  1. Slide 1: Community Consultation Meeting – Oakdale West Estate

    Community Consultation Meeting Oakdale West Estate April 2021 1

  2. Slide 2: Overview

    Overview Welcome and Introductions Consultation Requirements Project Update – OWE Project Update – Project Waratah Environmental Performance Safety Update Consultation and Community Interactions Stakeholder Feedback & Questions 2

  3. Slide 3: Welcome and Introductions

    Welcome and Introductions Project Team: Organisation Goodman SLR Consulting Ersed Role Proponent Stakeholder Engagement Environmental Representative Key Contacts Stephanie Partridge Dan Thompson Carl Vincent Kym Dracopoulos Kate McKinnon Alasdair Cameron Lachlan O’Reilly Luke Ridley Stakeholder Repr

  4. Slide 4: Consultation Requirements

    Consultation Requirements • Upcoming Development Applications – Modification 7 to SSD 7348 – New SSD for building 4E – PCC DA for Building 3B 4

  5. Slide 5: Oakdale West Estate - MOD 7 Estate Masterplan

    [REFER TO DRAWING OAK MPC3 FOR CONTINUATION PRELIMINARY. Oakdale West Estate - MOD 7 Estate Masterplan ( global environmental and advisory solutions S | Re wu

  6. Slide 6: 4E Site Plan

    PRELIMINARY. 4E Site Plan Proposed Warehouse Facil Oakdale West Estate - MOD 7 = global environmental and advisory solutions

  7. Slide 7: Development Area Schedule

    Development Area Schedule ‘Sto Arca ‘46.044 aq Warehouse 3641 10,000 eqn ‘Warehoune 38-2 10,000 aq Ofice 38-1 (2 ievela) = 1,000 aqmn Oflce 38-22 bevels) 1,000 0g N \ Total BuidngAma = -22,0008qm | paring 6176 eqn ‘Ske Cover (sxc. curing) 48% q Foor Space Ratio aasst) | Handsteue! Aron 16AI5 oq glob

  8. Slide 8: Consultation Requirements - CEMP

    Consultation Requirements - CEMP Condition D120 of SSD7348 requires • Project will be completed by Goodman to consult with TfNSW, Prime Constructions. Council and Water NSW prior to • Project is forecasted to finalising the CEMP (Stage 1B & 1C). commence in July ‘21 & finish in March ‘22. • Prime Co

  9. Slide 9: Progress To Date & Upcoming Works - OWIE

    Progress To Date & Upcoming Works - OWIE • Compass Drive is complete and dedicated to council • Road 1 Complete and Final inspection carried out by Council prior to dedication. • Road 3 nearing completion. Targeted to be complete in June 2021. • Bulk Earthworks complete in Precinct 1. • Bulk earthwo

  10. Slide 10: Progress To Date – Lot 2B

    Progress To Date – Lot 2B • Warehouse structural steel complete; • Warehouse ground floor slabs complete; • Warehouse suspended slabs complete; • Total in-ground services 85% complete; • 32 External hardstand pours complete; • Warehouse roof installation complete; • HVAC Units installation progressi

  11. Slide 11: Upcoming Works – Lot 2B

    Upcoming Works – Lot 2B • Carpark preparation works continuing; • Bump-out cladding works continuing; • Window frame & glazing installation progressing; • HVAC Unit installation; • Fire protection to Primary structure continuing on Level P2, P3 & P4; • External pours continuing; • Main office roof i

  12. Slide 12: Progress To Date – Lot 1A

    Progress To Date – Lot 1A • Erosion & Sediment Control installation complete; • Site Compound setup is complete; • On-lot detailed earthworks 90% complete to the Low Bay; • Low Bay Structural Pile Installation progressing with over 50% of piles completed; • High Bay Structural Piles complete; • 85%

  13. Slide 13: Upcoming Works – Lot 1A

    Upcoming Works – Lot 1A • Continuation of in-ground hydraulic and electrical services; • Structural Steel installation commencing on 27 April 2021; • Continuation of the Structural Piles to the Low Bay; • Continuation of the Installation of the CTFCR to the High Bay & Low Bay; • Continuation of nort

  14. Slide 14: ER Inspections and Audits: SSD7348

    ER INSPECTIONS AND AUDITS: SSD7348 ER INSPECTIONS 2019 TOTAL 3 2020 QTR1 (JAN-MARCH) 16 2020 QTR 2(APRIL-JUNE) 10 2020 QTR 3 (JULY-SEPT) 9 2020 QTR 4 (OCT-DEC) 7 2021 QTR 5 (JAN-MAR) 6 2021 QTR 6 (APR – Part) 3 TOTAL TO DATE 54 Copyright © ErSed 2011

  15. Slide 15: ER Inspections and Audits: SSD7348

    ER INSPECTIONS AND AUDITS: SSD7348 ER AUDITS THIS PERIOD FEB 21 • OWIE – INFRASTRUCTURE • INDUCTIONS AND ENV TRAINING • WASTE MANAGEMENT • CHEM AND DANGEROUS GOODS MARCH 21 • LOT 1A • INDUCTIONS AND ENV TRAINING • AQMP • SWMP • FIP • WASTE MANAGEMENT • CHEM AND DANGEROUS GOODS • MONITORING AND REPOR

  16. Slide 16: Environmental Performance: SSD7348

    ENVIRONMENTAL PERFORMANCE: SSD7348 NON COMPLIANCES, QUARTER 4 NIL QUARTER 5 NIL Copyright © ErSed 2011

  17. Slide 17: EC Inspections and Audits - SSD10397

    EC INSPECTIONS AND AUDITS- SSD10397 INSPECTIONS AUDITS THIS PERIOD JULY 20 3 AUGUST 20 0 SEPTEMBER 20 1 OCTOBER 20 1 NOVEMBER 20 1 DECEMBER 20 1 JANUARY 21 0 FEBRUARY 21 1 MARCH 21 5 APRIL 21 PART 0 TOTAL 8 Copyright © ErSed 2011

  18. Slide 18: Environmental Performance - SSD10397

    ENVIRONMENTAL PERFORMANCE- SSD10397 INCIDENTS AND COMPLAINTS AS DETAILED IN THE MONTLY REPORTS INCIDENTS NIL NON COMPLIANCES NIL Copyright © ErSed 2011

  19. Slide 19: Safety

    Safety • Lot 2B – A Near Miss occurred with a HV line for the temporary builders supply; • OWIE - Single Vehicle Accident. Road traffic accident occurred off site in a watercart while travelling between work sites 19

  20. Slide 20: Consultation and Community Interactions

    Consultation and Community Interactions • Damage to Aldington Road – Contractor inspected and repairs undertaken • Thankyou email received from Resident re tyre repair • Attendance at monthly resident meeting Emmaus Retirement Village, discussed project progression generally and stormwater strategy

  21. Slide 21: Communications and Consultation Channels

    Communications and Consultation Channels Sources of information and complaints/enquiries via: • Website: oakdaleopportunities.com • Email: community.oakdalewest@goodman.com • Phone: 1300 002 887 • Post: Level 17, 60 Castlereagh Street, Sydney, NSW 2000 • Community Meetings: Subject to scheduling • E

  22. Slide 22: Stakeholder Feedback & Questions

    Stakeholder Feedback & Questions 22