Slide 1: Poised for Delivery
© Euromax RESOURCES Poised for Deliveny BS.
Slide 2: The Ilovica Package
© Euromax RESOURCES The llovica Package In the heart of Europe 83,000 oz Au/yr + 16,000 t Cu/yr Experienced Management Team EBRD - shareholder Major Construction Group Partner EIA Approved Mining Concession Stakeholder support German Supported Project Financing 90% of Capex Financing Arranged Low St
Slide 3: The Ilovica Project
© Euromax RESOURCES The llovica Project PEA Completed M&lI Resource Open Pit - 1:1 Strip 256.8mt @ . PFS Completed 0.32g/t Au (2.6Moz) conventional drill & FS Completed 0.21% Cu (1.2Blb) “ 2 Shovels, 19 trucks 10 Mt throughput/yr Downstream TMF Local EIA Complete Conventional grind, —_ Valley next t
Slide 4: US$474.3 million capex
U S $ 4 7 4 . 3 million Prices: USD 1,220/oz Au; USD 2.90/lb Cu 3
Slide 5: Macedonia
© Euromax RESOURCES Macedonia Governmental & GDP USD 11 billion Tax rate 10% Public Support . uy: : Population 2 million Excellent infrastructure Educated workforce [Rigtomietel-w-telet-an-iem VWorld Bank Doing with EU and EFTA Business 6% EU, 12% World 25% Unemployed
Slide 6: Experienced Management Team
¢ Euromax Experienced Management Team Steve Varshan Patrick Martyn Tim Randy Bill Raymond Sharpe Gokool — Forward Konig | Morgan-Wynne — Matkaluk Abel Threlkeld CEO CFO COO Chairman Director Director Director Director All administrative functions transferred from Canada / London to Skopje * Sharehol
Slide 7: Finance Plan
© Euromax RESOURCES Finance Plan FS & Pre-construction | Aurubis Offtake US$ 24m German Government EBRD/Stream/CCC Untied ECA cover CCC to provide US$ US$ 215m PF 25m sub-debt for US$ 25m CAT construction US$ 160m Stream US$ 25m CCC US$ 425m Total Project Finance Banks mandated 12 yr tenor Initial D
Slide 8: Next Steps
Next Steps Main Mining Project Submission Main Board TSX Finalise Project & Equipment Finance Tied ECA Value Engineering FEED Optimised Feasibility Study Construction Permit Construction Decision Construction Contract Definition Construction 24 months First Production Q4 2018,
Slide 9: Corporate Information
¢ Euromax Corporate Information Capitalization Overview Holding Share price against Market Market cap Vector Junior Gold Miners Index Closing price (8 June 16) 52 Week High 52 Week Low Shares Basic Shares Fully Diluted Major Shareholders Holding EBRD Richard Griffiths Richmond Capital 5 9 oo sea ga?
Slide 10: Steve LC Sharpe
© Euromax www.euromaxresources.com Steve LC Sharpe President & CEO E: ssharpe@euromaxresources.co.uk Varshan Gokool Chief Financial Officer E: vgokool@euromaxresources.co.uk Pat Forward Chief Operating Officer E: pforward@euromaxresources.co.uk
Slide 11: Appendix — The Feasibility Study
© Euromax RESOURCES Appendix — The Feasibility Study ¢ Study by various consultants and engineers * Lead by Amec Foster Wheeler who finalised report in December * Cost Estimation is +/-10% ¢ Price Assumptions are as per current analyst consensus: * US$1 220 /oz Au, US$18 /oz Ag and US$2.90 /Ib Cu. S
Slide 12: DFS / FEED Main Aims
© Euromax RESOURCES DFS / FEED Main Aims Mineral Resource Update — Drilling plus new estimate by Tetra Tech * Improve Classification Improve Classification Mining Study - DMT * Improve Classification based on new resources and more detailed schedule, better geotech Plant and Mine Infrastructure — Am
Slide 13: •
• • • • • 12
Slide 14: Mining - DMT
© Euromax RESOURCES Mining - DMT ‘The mining method will use conventional drilling and blasting together with shovel Gieadte __ Gennes ee . Classification | Tonnage Au Cu Au Cu and trucks supported by a fleet of ancillary tat) | @) | (Moz) [by equipment Probable 112.6 0.30 0.19 0.84 355.0 Proven 85.
