Pt Royaltama Mulia Kontraktorindo Tbk · IDX:RMKO

Pt Royaltama Mulia Kontraktorindo Tbk — Q3 2026 Earnings Presentation

34 slides from Pt Royaltama Mulia Kontraktorindo Tbk's earnings presentation, November 2026

  1. Slide 1: Corporate Presentation 3Q 2026 Performance

    CORPORATE PRESENTATION 3Q 2026 PERFORMANCE PT Royaltama Mulia Kontraktorindo Tbk Optimizing Assets, Accelerating Momentum. 1

  2. Slide 2: Disclaimer

    DISCLAIMER This presentation material was prepared by PT Royaltama Mulia Kontraktorindo Tbk. (“RMKO”/“Company”) and has not been independently verified. No representation or warranty, express or implied, is made and no reliance is made on the accuracy or completeness of the information presented or c

  3. Slide 3: Agenda

    AGENDA 01 02 03 04 05 COMPANY OUTLOOK & OPERATIONAL FINANCIAL APPENDIX PROFILE STRATEGY PERFORMANCE PERFORMANCE 3

  4. Slide 4: Company Profile

    Chapter 1 COMPANY PROFILE 4

  5. Slide 5: From Mining Contractor to Integrated Energy Logistics Leader

    FROM MINING CONTRACTOR TO INTEGRATED ENERGY LOGISTICS LEADER 2017 2019 2020 2021 2022 2023 2024 2025 2026 Launched Successfully Successfully Commenced Appointed as Public Finalized Finalized Right Issue I first mining developed developed the 38-km the primary Listing (IPO) dedicated dedicated Raising

  6. Slide 6: Company Structure Overview

    COMPANY STRUCTURE OVERVIEW PT RMK Investama Vincent Saputra Public 73.082% 0.002% 26.916% ROKT RMBE 99.99% 99.99% Per July 2026, after RIght Issue period ROKT: Royaltama Mulia Konstruksi, RMBE: Royaltama Mulia Beton 6

  7. Slide 7: Management Team

    MANAGEMENT TEAM VINCENT SAPUTRA President Commissioner ROKHMAD SUNANTO Independent Commissioner WILLIAM SAPUTRA Chief Executive Officer DANIEL YOSA Chief Operating Officer ELBERT Chief Financial Officer 7 7

  8. Slide 8: Why Invest in RMKO

    WHY INVEST in RMKO 01 02 03 04 Strategic Integrated Affiliated with New and Assets Location Mining Service PT RMK Energy Big Fleets Tbk 05 06 07 08 Solid Balance Sheet High Safety Long Track Record Good Corporate DER 0.19 time* Standard Experienced & Governance Zero fatality Professional Implementing

  9. Slide 9: Competitive Advantage

    COMPETITIVE ADVANTAGE Affiliated with PT RMK Energy Tbk, providing an integrated coal logistics solution 01 02 03 04 05 06 Partnership Owning 38 km Having Train Holding mining Competent New & big with PT Kereta of coal hauling Loading System permits team fleets Api Indonesia road (TLS) (KAI) in South

  10. Slide 10: Our Services

    OUR SERVICES 01 02 03 04 05 06 Infrastructure Mining Hauling Reclamation Emplacement Rental Preparation ● Survey and ● Hauling road Ex-Mining Services ● Heavy exploration construction Area equipment ● Mining ● Stockpile infrastructure ● Mine modelling ● Coal hauling management rental and design ● To

  11. Slide 11: Business Process

    BUSINESS PROCESS Mining Services Rental Services Striping Top Soil And Train Loading System Land Clearing Coal Getting Hauling Stockpile Overburden (TLS) Overburden Dumping Top Soil Spreading Reclamation in Disposal 11

  12. Slide 12: Outlook & Strategy

    Chapter 2 OUTLOOK & STRATEGY 12

  13. Slide 13: Public Road Coal Hauling Ban

    PUBLIC ROAD COAL HAULING BAN Regulatory Catalyst: South Sumatra Governor's Instruction No. 500.11/004/INSTRUKSI/DISHUB/2025 (effective Jan 1. 2026) ban on coal transport via public roads Infrastructure Vitality Dedicated coal hauling road is now the exclusive logistics solution for affected mines in

