11. Slide 11: Vision and Strategy of Waterberg

    Slide 11: Vision and Strategy of Waterberg

    VISION AND STRATEGY OF WATERBERG 11 Vision: We will create exceptional value by: • being an innovative, integrated and synergistic carbon company • utilising and developing excellence in people, value adding processes and structures to produce sustainable returns Value growth • Brownfields expansion

  12. Slide 12: The Waterberg Coalfield - Overview

    Slide 12: The Waterberg Coalfield - Overview

    THE WATERBERG COALFIELD - OVERVIEW 12 Vital statistics Dimensions: • Stretches 40km from N to S and 88km E to W • Extends westwards into Botswana Geological characteristics: • Ecca group of coal deposits • 75,7 billion tonnes of in-situ inferred resources (Upper & Middle Ecca) • More than 50% of the

  13. Slide 13: Waterberg Coalfield Mapped

    Slide 13: Waterberg Coalfield Mapped

    WATERBERG COALFIELD MAPPED 13 Zoetfontein Fault Botswana Grootegeluk Daarby Fault Mine Deep Coal (250m below surface) Eenzaamheid Fault Shallow Coal Open Pit Waterberg Coalfield is fault bounded: • Zoetfontein fault along the Northern side • Eenzaamheid fault along the Southern boundary • Daarby fau

  14. Slide 14: Exxaro in the Waterberg

    Slide 14: Exxaro in the Waterberg

    EXXARO IN THE WATERBERG 14 Botswana Waterberg North Zonderwater Thabametsi Grootegeluk MCWAP Phase 1 by MCWAP Upgrade 2015 Phase 2 by rail capacity 2020 by 2018/19

  15. Slide 15: Geological Complexity of the Waterberg Coalfield

    Slide 15: Geological Complexity of the Waterberg Coalfield

    GEOLOGICAL COMPLEXITY OF THE WATERBERG COALFIELD 15 15

  16. Slide 16: Comparative Cross-Section Through the Waterberg Coalfield

    Slide 16: Comparative Cross-Section Through the Waterberg Coalfield

    COMPARATIVE CROSS-SECTION THROUGH THE WATERBERG COALFIELD 16 Volksrust Formation •The Volksrust formation consists of a thick interbedded coal / shale deposit •In-situ average heat value ~11.7 Mj/Kg for benches 2 to 5 •Eskom requirement > 20 Mj/Kg •Not suitable to mine as a ROM product to Eskom 87m

  17. Slide 17: Grootegeluk's Current Operations

    Slide 17: Grootegeluk's Current Operations

    GROOTEGELUK’S CURRENT OPERATIONS Other local SSCC 10.3% Ash GG1 Export BENCH BENCH 1 GG6 PSC 35% Ash BENCH 2 GG2 Domestic BENCH 3 Eskom Eskom GG8 Medupi Matimba BENCH 4 GG7 Domestic BENCH 5 GG3 PCI BENCH 6 11% Ash BENCH 7a BENCH 7b BENCH 8 Domestic Small nuts BENCH 9a,b 15% Ash BENCH 10 BENCH 11 GG4

  18. Slide 18: Understanding Grootegeluk Plant Capacities and Products

    Slide 18: Understanding Grootegeluk Plant Capacities and Products

    UNDERSTANDING GROOTEGELUK PLANT CAPACITIES AND PRODUCTS 18 Plant ROM Process SSCC/ Exp PSC Met Coal GG 1 15.0 Double Stage 1.65 4.85 GG 2 9.2 Single Stage 4.28 GG 3 2.0 Crush & Screen 1.96 GG 4/5 2.6 Single Stage 1.27 1.50 GG 6 Ph 1 5.5 Double Stage 0.75 1.67 GG 7 7.0 Crush & Screen 6.86 GG 8 19.0 S

  19. Slide 19: Grootegeluk – History of Growth and Value Addition

    Slide 19: Grootegeluk – History of Growth and Value Addition

    GROOTEGELUK – HISTORY OF GROWTH AND VALUE ADDITION 19 OC Pit (1980) GG2 GG3 (1992) (1990) GG4/5 (1996,1998) GG1 (1980) GG6 (2006) Semi Coke - P1 (2007) GG7/8 (2014) Multi products = 18.5 million annual tonnes (pre-Medupi) Resources = 4.7 billion tonnes

  20. Slide 20: Waterberg Landscape in Summary

    Slide 20: Waterberg Landscape in Summary

    WATERBERG LANDSCAPE IN SUMMARY 20 • Grootegeluk ~ 4.7 Bn tonnes and > 50 years LoM at current Massive resource rates base • Thabametsi ~ 4.8 Bn tonnes, > 50 Years LoM @ GG rates • Waterberg North ~ 2.2 Bn tonnes • Turfvlakte East ~ included in GG • Semi Soft Coking Coal – 10.3% Ash Reserve character