Slide 15: Plant and Mine Infrastructure — Amec Foster Wheeler
© Euromax RESOURCES Plant and Mine Infrastructure — Amec Foster Wheeler ¢ 10Mt a year throughput ¢ Primary gyratory in pit crusher with | conveyor from pit to plant — * SAG mil with two ball mills plus pebble * Bulk flotation and CIL on Flotation cleaner Pre-Leach Thideering [1oades caroon-} aon L >
Slide 16: Tailings Management Facility - Golder & Faculty of C Eng.
© Euromax RESOURCES Tailings Management Facility - Golder & Faculty of C Eng. * Downstream method of construction and wall raising to safeguard the long term integrity. * Minimum operational freeboard of 2m adopted to comply with International Commission on Large Dams (ICOLD) ead Starter wall embank
Slide 17: ESIA — Golder & SWS
© Euromax RESOURCES ESIA — Golder & SWS Impacts and mitigations complete for: * Security of water supply to llovica, Shtuka, plus other villages currently reliant on llovica reservoir. * Security of water supply for irrigation in Strumica basin. * Water quality of potable water supply to llovica and
Slide 18: Hydrology and Hydrogeology — SWS
© Euromax RESOURCES Hydrology and Hydrogeology — SWS Inputs in to all engineering studies and E&S impacts. Comprehensive baseline work to ensure: ¢ Use of available and unutilised water resources nearby * Conservation of site run-off and recycling of wastewater ¢ Maintaining the reliability and wate
Slide 19: Capital Expenditure
© Euromax RESOURCES Capital Expenditure * The capital cost estimate includes engineering, procurement, construction, start-up and cold commissioning. Provision is also made for owner's costs. * The base date for pricing is September 2015. * The estimate covers the direct field costs of executing the
Slide 20: Operating Costs
© Euromax RESOURCES Operating Costs * Total work force at steady state is 487 (Mining avg 258, Plant etc 131, Admin 98) Opex Summary Total Sulphide Ore Fixed Cost Variable Cost Cost Centre $M/Year $/t $/Year $/t $/t Mining 35.36 3.53 8.38 26.99 2.70 (average - including labour) Labour 8.80 0.88 8.80
Slide 21: Sensitivities
© Euromax RESOURCES Sensitivities Change in Factor -30% -20% -10% 0 10% 20% 30% capital $622 $561 $501 $440 $380 $319 $259 expenditure aoe ee $777 $664 $552 $440 $327 $212 $98 Gold Price $108 $219 $330 $440 $550 $660 $769 Recovery $350 $381 $410 $440 $470 $499 $529 Copper Price $99 $213 $327 $440 $5
Slide 22: NPV and IRR Sensitivity to Metal Prices
© Euromax RESOURCES Sensitivities NPV and IRR Sensitivity to Metal Prices (US$) Copper Gold Price NPV at 0% NPV at 5% NPV at 10% Price (US$ discount discount (US$ M) discount IRR (US$ oz) Ib) (US$ M) (US$ M) Pre-tax | Post-tax Pre-tax Post-tax Pre-tax Post-tax Pre-tax Post-tax 1 100 2.50 $474 $412 $
Slide 23: Varshan Gokool Pat Forward Martyn Konig
Varshan Gokool Pat Forward Martyn Konig Tim Morgan- Randal CFO & Directo COO & Director Non-Executive Wynne Matkaluk Chairman Non-Executive Director Non-Executive Director 22
Slide 24: Development Next Steps
© Euromax RESOURCES Development Next Steps Value Engineering — In Parallel to FEED * Crusher location — could add two or more years mine life * Map copper oxides, involves further testwork and copper oxide assay — less conservative on recovery reductions in early years * Silver assays — will allow s
Slide 25: Cautionary Statements
© Euromax RESOURCES Cautionary Statements No securities commission or similar authority in Canada or the United States has reviewed or in any way passed comment on this presentation. No information in this presentation shall constitute an invitation to invest in Euromax Resources Ltd. (the “Company”