  1. Slide 1: Woodlawn Eco-Precinct Community Liaison Committee Meeting

    WOODLAWN ECO-PRECINCT COMMUNITY LIAISON COMMITTEE MEETING 17th April 2025

  2. Slide 2: Acknowledgement of Country

    ACKNOWLEDGEMENT OF COUNTRY Veolia acknowledges Ngunnawal people as the traditional custodians of the lands and waters in which we live and work and their continuing connection to land, water and community. We pay respects to their Elders past, present and emerging and any first nations people presen

  3. Slide 3: Meeting Agenda

    MEETING AGENDA ITEM TOPIC 1 Introduction and welcome 2 Apologies 3 Actions from previous meeting 4 Eco-Precinct Update ● Operations ● Environmental Compliance Update 5 ARC presentation 6 DPHI - Rob Sherry (RS) - NSW DPHI Acting Director Compliance ● The role of the DPHI ● What's the difference betwe

  4. Slide 4: Introduction and Welcome

    INTRODUCTION AND WELCOME

  5. Slide 5: Meeting Attendance/Apologies

    MEETING ATTENDANCE/APOLOGIES DATE Thursday 17th April 2025 Time 5:00pm to 7.00pm LOCATION Woodlawn Conference Room 619 Collector Road, Tarago NAME PRESENT NAME PRESENT Jamie Seaton (JS) (Chair) Carmen Leocherer - (CL) (Veolia) CR Keith Smith (KS) (GMC Councillor) Kathryn Whitfield (KLW) (Veolia ARC

  6. Slide 6: Actions from Last Meeting

    ACTIONS FROM LAST MEETING

  7. Slide 7: Meeting Actions

    MEETING ACTIONS ITEM ACTION ASSIGNED TO 1 ACTION: SMc to develop a FAQ for inclusion on the website within 4 weeks. Intent is for the existing SMc (Veolia) webform to continue to be used for new questions raised by the community and FAQs updated as needed. 2 ACTION: RC to revisit status of audit rep

  8. Slide 8: Eco-Precinct Operational Update

    Traffic Lights Attention required ECO-PRECINCT Area of focus OPERATIONAL UPDATE Going well

  9. Slide 9: Positive outcomes since last meeting: Wins

    ECO-PRECINCT Positive outcomes since last meeting WINS! • COMMUNITY - Veolia Mulwaree Trust gave out over $730,000 in 2025 and has just approved another $250,000 in the March 2025 round. • WATER MANAGEMENT - All dams continue to reduce further below freeboard. • REGULATORS - Very productive F2F meet

  10. Slide 10: Operational Update Performance

    OPERATIONAL UPDATE PERFORMANCE Bioreactor Landfill - Licence tonnage YTD Waste Processed (licence 7 Sep 2024 - 13 Apr 2025) ● Regional Waste 70,547 t - (licence 125,000t) ● Sydney Waste 432,248 t - (licence 900,000t) ○ Both are within licence limits for Sep 2024 - Sep 25 period Mechanical Biological

  11. Slide 11: Water Management: Storage status and location

    WATER Storage status and location MANAGEMENT Coffer Dam #2 ED1 Plant Collection Dam Coffer Dam #1 Office area Leachate Treatment Plant ED3N 1-4 Plant collection catchment ED3S ED3SS Western Ridge catchment Bioreactor Void catchment

  12. Slide 12: Water Management: Freeboard Management

    WATER MANAGEMENT FREEBOARD MANAGEMENT * Note: 1 L/s = 86,400 L/day @ 20% evaporation = 17,280 L/day

  13. Slide 13: Water Management: Treated Leachate Strategy Summary

    WATER MANAGEMENT TREATED LEACHATE STRATEGY SUMMARY Short term next 18 months ● Temporary tank farm - 48 ML - 4 installed and approved for use (1 tank full) ● Integrity testing Coffer dam 1 - March and April 2025 ● Permanent tank farm 1 - 48ML - Approval application submitted - July 2025 ● Permanent

  14. Slide 14: Eco-Precinct Operational Update: Bio-Energy

    ECO-PRECINCT OPERATIONAL UPDATE BIO-ENERGY Bioenergy 2025 Biogas Capture ● Gas collected 01/25-03/25: 9,760,797 m3 - (46% methane) ● Energy Generation 01/25-03/25: 13,751 MWh ● In 2025, the captured emission is equivalent to removing 78,831 cars off the road

  15. Slide 15: Eco-Precinct Operational Update: Odour Complaints

    ECO-PRECINCT OPERATIONAL UPDATE ODOUR COMPLAINTS ● Odour complaints and events have have not significantly changed compared to the same time last year. ● Odour movement is heavily dependant on weather conditions. Storms in February adding to odour events ● Colder weather conditions show an increase

