Slide 1: Duke Energy Carolinas Resource Plan Stakeholder Meeting 1
Duke Energy Carolinas Resource Plan Stakeholder Meeting 1 Virtual Meeting – February 22, 2023 *Please note, with the exception of the afternoon session, this meeting is being recorded. Presentations will be posted on the IRP website, and discussion portions will be kept for internal purposes only to
Slide 2: Today's Agenda
Today’s Agenda 9:00am: Welcome, Introductions, and Housekeeping Items 9:15am: Resource Planning Process Overview 10:15am: Break 10:30am: Technical Session: Development of Load Forecast and Key Drivers 12:30pm: Lunch Break 1:30pm: South Carolina Session: Available for Additional SC Comments and Quest
Slide 3: Great Plains Institute (GPI)
Great Plains Institute (GPI) Doug Scott, Aileen Cole Vice President, Energy Systems Policy Research Specialist Trevor Drake, Senior Program Manager Alissa Bemis, Amy Ward Meeting & Administrative Policy Associate Coordinator
Slide 4: Related GPI Work
Related GPI Work • Integrated Resource Planning • Power Plant Host Community Impacts • Time-Varying Rate Designs • Electric Vehicle Investments and Programs • Distribution System Planning • Load Flexibility and Demand Response Programs • Utility Performance Metrics
Slide 5: Duke Energy Welcome
Duke Energy Welcome Swati Daji Senior Vice President, Enterprise Strategy and Planning
Slide 6: Meeting Ground Rules
Meeting Ground Rules • Respect each other: Help us to collectively uphold respect for each other's experiences and opinions, even in difficult conversations. We need everyone’s wisdom to achieve better understanding and develop robust solutions. • Focus on today’s topics: There are many topics that
Slide 7: Attendee Roles: Observers
Attendee Roles: Observers • Please use the “Q&A” feature, on the menu at the bottom of your screen, to submit questions to presenters and Technical Representatives. Please be respectful and focus on issues, not people • Questions/comments submitted will be seen by GPI staff, presenters, and Technica
Slide 8: Attendee Roles: Technical Representative
Attendee Roles: Technical Representative • May utilize the camera and unmute themselves. • To manage participation, please use the “raise hand” feature to indicate you would like to join the conversation. • Technical Representatives (like Observers) may also submit questions to presenters by using t
Slide 9: Additional Participation
Additional Participation Meeting materials/recordings will be uploaded to the website: Meeting recordings (Q&A portions of meetings will be removed to adhere to the non- www.duke-energy.com/carolinas-irp attribution rule) and meeting summaries will be uploaded to the website for Information/feedback
Slide 10: Stakeholder Engagement Process Overview
Stakeholder Engagement Process Overview Rebecca Dulin, Enterprise Strategy & Planning
Slide 11: 2023 Resource Planning Stakeholder Engagement Overview
2023 Resource Planning Stakeholder Engagement Overview Feb Mar Apr May Jun Jul Aug Sep Meeting 1 Meeting 4 Final Modeling and Feb. 22 Mid-April Document Preparation Introduction & Topics TBD Process Overview IRP Filing Meeting 3 (PSCSC) Technical Session: Late April: March 22 Aug. 15 Load Forecast m
Slide 12: 2023 Resource Planning Stakeholder Engagement Overview
2023 Resource Planning Stakeholder Engagement Overview Potential Technical Meeting Topics: Load Forecast Resource Assumptions: Selectable Resources: Cost Solar Availability (year first available, annual/cumulative limits, etc.) Solar Plus Storage Operational characteristics Standalone Stor
Slide 13: Questions?
<e GREAT /PLAINS®’ Bettet Eneray. Naat INSTITUTE Batioy Word
Slide 14: Resource Planning Process Overview
Resource Planning Process Overview Glen Snider, Managing Director, Carolinas Integrated Resource Planning
Slide 15: Resource Planning for a Dual State System
Resource Planning for a Dual State System Carolinas Service Territory Duke Energy owns 33 GW of power generating capacity across our 56,000 square mile service territory serving 4.5 million retail customers in North and South Carolina The plan must meet the needs of customers in growing Carolina
Slide 16: Carolinas Combined Fleet Transition Progress
Carolinas Combined Fleet Transition Progress With the deterioration of the domestic coal industry, a measured exit from coal-fired generation is a strategic imperative to insulate customers from growing risks around fuel price and availability for these aging units. The combined DEC/DEP fleet is a n
Slide 17: Fundamentals of Resource Planning in the Carolinas
Fundamentals of Resource Planning in the Carolinas Planning to Serve Increasing Energy Needs Demand Patterns Vary Seasonally Winter Day Load forecast changes Customer Secondary evening peak as Economic development driving growth customers return home Demand Effects of customer programs and gri
Slide 18: Planning Objectives for a Changing Energy Landscape
Planning Objectives for a Changing Energy Landscape Power Supply Reliability Balance Risks for Orderly Transition Maintain adequate long-term reserves to serve Manage pace of coal retirements and emissions customers through peak demand periods reductions Maintain adequate system flexibility to
Slide 19: Developing a Resource Portfolio: Analytical Process
Developing a Resource Portfolio: Analytical Process Develop Spring 2023 Model Inputs Long-Term Planning Models Reliability Verification Strategic Energy & Risk Valuation Forecasts & Assumptions Model (SERVM) Load Forecast Evaluate portfolio reliability over 43 weather years, including EE/DSM
Slide 20: Components of a Resource Plan
Components of a Resource Plan Near-Term 15-Year Path to Actions Outlook 2050 Relatively low uncertainty in Greater uncertainty over IRP Significant uncertainty in near term planning horizon long-term future Approvals often sought prior Iterations and revisions in Indicative plans subject
Slide 21: <e GREAT /PLAINS®’ Bettet Eneray.
