For personal use only INVESTOR PRESENTATION SOUTH-WEST CONNECT OCTOBER 2023 Building the pre-eminent vertically integrated Lithium business in Ontario, Canada ASX | GT1
Slide 2: Indigenous Partners Acknowledgement
INDIGENOUS PARTNERS ACKNOWLEDGEMENT For personal use only We would like to say Gchi Miigwech to our Indigenous partners. GT1 appreciates the opportunity to work in the Traditional Territory and remains committed to the recognition and respect of those who have lived, travelled, and gathered on the l
Slide 3: Corporate Snapshot
CORPORATE SNAPSHOT 276.1M SHARES ON ISSUE GT1 $0.47 $129.8M $104.2 $25.6M $0 5.8M OPTIONS For personal use only ASX CODE SHARE PRICE MARKET CAP EV CASH DEBT 18.5M PERFORMANCE RIGHTS SHARE REGISTER SHARE PRICE PERFORMANCE 0.8 AMCI 0.7 9.07% LGES 0.6 7.87% BOARD & MANAGEMENT 0.5 6.62% 0.4 OTHERS 60.7%
Slide 4: Company Overview
COMPANY OVERVIEW Extensive Portfolio of Company Highlights projects in Tier-1 jurisdiction For personal use only Tier-1, low risk mining jurisdiction 24.5Mt1 1.14% ▪ Prime position to support the North American EV market TOTAL JORC MINERAL AVERAGE LI2O GRADE PENNOCK ▪ Supportive and proactive Govern
Slide 5: Board and Management
BOARD AND MANAGEMENT Extensive experience and proven track record of rapidly advancing and delivering lithium projects globally For personal use only JOHN YOUNG CAMERON HENRY Non-Executive Chairman Executive Director Highly experienced geologist 20 years' experience managing and operating public com
Slide 6: Executive Team
EXECUTIVE TEAM For personal use only LUKE COX MATT HERBERT Chief Executive Officer Chief Operation Officer SCOTT GILBERT NATHAN SIMS Chief Financial Officer VP Operations - Exploration JOHN WINTERBOTTOM ROGER SOUCKEY GM Technical Services VP HR and Communities METALS GREEN TECHNOLOGY METALS 66
Slide 7: Why Ontario?
GT1 is strategically WHY ONTARIO? positioned at the heart of the Ontario battery TIER-1 MINING JURISTDICTION ecosystem, making it the ideal choice as the $1.5b >$25b Western Hub Eastern preferred local lithium For personal use only Hub In Strategic Innovation Fund Committed in battery minerals suppl
Slide 8: Supply Chain Rock to EV-Battery
SUPPLY CHAIN ROCK TO EV-BATTERY For personal use only MINE MADE IN ONTARIO CONCENTRATE GT1 Organic Growth Spodumene Process Plant CONVERT CAM BATTERY CAR Exploration LITHIUM CONVERSION CATHODE ACTIVITY BATTERY MANUFACTORING CAR MANUFACTORING GT1 Resources FACILITY MATERIAL FACILITY FACILITY FACILITY
Slide 9: Pioneering Ontario's Lithium Future
PIONEERING ONTARIO'S LITHIUM FUTURE 3 stage integrated strategy to become the first Concentrates and Chemicals producer in the region For personal use only Development of a regional supply chain with multiple mine and process hubs feeding a central lithium conversion facility, made in Ontario WESTER
Slide 10: Integrated Project - Flowsheet
INTEGRATED PROJECT - FLOWSHEET Conventional mining and For personal use only conversion processes Concentrators Seymour: Crushing and Dense Media Separation (DMS) Root: Crushing, DMS, milling, magnetic removal, mica and spodumene flotation Conversion Facility Thunder Bay: Analcime by-product t
Slide 11: World Class Infrastructure
WORLD CLASS INFRASTRUCTURE The Integrated Project located in Northern Ontario, one of the premier regions in the world for lithium exploration, with proximity to infrastructure, car manufacturers, battery storage and major high-tech population centres compared to other provinces in Canada For person
Slide 12: Indicative Timeline to Production
INDICATIVE TIMELINE TO PRODUCTION For personal use only 1. All proposed production dates quoted are indicative GREEN TECHNOLOGY METALS 12
Slide 13: Strategic Highlights