  21. Slide 21: Content

    Slide 21: Content

    CONTENT 21 Strategy Why is the Waterberg Game plan important? Geology Brownfields expansions How will we unlock value in the Greenfields potential Waterberg? Downstream opportunities Sustaining capi tal What needs to be done to make Internal enabling this happen? External enabling Power station What

  22. Slide 22: Exxaro's Waterberg Development Plan

    Slide 22: Exxaro's Waterberg Development Plan

    EXXARO’S WATERBERG DEVELOPMENT PLAN 22 Brownfields Greenfields Downstream GG7+8 Thabametsi North Phase Semi-Coke plant • PSC, +14.6Mtpa 1 • Retorts 1-4 operational GG6 Expansion • GG ROM & IPP Coal, • Retorts 5+6: Semi- • Export, +1.5Mtpa +3.5Mtpa Coke, +72ktp Thabametsi North Phase • Retorts 7+8: S

  23. Slide 23: GMEP Expansion – Visual

    Slide 23: GMEP Expansion – Visual

    GMEP EXPANSION – VISUAL Animated fly over 23 Note, This is a hyperlink to the GMEP fly-over

  24. Slide 24: Brownfields Project Summary: GG6 Expansion

    Slide 24: Brownfields Project Summary: GG6 Expansion

    BROWNFIELDS PROJECT SUMMARY Upper Pit 24 GG6 Expansion Increased rate of Pit Liberation Conversion of GG 2 plant to enable full double stage washing Additional SSCC / Export Coal ~ 1.5Mtpa Changes required to current load-out station

  25. Slide 25: Brownfields Project Summary: Pit Bottom Bench 13, GG9/10

    Slide 25: Brownfields Project Summary: Pit Bottom Bench 13, GG9/10

    BROWNFIELDS PROJECT SUMMARY Pit Bottom 25 Bench 13 Implementation of GG6 Expansion and Bench 5 liberation to supply Medupi enables Pit Bottom liberation of B9B/11/13 Bench 13 suitable as Metallurgical ROM feed Full-scale mining test successfully completed GG9/10 • Supplement GG 4/5 Met coal producti

  26. Slide 26: Greenfields Project Summary: Thabametsi

    Slide 26: Greenfields Project Summary: Thabametsi

    GREENFIELDS PROJECT SUMMARY Thabametsi 26 BACKGROUND Northern Thabametsi development phase Complex • Grootegeluk ROM replacement (Sulpher) LT access Thabametsi North Phase 1 • 3,5Mtpa coal supply to IPP 600MW Thabametsi North Phase 2 Initial access • Eskom Mpumalanga PSC, +8.0Mtpa. SSCC, +2.2Mtpa. T

  27. Slide 27: Downstream Opportunities

    Slide 27: Downstream Opportunities

    DOWNSTREAM OPPORTUNITIES Semi-Coke, Market Coke 27 Semi-Coke Phase 2 Expand 4 additional retorts (2+2) inline with existing plant Feedstock supply from GG9/10 ( 220ktpa coal required) Retorts 5+6: Semi-Coke, +72ktpa Retorts 7+8: Semi-Coke, +72ktpa Market Coke Phase 1 • Feedstock from GG6 Expansion (

  28. Slide 28: Strategy: Waterberg Project Contributions

    Slide 28: Strategy: Waterberg Project Contributions

    STRATEGY: WATERBERG PROJECT CONTRIBUTIONS 28 Grootegeluk TM Reductants Project Date* PSC SSCC Met IPP PSC Exp. SSCC Met S-C MC Existing Operations Current      GG9/10 2016  Semi-Coke 5&6 2018   GG6 Expansion 2019   Semi-Coke 7&8 2019   Market Coke ph 1 2020   Thabametsi North Ph 1 2021

  29. Slide 29: Content

    Slide 29: Content

    CONTENT 29 Strategy Why is the Waterberg Game plan important? Geology Brownfields expansions How will we unlock value in the Greenfields potential Waterberg? Downstream opportunities Sustaining capital What needs to be done to make Internal enabling this happen? External enabling Power station What

  30. Slide 30: Exxaro's Waterberg Development Plan

    Slide 30: Exxaro's Waterberg Development Plan

    EXXARO’S WATERBERG DEVELOPMENT PLAN 30 Sustaining capital Internal enabling External enabling (2015-2019) • In-pit crusher and • TFR ramp-up • Truck replacement conveyer (IPCC): • TCSA (Entitlement) Strategy – R823m Improve Ex-pit tempo • Water (MCWAP 1 / • Shovel replacement • Load-out station MCWA

  31. Slide 31: Internal Enabling Project Summary: IPCC

    Slide 31: Internal Enabling Project Summary: IPCC

    INTERNAL ENABLING PROJECT SUMMARY: IPCC* * In Pit Crushing and Conveying 31 Note, This is a hyperlink to the Semi Mobile transporter