<e GREAT /PLAINS®’ Bettet Eneray. Naat INSTITUTE Batioy Word
Slide 22: Break
Break Please return at 10:35am
Slide 23: Technical Session: Load Forecast
Technical Session: Load Forecast Duke Energy Presenters: Stakeholder Technical Representatives: Glen Snider, Managing Director, Carolinas Integrated Resource Planning PJ Klein, Corning Incorporated Ben Passty, Principal Load Forecasting Analyst Adam Helsel, Fujifilm Diosynth Biotechnologies
Slide 24: Fundamentals of Resource Planning in the Carolinas
Fundamentals of Resource Planning in the Carolinas Planning to Serve Increasing Energy Needs Demand Patterns Vary Seasonally Winter Day Load forecast changes Customer Secondary evening peak as Economic development driving growth customers return home Demand Effects of customer programs and gri
Slide 25: Sample DEC Forecasted Energy Sales
Sample DEC Forecasted Energy Sales – System Obligation at Generator (GWh) sample *Source: 2022 Carbon Plan, Chapter 2, Table 2-1 | 25
Slide 26: Load forecasting methodology overview
Load forecasting methodology overview Inputs Energy Forecast Baseline Forecast and Validation Adjustment Econometric Baseline Data Weather Peak Load UEE, NEM, EV Modeling by Energy Gathering Normalization Forecast Adjustments Customer Class Forecast Historical energy consumption Test all economi
Slide 27: Primary Forecast Drivers by Customer Class
Primary Forecast Drivers by Customer Class Retail Load System Load Residential Commercial Industrial Government Wholesale Population Gross Domestic Manufacturing Employment Contract by Contract Product Employment Income Rates Income Industrial Production Rates Weather Rates I
Slide 28: Forecasting Process
Forecasting Process EXTERNAL DATA INTERNAL DATA Initial Forecast: Customer Growth Multiple Itron SAE modeling runs Efficiency trends Large Account trends Load Shapes MWh Sales Strategic Issues MW Peaks Appliance saturations Appliance status Rate Design IVVC Other EV Load Forecast Weather
Slide 29: Peak and Hourly Load Estimation Process
Peak and Hourly Load Estimation Process External Source Data Load (MW) Itron/SAE Model Runs Internal Source Data DEC/DEP DEC/DEP Annual Forecasts Hourly Forecasts | 29
Slide 30: Key Takeaways
Key Takeaways The load forecast isn’t just about a number, but about presenting a coherent understanding of relationships between the drivers, inputs, and resulting load forecasts Allows for understanding of a whole range of possible futures Allows the Company to be understand potential headwi
Slide 31: Load Forecast: Energy Efficiency
Load Forecast: Energy Efficiency sample *Source: 2022 Carbon Plan, Chapter 2, Table 2-1 | 31
Slide 32: Utility Energy Efficiency Forecast Update
Utility Energy Efficiency Forecast Update The Companies continue to forecast aggressive but achievable implementation of utility energy efficiency programs over the planning horizon. Updates since last filing: Using the Fall 2022 retail load forecast (instead of Spring 2022) Updated with 2023 pr
Slide 33: Forecast – 1% of Eligible Retail Load
Forecast – 1% of Eligible Retail Load DEC 1% Cumulative EE kWh - With Roll-off* DEP 1% Cumulative EE kWh - With Roll-off* 9,000 9,000 8,000 8,000 7,000 7,000 6,000 6,000 Millions Millions 5,000 5,000 4,000 4,000 3,000 3,000 2,000 2,000 1,000 1,000 0 0 2023 Forecast 2022 Forecast 2023 Forecast 2022 F
Slide 34: Forecast – 1.5% of Eligible Retail Load
Forecast – 1.5% of Eligible Retail Load DEP 1.5% Cumulative EE kWh - With Roll-off* DEC 1.5% Cumulative EE kWh - With Roll-off* 6,000 9,000 5,000 8,000 7,000 4,000 6,000 Millions 3,000 Millions 5,000 4,000 2,000 3,000 1,000 2,000 1,000 0 0 2023 Forecast (1.5% of Eligibile Retail) 2022 Forecast (1 %
Slide 35: Potential Enablers for Long Term EE/DSM Forecast - Updates
Potential Enablers for Long Term EE/DSM Forecast - Updates Structural modifications and mechanisms that remove market barriers to program participation In collaboration with the On-Tariff Working Group, designed and filed Multifamily New Construction Tariff On Bill Pilot (Docket E-2 Sub 1307). Filed
Slide 36: Potential Enablers for Long Term EE/DSM Forecast - Updates
Potential Enablers for Long Term EE/DSM Forecast - Updates Modifications expanding the potential measures and offers reducing consumption from the grid While no clear plans or path toward program attribution, the Company is working to provide input when requested from NC Building Code Council and U
Slide 37: Load Forecast: NEM Rooftop Solar
Load Forecast: NEM Rooftop Solar sample *Source: 2022 Carbon Plan, Chapter 2, Table 2-1 | 37
Slide 38: Carolinas Net Metered (NEM) History – DEC & DEP
Carolinas Net Metered (NEM) History – DEC & DEP NEM adoption has been accelerating Factors influencing historical trends in the Carolinas HB589 Rebate Program Investment Tax Credits (ITC) 25% SC Tax Rebate Falling solar panel prices Recent trends in adoption influence SC Act 236 expi
Slide 39: DRAFT Carolinas NEM Solar Forecast
DRAFT Carolinas NEM Solar Forecast NEM as % of Total System Energy Jurisdiction Spring 2023 Spring 2022 2023 Duke Energy Carolinas 0.5% 0.5% Duke Energy Progress 0.6% 0.5% 2025 Duke Energy Carolinas 0.8% 0.6% Duke Energy Progress 0.9% 0.6% 2030 Duke Energy Carolinas 1.3% 0.9% Duke Energy Progress 1.