STRATEGIC HIGHLIGHTS LOI signed for conversion facility For personal use only First ever Offtake agreement Transformational 24.5 million in Thunder Bay with due diligence executed and A$20m strategic tonne resource base across underway Investment from LG Energy Ontario Projects Solution SIF Funding
Slide 14: Preliminary Economic Assessment
PRELIMINARY ECONOMIC ASSESSMENT The full potential of our mineral endowment will be unlocked through Pit to Product Lithium Business Development Integrating mine, concentrator and conversion plant Study to Include For personal use only A sustainable, valuable vertically integrated lithium operatio
Slide 15: Stage 1: Eastern Hub
Stage 1: For personal use only EASTERN HUB FALCON JUNIOR OWNERSHIP 100% Owned AREA 32,720 Hectares RESOURCE (Current) 9.9Mt @ 1.04% Li2O (with 5.2Mt @ 1.29% Indicated) EXPLORATION TARGET 22 to 26 Mt @ 0.8 to 1.5% Li2O DRILLING 74,667m STAGE Pre-Development EXPECTED FIRST 2025 PRODUCTION The potentia
Slide 16: Seymour
SEYMOUR Central processing facility located at Seymour Potential to add satellite pits from the Junior and Falcon projects For personal use only Mineral Resource Increased geological confidence with +50% in the Indicated category 7736m infill drilling program underway to increase mineral resourc
Slide 17: Green Lithium Production in Canada
GREEN LITHIUM PRODUCTION IN CANADA Minimal environmental impact – small operation For personal use only Designed with minimal ground impact Minimised footprint - only~500ha 2 open pits – staged North and South Aubry Dry stacked tailings No chemicals in processing DMS only concentrator – NO CHE
Slide 18: Seymour Project - Progress
SEYMOUR PROJECT - Progress Plant layout and sections For personal use only GREEN TECHNOLOGY METALS 18
Slide 19: Permitting Schedule
PERMITTING SCHEDULE 2021 - 2022 Baseline data collection Technical studies & engineering For personal use only Indigenous consultation Pre-submission consultation with government agencies 2023 3 years of baseline data completed Indigenous consultation – In progress Project design compl
Slide 20: Testwork - Concentrator
TESTWORK - Concentrator Conventional mining processes utilising industry expertise Seymour – Very coarse, clean in nature – Spodumene For personal use only HLS Completed – Achieved a 72% recovery. Demonstrating Seymour’s coarse grain spodumene is amenable to DMS. Opportunity for further optimi
Slide 21: Junior Lithium Project
JUNIOR LITHIUM PROJECT Potential to significantly add to Eastern-hub Sample Name E N Type Li2O % resource base F713162 Despard 422507 5586337 Float 3.23 For personal use only LCT spodumene-bearing pegmatites F713124 Despard 422504 5586341 Outcrop 2.56 Tape measuring up to 40 meters in length and app
Slide 22: Stage 2: Conversion Facility
Stage 2: For personal use only CONVERSION FACILITY OWNERSHIP Under option AREA 25 Hectares STAGE Preliminary Economic Assessment PRODUCTION 2028 22
Slide 23: Conversion Facility
CONVERSION FACILITY Stage 1 – proposed circa 20-25 kt capacity For personal use only Stage 2 – plant/site layout confirmed for additional train Proposed Alkali leach flow sheet - analcime by-product that can be treated and potentially used for civil/fill applications. Flow sheet currently being impl
Slide 24: Conversion Facility
CONVERSION FACILITY Initial emissions studies underway – complete Oct 23 Geotechnical investigation - work commenced Serviced site – power, natural gas, water and municipal sewer. For personal use only Grid power – Hydropower connection 115kV line adjacent to the property Port and rail acc
Slide 25: Stage 3: Western Hub
Stage 3: For personal use only WESTERN HUB OWNERSHIP 100% Owned AREA 23,095 Hectares RESOURCE (Current) 14.6Mt @ 1.21% Li2O EXPLORATION TARGET 20-24Mt @ 0.8 to 1.5% Li2O DRILLING 42,000m STAGE Preliminary Economic Assessment EXPECTED FIRST 2028/9 PRODUCTION The potential quantity and grade of Explor
Slide 26: Western Hub - Root Bay
