Slide 1: Community Consultation Meeting – Oakdale West Estate
Community Consultation Meeting Oakdale West Estate April 2021 1
Slide 2: Overview
Overview Welcome and Introductions Consultation Requirements Project Update – OWE Project Update – Project Waratah Environmental Performance Safety Update Consultation and Community Interactions Stakeholder Feedback & Questions 2
Slide 3: Welcome and Introductions
Welcome and Introductions Project Team: Organisation Goodman SLR Consulting Ersed Role Proponent Stakeholder Engagement Environmental Representative Key Contacts Stephanie Partridge Dan Thompson Carl Vincent Kym Dracopoulos Kate McKinnon Alasdair Cameron Lachlan O’Reilly Luke Ridley Stakeholder Repr
Slide 4: Consultation Requirements
Consultation Requirements • Upcoming Development Applications – Modification 7 to SSD 7348 – New SSD for building 4E – PCC DA for Building 3B 4
Slide 5: Oakdale West Estate - MOD 7 Estate Masterplan
[REFER TO DRAWING OAK MPC3 FOR CONTINUATION PRELIMINARY. Oakdale West Estate - MOD 7 Estate Masterplan ( global environmental and advisory solutions S | Re wu
Slide 6: 4E Site Plan
PRELIMINARY. 4E Site Plan Proposed Warehouse Facil Oakdale West Estate - MOD 7 = global environmental and advisory solutions
Slide 7: Development Area Schedule
Development Area Schedule ‘Sto Arca ‘46.044 aq Warehouse 3641 10,000 eqn ‘Warehoune 38-2 10,000 aq Ofice 38-1 (2 ievela) = 1,000 aqmn Oflce 38-22 bevels) 1,000 0g N \ Total BuidngAma = -22,0008qm | paring 6176 eqn ‘Ske Cover (sxc. curing) 48% q Foor Space Ratio aasst) | Handsteue! Aron 16AI5 oq glob
Slide 8: Consultation Requirements - CEMP
Consultation Requirements - CEMP Condition D120 of SSD7348 requires • Project will be completed by Goodman to consult with TfNSW, Prime Constructions. Council and Water NSW prior to • Project is forecasted to finalising the CEMP (Stage 1B & 1C). commence in July ‘21 & finish in March ‘22. • Prime Co
Slide 9: Progress To Date & Upcoming Works - OWIE
Progress To Date & Upcoming Works - OWIE • Compass Drive is complete and dedicated to council • Road 1 Complete and Final inspection carried out by Council prior to dedication. • Road 3 nearing completion. Targeted to be complete in June 2021. • Bulk Earthworks complete in Precinct 1. • Bulk earthwo
Slide 10: Progress To Date – Lot 2B
Progress To Date – Lot 2B • Warehouse structural steel complete; • Warehouse ground floor slabs complete; • Warehouse suspended slabs complete; • Total in-ground services 85% complete; • 32 External hardstand pours complete; • Warehouse roof installation complete; • HVAC Units installation progressi
Slide 11: Upcoming Works – Lot 2B
Upcoming Works – Lot 2B • Carpark preparation works continuing; • Bump-out cladding works continuing; • Window frame & glazing installation progressing; • HVAC Unit installation; • Fire protection to Primary structure continuing on Level P2, P3 & P4; • External pours continuing; • Main office roof i
Slide 12: Progress To Date – Lot 1A
Progress To Date – Lot 1A • Erosion & Sediment Control installation complete; • Site Compound setup is complete; • On-lot detailed earthworks 90% complete to the Low Bay; • Low Bay Structural Pile Installation progressing with over 50% of piles completed; • High Bay Structural Piles complete; • 85%
Slide 13: Upcoming Works – Lot 1A
Upcoming Works – Lot 1A • Continuation of in-ground hydraulic and electrical services; • Structural Steel installation commencing on 27 April 2021; • Continuation of the Structural Piles to the Low Bay; • Continuation of the Installation of the CTFCR to the High Bay & Low Bay; • Continuation of nort
Slide 14: ER Inspections and Audits: SSD7348
ER INSPECTIONS AND AUDITS: SSD7348 ER INSPECTIONS 2019 TOTAL 3 2020 QTR1 (JAN-MARCH) 16 2020 QTR 2(APRIL-JUNE) 10 2020 QTR 3 (JULY-SEPT) 9 2020 QTR 4 (OCT-DEC) 7 2021 QTR 5 (JAN-MAR) 6 2021 QTR 6 (APR – Part) 3 TOTAL TO DATE 54 Copyright © ErSed 2011
Slide 15: ER Inspections and Audits: SSD7348
ER INSPECTIONS AND AUDITS: SSD7348 ER AUDITS THIS PERIOD FEB 21 • OWIE – INFRASTRUCTURE • INDUCTIONS AND ENV TRAINING • WASTE MANAGEMENT • CHEM AND DANGEROUS GOODS MARCH 21 • LOT 1A • INDUCTIONS AND ENV TRAINING • AQMP • SWMP • FIP • WASTE MANAGEMENT • CHEM AND DANGEROUS GOODS • MONITORING AND REPOR
Slide 16: Environmental Performance: SSD7348
ENVIRONMENTAL PERFORMANCE: SSD7348 NON COMPLIANCES, QUARTER 4 NIL QUARTER 5 NIL Copyright © ErSed 2011
Slide 17: EC Inspections and Audits - SSD10397
EC INSPECTIONS AND AUDITS- SSD10397 INSPECTIONS AUDITS THIS PERIOD JULY 20 3 AUGUST 20 0 SEPTEMBER 20 1 OCTOBER 20 1 NOVEMBER 20 1 DECEMBER 20 1 JANUARY 21 0 FEBRUARY 21 1 MARCH 21 5 APRIL 21 PART 0 TOTAL 8 Copyright © ErSed 2011
Slide 18: Environmental Performance - SSD10397
ENVIRONMENTAL PERFORMANCE- SSD10397 INCIDENTS AND COMPLAINTS AS DETAILED IN THE MONTLY REPORTS INCIDENTS NIL NON COMPLIANCES NIL Copyright © ErSed 2011
Slide 19: Safety
Safety • Lot 2B – A Near Miss occurred with a HV line for the temporary builders supply; • OWIE - Single Vehicle Accident. Road traffic accident occurred off site in a watercart while travelling between work sites 19
Slide 20: Consultation and Community Interactions
Consultation and Community Interactions • Damage to Aldington Road – Contractor inspected and repairs undertaken • Thankyou email received from Resident re tyre repair • Attendance at monthly resident meeting Emmaus Retirement Village, discussed project progression generally and stormwater strategy
Slide 21: Communications and Consultation Channels
Communications and Consultation Channels Sources of information and complaints/enquiries via: • Website: oakdaleopportunities.com • Email: community.oakdalewest@goodman.com • Phone: 1300 002 887 • Post: Level 17, 60 Castlereagh Street, Sydney, NSW 2000 • Community Meetings: Subject to scheduling • E
Slide 22: Stakeholder Feedback & Questions
Stakeholder Feedback & Questions 22