  16. Slide 16: Eco-Precinct Operational Update: Odour Management

    ECO-PRECINCT OPERATIONAL UPDATE ODOUR MANAGEMENT Completed ● Waste and rock interface gas collection in the bioreactor along the void perimeter (1000 m of horizontal gas collection) in operation (green lines) since August 2024. In the process of planning replicated system on the new lift. ● Monthly

  17. Slide 17: Environmental Compliance Update

    ENVIRONMENTAL COMPLIANCE UPDATE

  18. Slide 18: Operational Update: EPA Clean Up Notice

    OPERATIONAL UPDATE EPA CLEAN UP NOTICE EPA Clean Up Notice EPA issued Woodlawn a Clean Up Notice freeboard exceedance ○ All tanks are in use. Veolia is seeking to maintain these after November 2025, until additional measures are constructed (permanent tank farms, Reverse Osmosis) EPA issued Woodlawn

  19. Slide 19: Independent Odour Audit Updates

    INDEPENDENT ODOUR AUDIT UPDATES ACTION STATUS COMPLETION DATE ● Odour mitigation from the void Veolia have engaged a landfill engineer to undertake a review of Engaged Tonkin to undertake the landfill operating practices. ● Active tipping face Site visit 15 May This review will address odour mitigat

  20. Slide 20: Environmental Compliance Update: PA Modifications & Post Approval Applications

    ENVIRONMENTAL COMPLIANCE UPDATE PA MODIFICATIONS & POST APPROVAL APPLICATIONS APPROVAL TYPE DESCRIPTION STATUS MP 10_0012 Modification Modify the existing project approval for the Bioreactor and MBT to: Submission with DPHI • Originally to construct an approximately 100 ML dam at the Bioreactor to h

  21. Slide 21: Environmental Compliance Update: PA Modifications & Post Approval Applications

    ENVIRONMENTAL COMPLIANCE UPDATE PA MODIFICATIONS & POST APPROVAL APPLICATIONS APPROVAL TYPE DESCRIPTION STATUS MP 10_0012 Modification Thermal treatment facility. Thermally treat brine and treated leachate liquid In pre-feasibility studies (TBC) using waste heat from the existing on-site power stati

  22. Slide 22: ARC Project Update

    ARC PROJECT UPDATE

  23. Slide 23: ARC Submissions Update

    ARC Submissions UPDATE Planning Progress • Submissions Report and Amendment Report are in final review stages • Related technical studies: 11 completed and 5 in the final stages of review • Actively assessing what the Energy from Waste policy framework policy review means for our project timeline an

  24. Slide 24: DPHI Presentation

    DPHI presention

  25. Slide 25: DPHI

    DPHI NSW Department of Planning Housing Infrastructure (JH to introduce) ● The role of the DPHI ● What's the difference between a CLC and a CCC

  26. Slide 26: EPA Presentation

    EPA Presentation

  27. Slide 27: What is a seep and a pathway?

    What is a seep and a pathway? Seep - Is an Engineering term - It refers to soil around a dam that acts like a sponge, the seep can expand as the water level rises and shrinking when it lowers. Pathway - In this instat refers to possible pathways from a seep to the environment. Cracks in rock, porous

  28. Slide 28: EPA

    EPA NSW EPA representatives: ● Veolia’s - Hydrological Risk Assessment (HRA) ● EPA - HRA review and water sampling program ● What is Veolia required to do next ● Questions

  29. Slide 29: Community Q&A

    COMMUNITY Q&A

  30. Slide 30: CLC Questions

    CLC QUESTIONS ● List of questions have been sent to Veolia - will be answered with the minutes ● Are there any questions for Veolia from the CLC

  31. Slide 31: CLC New Actions

    CLC NEW ACTIONS ACTION STATUS COMPLETION DATE ● INSERT TEXT Insert text Insert tex

  32. Slide 32: Next Meeting

    NEXT MEETING The next Community Liaison Meeting will be held at the Woodlawn Eco-Precinct Office - TBC agreed.

  33. Slide 33: Vision for Woodlawn (Appendix 1)

    VISION FOR WOODLAWN appendix 1

  34. Slide 34: Vision for Woodlawn

    ECO-PRECINCT 20 YEAR VISION FOR WOODLAWN We will shortly be releasing a community flyer to show what we’ve achieved in the past 20 years of Woodlawn and to highlight our key areas of focus for the next 20 years. These areas of future focus include: • Operational improvements: We’ll continue to devel