WESTERN HUB Root Bay Excavation For personal use only The original Root Bay outcrop was only exposed when the local forestry came through and cleared roads and trees. GT1 teams have been successfully trenching the ridge and exposing LCT pegmatites East and West of the original find. Exploration Geol
Slide 27: Root Bay - Deep Potential
ROOT BAY – Deep Potential Root Bay Thickness For personal use only The stacked pegmatites within the Root Bay area progressively get thicker from East to West with Pegmatite #6 on the west averaging 18m thickness. Depth All of the pegmatites are open at depth with the capability to extend further. T
Slide 28: Root Project - Plant Layout & Sections
ROOT PROJECT – Plant layout & sections High grade - finer grained spodumene however still coarse against benchmarks For personal use only Hybrid DMS/Flotation concentrator envisaged – better recoveries Proposed standard Tailings Storage Facility (TSF) Standard permitting timelines – federal
Slide 29: McCombe & Morrison
MCCOMBE & MORRISON McCombe Maiden inferred JORC Resource – 4.5 @ 1.01% Li2O Exceptional high- For personal use only grade drill success - Highest Grade Drill Intercept to date 4.06% Li2O Thick and continuous high grade spodumene pegmatites from surface Morrison Historical drilling delineated s
Slide 30: Community
COMMUNITY “FIRST NATION DRILLING” JV GT1 and our drilling partner G4 Drilling have been working on an For personal use only indigenous JV drilling initiative for the past year with Lac Seul community. The formation of a new Company “First Nation’s Drilling” represents an incredible opportunity t
Slide 31: Stage 4: Additional Projects
Stage 4: For personal use only ADDITIONAL PROJECTS 31
Slide 32: Allison
ALLISON AREA 9,444 Hectares For personal use only STAGE Exploration Located 42km from the Root Lithium Project and easily accessible by road Believed to be the source of LCT pegmatite occurrences in the region 3 claim blocks; North, Central and South lie on the edge of a fertile granite believ
Slide 33: Pennock
PENNOCK AREA 1389 Hectares For personal use only STAGE Exploration An extensive reconnaissance program is underway over the entire Pennock project. Pennock is located adjacent to Frontier Lithium’s Pennock Pegmatite, that has a 30x16m spodumene-bearing outcrop with results from Frontiers channel sam
Slide 34: What Is Next?
WHAT IS NEXT? Root Bay further drilling For personal use only Seymour DMS Test work results – October Conversion Test work – Q4 2023 & ongoing Integrated PEA – Q4 2023 Junior maiden drilling program – Q1 2024 Seymour MRE update Finalisation of partnering process for downstream DFS: S
Slide 35: Contacts
For personal use only Contacts Chief Executive Officer Luke Cox L1, 338 Barker Rd, Subiaco Perth, Western Australia 6008 Email: info@greentm.com.au Investor Relations and Media Jacinta Martino Email: ir@greentm.com.au Share registry Automic Group Email: hello@automic.com.au ASX GT1
Slide 36: Appendix | Mineral Resource Estimate
APPENDIX | MINERAL RESOURCE ESTIMATE Project Tonnes (Mt) Li2O (%) Root Project Root Bay Indicated 9.4 1.30 For personal use only Inferred 0.7 1.14 Total 10.1 1.29 McCombe Inferred 4.5 1.01 Total 14.6 1.21 Seymour Project1 North Aubry Indicated 5.2 1.29 Inferred 2.6 0.93 South Aubry Inferred 2.1 0.55
Slide 37: Appendix | Disclaimer
APPENDIX | DISCLAIMER Important information: Green Technology Metals Limited (ASX GT1) ACN 648 657 649 (the "Company") is the issuer of this presentation. Not a disclosure document: This presentation is not a disclosure document for the purposes of Chapter 6D of the Corporations Act 2001 (Cth) ("Cor
Slide 38: Appendix | Competent Persons Statement
APPENDIX | COMPETENT PERSONS STATEMENT The information in this Presentation that relates to the Exploration Results is based on activities carried out by Mr Luke Cox. Mr Cox has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and the act