  14. Slide 14: Railway Capacity Outlook

    RAILWAY CAPACITY RAILWAY CAPACITY OUTLOOK OUTLOOK PT Kereta Api Indonesia (KAI) is expanding South Sumatra’s coal rail network and fleet capacity. ● KAI plans to develop triple track lines across the corridor. ● KAI is investing in 54 new locomotives. 1.125 flat wagons. and 966 bottom-dump wagons. ● K

  15. Slide 15: The Core of South Sumatra's Coal Industry

    THE CORE OF SOUTH SUMATRA’S COAL INDUSTRY Lahat to Muara Enim region is In 2024. PTBA produced Other major producers in the area include the heart of South Sumatra’s around 42 Mtpa. PTBA Pendopo Energi Batubara (BUMI Group). coal basin. with about 60% targets 100 Mtpa by Mustika Indah Permai (Adaro

  16. Slide 16: Corporate Strategy

    CORPORATE STRATEGY 01 02 03 Developing Optimizing the Optimizing coal infrastructure potential of coal loading capacity mining services 04 05 People & asset Operational management excellence 16

  17. Slide 17: Our Achievement in 3Q 2026

    OUR ACHIEVEMENT IN 3Q 2026 2026 9M 2026 ACHIEVEMENT No Indicator UNIT (a) (b) b/a Target Actual (%) Mining Services Hauling mn ton 1.8 1.1 63.1 1 Operational Rental Services Loading TLS mn ton 2.8 2.3 82.6 Operating revenue bn Rp 553.1 345.3 62.4 Profitability Gross profit bn Rp 35.6 19.4 54.5 2 Finan

  18. Slide 18: Hauling Road Covered 3rd Parties Mining Area

    HAULING ROAD COVERED 3RD PARTIES MINING AREA Cakrawala Tiga Putri Duta Bara Pratama Sahala Bara Ulima Nitra Sinar Wijaya Bersaudara Utama (DBU) Manunggal Lestari (SBL) (UN) Energi (SWE) (TPB) (CPM) 18

  19. Slide 19: TLS 2 Reaches 60% Completion, On Track for 2027

    TLS 2 REACHES 60% COMPLETION ON TRACK FOR 2027 OPERATIONS 60% The construction of the Train Loading System (TLS) 2 facility in Gunung Megang completion has reached 60% completion, in line with the planned 2027 operational target ● The new facility will add capacity 4-5 million tons/year ● Total capa

  20. Slide 20: Chip Sealed Hauling Road 26% Completion

    CHIP SEALED HAULING ROAD 26% COMPLETION Before The hauling road is being built with a chip seal surface, a durable and cost-efficient pavement suited to heavy hauling operations. Chip seal progress has reached 26%. Beyond increasing road thickness, RMKO will also expand hauling road After connectivit

  21. Slide 21: Corporate Action Right Issue

    CORPORATE ACTION RIGHT ISSUE Rights Issue I Proceeds Rights Issue I Subscriber Amount • RMKO successfully completed its Rights Issue I, raising a total PT RMK Investama (RMKI) IDR108.0 billion of IDR114.3 billion Public IDR6.3 billion • Main shareholder, RMKI, fully Total IDR114.3 billion exercised

  22. Slide 22: Operational Performance

    Chapter 3 OPERATIONAL PERFORMANCE 22

  23. Slide 23: Operating RMKE's Dedicated Coal Hauling Road Facility

    OPERATING RMKE’S DEDICATED COAL HAULING ROAD FACILITY Item Detail Asset owner RMKE (group asset) Operator RMKO Completed length 38 km Mines connected 6 new mines (since 1Q 2025) Next Step Extended access to potential mines The hauling road is the entry point where mine volume enters the group’s inte

  24. Slide 24: Operating RMKE's Stockpile Facility

    OPERATING RMKE’S STOCKPILE FACILITY Item Detail Asset owner RMKE (group asset) Operator RMKO Stockpile capacity (current) 160,000 tons Water sprayers and water cannons Dust control (being installed) 8 scrapers, under development by TLS 2 RMKE Total capacity after TLS 2 300,000 tons RMKO also operate

  25. Slide 25: Operating RMKE's TLS

    OPERATING RMKE’S TLS Item Detail Asset owner RMKE (group asset) Operator RMKO TLS 1 capacity 4-5 million tons per year Built by a third party, TLS 2 planned operation end-2027 Total capacity after TLS 2 8-10 million tons per year ● RMKO also operates RMKE’s Train Loading System (TLS) to increase TLS