  32. Slide 32: Internal Enabling Project Summary: IPCC

    Slide 32: Internal Enabling Project Summary: IPCC

    INTERNAL ENABLING PROJECT SUMMARY: IPCC* * In Pit Crushing and Conveying 32 BACKGROUND Semi Mobile Crushers Bench 5 implemented - GMEP Implement Upper Bench System (Bench 2-4) Counter travel distance increases due to pit advance Optimise long-term capital (fleet increases) Manage long-term operat

  33. Slide 33: Internal Enabling Project Summary: LOS

    Slide 33: Internal Enabling Project Summary: LOS

    INTERNAL ENABLING PROJECT SUMMARY: LOS* * New load-out station 33 BACKGROUND • Current facility not adequate (D8) • Upgrade rail: 26 tonnes per axle 200-wagon train • Rapid multi-product load-out station • Linked to GG10 Expansion • Could provide for Thabametsi Export Coal

  34. Slide 34: MCWAP and Waterberg Water Requirement

    Slide 34: MCWAP and Waterberg Water Requirement

    MCWAP AND WATERBERG WATER REQUIREMENT 34 Phase 2 Phase 1

  35. Slide 35: Waterberg Plan: TFR Stages

    Slide 35: Waterberg Plan: TFR Stages

    WATERBERG PLAN: TFR STAGES 35 *TFR values from TFR 2013 Aug presentation

  36. Slide 36: Waterberg Rail Ramp-Up

    Slide 36: Waterberg Rail Ramp-Up

    WATERBERG RAIL RAMP-UP 20.0 WB - Logistic mix 16.0 14.0 12.0 10.0 8.0 6.0 4.0 2.0 |2014 | |2015 | |2016 | |2017 | |2018 | |2019 | |2020 | |2021 | |2022 | |2023 | |2024 |2025 | |2026 | |2027 | |2028 |2029 | |2030 ™ Road O7 08 O07 08 08 08 08 08 08 09 0g 09 0.9 09 09 09 0.9 @ Rail - MPU - - - - - - -

  37. Slide 37: Projects: GG Capex Requirements

    Slide 37: Projects: GG Capex Requirements

    PROJECTS: GG CAPEX REQUIREMENTS 2015 39 GG Projects 2015= R 3.061 Billion R 18,000 16,091 R 16,000 R 14,000 R 12,000 R Million R 10,000 R 8,000 5,261 R 6,000 3,061 3,440 R 4,000 2,579 R 2,000 1,750 R0 2015 2016 2017 2018 2019 5 Years RISK 63 58 62 66 71 320 GROWTH 743 811 2,784 1,501 774 6,613 IMPRO

  38. Slide 38: Content

    Slide 38: Content

    CONTENT 40 Strategy Why is the Waterberg Game plan important? Geology Brownfields expansions How will we unlock value in Greenfields potential the Waterberg? Downstream opportunities Sustaining capital What needs to be done to Internal enabling make this happen? External enabling What is the impact

  39. Slide 39: Sales Volumes from GG Footprint

    Slide 39: Sales Volumes from GG Footprint

    SALES VOLUMES FROM GG FOOTPRINT 41 Total sales volume 35 000 15 000 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 GG TM 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 GG 20.1 25.5 24.4 26.6 31.0 31.2 31.2 31.2 31.2 31.2 31.

  40. Slide 40: Sales Volumes from GG Footprint

    Slide 40: Sales Volumes from GG Footprint

    SALES VOLUMES FROM GG FOOTPRINT 42 AMSA and Domestic 4000 2000 0 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 AMSA Domestic 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 AMSA 1.8 1.6 1.7 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.

  41. Slide 41: Entitlement vs Production Capacity

    Slide 41: Entitlement vs Production Capacity

    ENTITLEMENT VS PRODUCTION CAPACITY 44 The increase in ... creates a platform for existing and available entitlement ... future growth projects 15 15 3 10 Export production (Mtpa) 10 4 Entitlement (Mtpa) 5 5 1 2 0 Exxaro Exxaro TCSA Exxaro Potential 0 Base Leased (TFR @ Baseline Inyanda Mafube Belfas

  42. Slide 42: In Conclusion

    Slide 42: In Conclusion

    IN CONCLUSION 45 24Mt rail capacity by 2018 The Waterberg is a strategic socio- MCWAP 1 by 2015 and MCWAP 2 by 2010 economic catalyst Increase export volumes and forex GG 6, GG9, GG10, brownfield expansions Semi Coke and Market Coke expansions We have prepared ourselves for growth through a robust p

  43. Slide 43: Thank You

    Slide 43: Thank You

    THANK YOU WE ARE POWERING POSSIBILITY!