Euromax Resources Ltd. · TSXV:EOX
Euromax Resources — Investor Presentation (June 2014)
22 slides from Euromax Resources's investor presentation, June 2014
Slide 1: It's all about execution…
It’s all about execution… Presentation - June 2014
Slide 2: It's all about Execution
It’s all about Execution ! A simple to develop, homogenous orebody with metallurgy receptive to basic, traditional, low-cost processing ! Located in a developed economic zone in the heart of Europe with all of the attendant infrastructure ! Overwhelming local, national and supranational support ! A
Slide 3: Seizing the Opportunity
Seizing the Opportunity • In March 2012 European Goldfields (EGU) was sold for US$2.5 billion • The former EGU Management identified a copper gold porphyry (Ilovitza) very similar to its Greek flagship project Skouries, on the same geological belt and of a similar age, just 100km to the North, over
Slide 4: PFS Highlights
PFS Highlights • NPV(5%) of US$675 million with an IRR of 19% before tax and an after tax NPV(5%) of US$558 million and after tax IRR 16% • Maiden Mineral Reserve announced of 225 Mt containing 2.45 Moz Au and 905 Mlb Cu* Throughput 10 Mtpa Mine life 23 yrs Strip ratio 0.7 : 1 Avg. process recovery
Slide 5: Geology & Resources
Geology & Resources • Gold-Copper porphyry with classic porphyry zonation and minimal post mineral overprinting in open pit material • Homogenous mineralisation with good grade continuity • Pit constrained M+I Mineral Resources of: o 237 Mt sulphide grading 0.33 g/t Au and 0.22% Cu o 36 Mt oxide gra
Slide 6: Mining and Reserves
Mining and Reserves • Mining by conventional open pit using large scale mining fleet • Strip Ratio of 0.7:1 • 10Mtpa operation using 100t trucks in a highly competitive mining equipment market with leasing a possibility (not in PFS) • PFS defines Maiden Probable Mineral Reserve of: o 209 Mt sulphide
Slide 7: Simple & Proven Processing
Simple & Proven Processing • Crushing at pit exit, crushed ore transported to plant using a conveyor • SAG and ball mill grinding SAG Mill Ball Mills ROM Ore Crushing Conveyor • Flotation of Cu-Au concentrate followed by tailings re-treatment to recover further Au to doré Tailings • Oxide stockpile
Slide 8: Tailings Management Facility
Tailings Management Facility • Waste rock from the open pit used for embankment construction Access road from plant Cofferdam Pit • 10Mt of waste rock mining brought forward in to pre-production to allow construction of starter dam • Standard downstream construction • Crusher located at starter dam
Slide 9: Layout & Infrastructure
. ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! ! . . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! ! . . ! . ! . ! . ! . ! ! . ! . ! . ! . . ! . ! . ! . ! . ! . ! . ! . ! . ! . ! ! . . ! . ! . ! ! . . !
Slide 10: Costs and Sensitivities
Costs and Sensitivities Pre-tax NPV and IRR Sensitivity to Metal Prices Gold Copper NPV @ 0% NPV @ 5% NPV @ 7.5% IRR (US$/oz) (US$/lb) (US$ m) (US$ m) (US$ m) (%) 1,100 2.50 757.5 284.3 146.4 11.4% 1,250 3.00 1,420.8 675.1 459.0 18.6% 1,400 3.50 2,084.0 1,066.0 771.6 24.9% Capital Cost Summary Opera
Slide 11: Embracing In-Country Expertise
Embracing In-Country Expertise • We have embraced the considerable depth and expertise in Macedonia and the Balkans by establishing a Technical Advisory Committee (TAC) to oversee and give guidance on the relevant technical disciplines involved in developing the project and form the core of our owne
Slide 12: Financing Plan
Financing Plan • The guiding principle behind our Financing Plan is to minimise shareholder dilution and it is being executed in two phases: o Phase 1 –The full FS/FEED period from now until construction; Q3 2016 o Phase 2 – To fund construction Phase 1 • Given the disparity between the Company’s ma
Slide 13: Financing Plan
Financing Plan Phase 2 • Phase 2 Financing will be initiated upon the filing of the NI 43-101 Report • The target funding for Phase 2 will be US$350 million (based on the indicative UFK debt carrying capacity) • Initiation of the Phase 2 financing will encompass the appointment of the Project Financ
Slide 14: Macedonia – A symbiotic relationship
Macedonia – A symbiotic relationship Importance of Euromax to Macedonia • Ilovitza is the first greenfield development in the Balkans region for over 20 years • Government recognize importance of exploiting natural resources • Ilovitza in production: o A transformational contributor to balance of pa
Slide 15: Streamlining & Focusing Resources
Streamlining & Focusing Resources • During the 4th Qtr 2013 and 1st Qtr 2014 – Management undertook a root and branch strategic review to ensure that all of its resources, both human and financial were deployed to the maximum effect in delivering Ilovitza and as such generating tangible returns to s
Slide 16: A Definitive Corporate & Financing Plan
A Definitive Corporate & Financing Plan Asset Construction based financing FS, Detailed Listings Engineering & Project Finance Design Q2 – 2014 Q3- 2014 2016 • Completion of non-core asset • Formally Engage PF banks • Drawdown project finance sales and corporate restructuring through UFK umbrella •
Slide 17: A Proven Board & Management Team
A Proven Board & Management Team Martyn Konig Steve Sharpe Varshan Gokool Pat Forward Tim Morgan-Wynne Randal Matkaluk Non-Executive President, CEO & Director CFO & Director COO & Director Non-Executive Non-Executive Chairman Director Director Previously SVP Business Previously VP and Previously VP
Slide 18: Corporate Information
Corporate Information Capitalization Overview Market cap C$14 M Share price against Market Vector Junior Gold Miners Index (GDXJ) – Closing Price (4 June 14) C$0.16 1 Jan ’13 – 30 May ’14 52 Week High C$ 0.42 52 Week Low C$ 0.09 Shares Basic 85.3 M Shares Fully Diluted 97.2 M Cash C$3.0 M Debt None
Slide 19: It's all about Execution…
It’s all about Execution… # Robust project economics # Simple mining & processing # Excellent logistics # Readily financeable without significant dilution # Unprecedented local, national & international support # A management team that has done it all before… 19 It's all about execution…
Slide 20: www.euromaxresources.com
www.euromaxresources.com Steve Sharpe President & CEO E: ssharpe@euromaxresources.co.uk T: +44 203 667 2970 Karen Coke Investor Relations Manager E: kcoke@euromaxresources.co.uk T: +44 203 667 2970 Tom Panoulias North American Representative E: tpanoulias@euromaxresources.co.uk T: +1 416 294 5649
Slide 21: Cautionary Statements
Cautionary Statements No securities commission or similar authority in Canada or the United States has reviewed or in any way passed comment on this presentation. No information in this presentation shall constitute an invitation to invest in Euromax Resources Ltd. (the "Company") or its securities
Slide 22: Resource & Reserve Statement
Resource & Reserve Statement Mineral Reserve (Effective June 2014) Grade Contained Metal Tonnage (Kt) Classification Au (g/t) Cu (%) Au (Koz) Cu (Klb) Sulphide (Fully Diluted) Probable 208,650 0.34 0.20 2,276 905,100 Oxide (Fully Diluted) Probable 16,230 0.33 - 172 - Mineral Resource (Effective 27 N
Euromax Resources — Investor Presentation (June 2014) on 6ix