  26. Slide 26: Mine Operational Equipment

    PERALATAN OPERASIONAL TAMBANG Unit Excavator Unit Hauler Unit Hauler Unit Excavator 3 (Big Digger) 16 (HD – 60Ton) 238 (Dump Truck – 20 Ton) 36 (Small Digger) 28 Unit Dozer 11 Unit Motor Grader 4 Unit Man Haul 14 Unit Water Truck 26

  27. Slide 27: Hauling Volume Surpasses 1.1 Million Tons

    HAULING VOLUME SURPASSES 1.1 MILLION TONS ON WIDER THIRD-PARTY MINE COVERAGE Mining Service Segment: Downstream Hauling Volume 3Q 2026 +138.5% YoY to 578.7 thousands ton 9M 2026 +122.4% YoY to 1.1 million ton Volume growth is driven by the increasing 1,136.1 number of third-party mines covered by RM

  28. Slide 28: TLS Volume Up 155.9% YoY to 2.3 Million Tons

    TLS VOLUME UP 155.9% YOY TO 2.3 MILLION TONS AS THIRD-PARTY MINE HAULING GROWS Rental Service Segment: Train Loading Volume (TLS) 3Q 2026 +77.9% YoY to 994.8 thousands ton 9M 2026 +155.9% YoY to 2.3 millions ton 2,345.2 Growth is supported by increasing hauling volume delivered directly from third-p

  29. Slide 29: Construction Pipeline: Building Infrastructure Behind Future Volume Growth

    CONSTRUCTION PIPELINE: BUILDING THE INFRASTRUCTURE BEHIND FUTURE VOLUME GROWTH Construction Segment: On-Going Project Project 1 Expanding and strengthening the hauling road network toward potential mines, opening new alignments, upgrading road foundations through CTRB and sub-base works, and sealing

  30. Slide 30: Financial Performance

    Chapter 4 FINANCIAL PERFORMANCE 30

  31. Slide 31: Strong Top-Line Growth Driven by Expanding Third-Party Mine Coverage

    STRONG TOP-LINE GROWTH DRIVEN BY EXPANDING THIRD-PARTY MINE COVERAGE Operating Revenue 3Q 2026 +32.8% YoY to IDR164.1bn Strong Top-Line Growth 9M 2026 9M 2026 +57.4% YoY to IDR345.32bn • Construction +130.9% YoY to IDR143.7bn, driven by progress on group support facilities in South Sumatra. • Rental

  32. Slide 32: 3Q 2026 Turnaround Lifting 9M 2026 into Positive Territory

    3Q 2026 TURNAROUND LIFTING 9M 2026 INTO POSITIVE TERRITORY EBITDA NET PROFIT & (LOSS) 3Q 2026 +225.6% YoY to IDR74.8bn 3Q 2026 +1,034% YoY to IDR48.6bn 9M 2026 +738.1% YoY to IDR59.4bn 9M 2026 +102.4% YoY to IDR1.2bn 48.6 74.8 45.6% 59.4 3.5% 29.6% 0.4% 18.6% 17.2% 4.3 -25.1% -27.8% -23.4% 23.0 -4.2

  33. Slide 33: Rights Issue and Earnings Recovery Strengthen the Balance Sheet

    RIGHTS ISSUE AND EARNINGS RECOVERY STRENGTHEN THE BALANCE SHEET Asset Liability Equity 3Q 2026 +10.6% to IDR616.2bn 3Q 2026 -14.2% to IDR325.1bn 3Q 2026 +63.4% to IDR 291.1bn 0.54 0.48 0.45 616.3 606.3 616.2 557.0 0.19 457.5 476.1 378.8 325.1 291.1 178.2 158.7 130.8 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q

  34. Slide 34: Thank You

    Wisma RMK 3rd Floor Jalan Puri Kencana Blok M4 No.1 Kembangan, Jakarta Barat, Jakarta 11610 E:rmk@ptrmk.com T:+62 21-5822-555 Thank You rmko.co.id PT Royaltama Mulia Kontraktorindo Tbk 34

PT Royaltama Mulia Kontraktorindo — Q3 2026 Earnings Presentation on 6ix