Slide 40: DRAFT Carolinas NEM Solar Forecast
DRAFT Carolinas NEM Solar Forecast NEM Projections Base Case projections use currently-approved tariffs in North Carolina and South Carolina Updates from 2022 Forecast: 18 additional months of adoption data Refreshed system costs (+20%) Refreshed residential rates (+10%) Extend 30% ITC t
Slide 41: Load Forecast: Electric Vehicles
Load Forecast: Electric Vehicles sample *Source: 2022 Carbon Plan, Chapter 2, Table 2-1 | 41
Slide 42: Carolinas Electric Vehicle History – DEC & DEP
Carolinas Electric Vehicle History – DEC & DEP History EV Registrations have increased about 45% YoY from 2021 to 2022 in DEC & DEP Light Duty EV adoptions were in line with the 2022 forecast while Medium and Heavy Duty EV adoptions were below forecast VIO = vehicles in operation Load Forecast D
Slide 43: DRAFT EV Adoption Forecast for the Carolinas
DRAFT EV Adoption Forecast for the Carolinas Base EV Projections Reflects impacts of IRA incentives, IIJA, additional EV models, OEM electrification pledges, ICEV bans in CA and other states Includes projections for light duty (LD), medium duty (MD), and heavy duty (HD) EV adoption 46% - 48% by
Slide 44: DRAFT EV and NEM Net Energy Impacts
DRAFT EV and NEM Net Energy Impacts Net Impacts of EVs and NEM Energy and peak capacity growth from EVs greatly outweigh reductions from NEM adoption DEC NEM/EV Net Load in TWh DEP NEM/EV Net Load in TWh 14.00 8.00 12.00 7.00 10.00 6.00 Nem Ind 5.00 Nem Ind Annual Energy (TWh) Annual Energy (TWh)
Slide 45: Load Forecast: Rate Design
Load Forecast: Rate Design sample *Source: 2022 Carbon Plan, Chapter 2, Table 2-1 | 45
Slide 46: Rate Design Opportunities
Rate Design Opportunities Time of Use and Dynamic Pricing Intersection with Demand Response System Beneficial Electrification Load Forecast Drivers | 4 6
Slide 47: Rate Design – More Options Yielding Grid Benefits
Rate Design – More Options Yielding Grid Benefits Dynamic & TOU Pricing Hourly Pricing Initiative Status Initiative Status Time periods based on system dynamics Filed (NC/SC) Dynamically drive price responsive behavior Critical peak prices or response rewards CPP Rates (NC/SC) New structures needed
Slide 48: <e GREAT /PLAINS®’ Bettet Eneray.
<e GREAT /PLAINS®’ Bettet Eneray. Naat INSTITUTE Batioy Word
Slide 49: Lunch Break
Lunch Break At 1:30pm we will return to address any additional South Carolina-specific comments or questions about today’s session
Slide 50: Additional SC-specific Comments and Questions
South Carolina Session: Additional SC-specific Comments and Questions Heather Shirley Smith Vice President, Regulatory Affairs and Policy (SC) Leigh Tondini Utility Strategy Director (SC) Sam Wellborn Associate General Counsel (SC) Earlier Identified Technical Representatives South Carolina Se
Slide 51: Additional Participation
Additional Participation Meeting materials/recordings will be uploaded to the website: Meeting recordings (Q&A portions of meetings will be removed to adhere to the non- www.duke-energy.com/carolinas-irp attribution rule) and meeting summaries will be uploaded to the website for Information/feedback
Slide 52: Next steps
Next steps: • Questions/feedback can be sent to DukeCarolinas@gpisd.net • The next meeting will take place on Thursday, March 16. GPI will be sending out an email in the next week with the link to register.