Kinder Morgan, Inc. · NYSE:KMI

Kinder Morgan — Kinder Morgan Energy Partners — 2010 KMP Analyst Conference

12 slides from Kinder Morgan's conference presentation, Jan 28, 2010

  1. Slide 1: Kinder Morgan Canada

    ENERGY PARTNERS, L.P. *Information *I f ti contained t i d in i this thi presentation t ti isi dated d t d as off 1/28/2010. 1/28/2010 For F currentt project j t scope and information on the Trans Mountain Pipeline expansion project, please see www.transmountain.com Kinder Morgan Canada Ian Anderson

  2. Slide 2: Trans Mountain Pipeline

    ENERGY PARTNERS, L.P. Trans Mountain Pipeline Capacity  Recently Expanded from 225,000 bpd to 300,000 bpd Markets  Lower Mainland BC  Washington State Refineries  Westridge Dock to markets in U.S. and Asia Regulation/Tolls  National Energy Board Regulated  Tolling Agreement with shippers thru

  3. Slide 3: Express – Platte Pipeline System

    ENERGY PARTNERS, L.P. Express – Platte Pipeline System Express - 280,000 bpd • 231,000 bpd Firm contracts thru 2012- 2012-15 • Excess capacity today • Rockies & Canadian production will fill space over time • Primary route for Canadian production to PADD IV refiners Platte - 143,000 - 165,000 bpd •

  4. Slide 4: Kinder Morgan Canada – Growth

    ENERGY PARTNERS, L.P. Kinder Morgan Canada – Growth (millions $US) Actual Actual Budget 2006-10 2006 2 2009 2010 Growth Trans Mountain 1 62.0 147.4 147.7 85.7 (Distributable Cash Flow) Express 1.7 14.6 12.9 11.2 (Cash Distributions) $63.7 $162.0 $160.6 $96.9 1. Growth Capex $720MM; Capacity 225,000

  5. Slide 5: Trans Mountain Expansion Project

    ENERGY PARTNERS, L.P. Trans Mountain Expansion Project Cost Capacity In- In-Service (USD$M) (bpd) Initial System 225,000 Phase I – Pump Stations $198 April 2007 260,000 -11 New Stations Phase II - Anchor Loop $522 -60 miles Jasper Spread May 2008 285,000 -38 miles Robson Spread Nov 2008 300,000 -2 N

  6. Slide 6: Anchor Loop Project – Challenges Overcome

    ENERGY PARTNERS, L.P. Anchor Loop Project – Challenges Overcome  Extreme Regulatory Oversight  Canadian Environmental Assessment Agency Screening  Parks Canada  National Energy Board  Department of Fisheries and Oceans  Transport Canada  BC Ministry of Environment  Environmental Sensitivity

  7. Slide 7: Oil Sands Production – Pipeline Capacity

    ENERGY PARTNERS, L.P. Oil Sands Production – Pipeline Capacity  Canadian producers will have spare pipeline capacity to the United States for many years  Trans Mountain can be expanded in stages to better meet growing demand offshore, including China 5,000 Export Pipeline Capacity 4,000 3,000 Bitu

  8. Slide 8: Trans Mountain Expansion

    ENERGY PARTNERS, L.P. Trans Mountain Expansion Phased Expansion Planned Total Estimated Completion Capacity Cost TMX-1 (+75,000) Nov. 2008 300,000 BPD $720MM NORTHERN TMX-2 (+80,000)* 2013/14 380,000 BPD $1.4B LEG TMX-3 (+320,000)* 2015/16 700,000 BPD $2.1B TMX-1 Northern Leg (+400,000)* Post TMX-3

  9. Slide 9: Port Metro Vancouver Increasing Crude Oil Exports

    ENERGY PARTNERS, L.P. Increasing Crude Oil Exports Port Metro Vancouver Safe, Efficient Annual Exports (bpd) 80,000 2009: 75,000 bpd 60,000 40,000 20,000 - 53 58 63 68 73 78 83 88 93 98 03 08 19 19 19 19 19 19 19 19 19 19 20 20 Monthly Record in 2009: 134,000 bpd 9

  10. Slide 10: Attractive Tanker Rates

    ENERGY PARTNERS, L.P. Attractive Tanker Rates Tanker Rates to Asia* Suezmax: attractive rates to Asia $/bbl 5.00 4.00 3.00 2.00 1.00 - Panamax, Aframax, Suezmax, VLCC, 350kbbl 650k bbl 1Mbbl 2Mbbl __________________________ * KMC estimate of tanker rates, used for evaluating relative costs for tanke

  11. Slide 11: Trans Mountain Expansion Benefits

    ENERGY PARTNERS, L.P. Trans Mountain Expansion Benefits 1. Cheaper 3. Less Risk  25% of new pipeline already built  Incremental capacity  Lower capital, operating costs /  Established pipeline route / less follow existing pipeline environment and aboriginal issues  Expand for Suezmax tankers 

  12. Slide 12: ENERGY PARTNERS, L.P.

    ENERGY PARTNERS, L.P. KINDER/MORGAN