  1. Slide 1: Woodlawn Eco-Precinct Community Liaison Committee Meeting

    WOODLAWN ECO-PRECINCT COMMUNITY LIAISON COMMITTEE MEETING

  2. Slide 2: Acknowledgement of Country

    ACKNOWLEDGEMENT OF COUNTRY Veolia acknowledges Ngunnawal people as the traditional custodians of the lands and waters in which we live and work and their continuing connection to land, water and community. We pay respects to their Elders past, present and emerging and any first nations people presen

  3. Slide 3: Meeting Agenda

    MEETING AGENDA ITEM TOPIC 1 Introduction and welcome 2 Apologies 3 Actions from previous meeting 4 Commercial agreement disclosure 5 Eco-Precinct Operational Update 1. EPA Clean up notice 6 ARC presentation 7 CLC meeting administration 1. Comment attribution in minutes 2. Member composition 3. Reque

  4. Slide 4: Introduction and Welcome

    INTRODUCTION AND WELCOME

  5. Slide 5: Apologies

    APOLOGIES

  6. Slide 6: Meeting Attendance

    MEETING ATTENDANCE DATE Wednesday 27 November 2024 Time 5:00pm to 7.00pm LOCATION Woodlawn Conference Room 619 Collector Road, Tarago NAME PRESENT NAME PRESENT Justin Houghton (JH) (Veolia) Skye Mcparland (SM) (Veolia - online) TBA (GMC Councillor) No representative (TSA Rep) Cr John Preston (JP) (Q

  7. Slide 7: Actions from Last Meeting

    ACTIONS FROM LAST MEETING

  8. Slide 8: Meeting Actions

    MEETING ACTIONS ITEM ACTION ASSIGNED TO 1 ACTION: Veolia to inform the CLC and the Council when alerts for mods are coming. Greg Hosking Veolia to develop a process for this. STATUS: Complete - Email updates will be sent out when alerts are coming. 2 ACTION: CLC Facilitator to remove inappropriate q

  9. Slide 9: Eco-Precinct Positive Outcomes Since Last Meeting

    ECO-PRECINCT Positive outcomes since last meeting WINS! • COMMUNITY - In November the Trust Presented 19 grants $173,000 and 54 donations $72,000 to local community projects - total to date $14.8 Million to 1,950 projects • WATER MANAGEMENT - All dams have been reduced back to below freeboard in the

  10. Slide 10: Eco-Precinct Operational Update

    Traffic Lights Attention required ECO-PRECINCT Area of focus OPERATIONAL UPDATE Going well

  11. Slide 11: Operational Update Performance

    OPERATIONAL UPDATE PERFORMANCE Bioreactor Landfill - Licence tonnage YTD Waste Processed (licence 7 Sep 2023 - 31 Jul 2024) ● Regional Waste 121,568 t - (licence 125,000t) ● Sydney Waste 664,687 t - (licence 900,000t) ○ Both are within licence limits for Sep 2023- Sep 24 period Mechanical Biological

  12. Slide 12: Water Management Freeboard Management

    WATER MANAGEMENT FREEBOARD MANAGEMENT ● ED1 - Below 0.5m freeboard - 165.5ML ○ Current evaporation throughput 226 L/s ○ Extra 48 L/sec evaporation system is under construction and to be commissioned end December 2024 ● ED3N Below 0.5m freeboard - 0.1ML ○ Currently 62 L/s mechanical evaporation ● ED3

  13. Slide 13: Water Management Storage Status and Location

    WATER Storage status and location (End of Jan 2024) MANAGEMENT Coffer Dam #2 ED1 Plant Collection Dam Coffer Dam #3 Coffer Dam #1 Office area Leachate Treatment Plant ED3N 1-4 Plant collection catchment ED3S ED3SS Western Ridge catchment Bioreactor Void catchment

  14. Slide 14: Treated Leachate Strategy Summary

    WATER MANAGEMENT TREATED LEACHATE STRATEGY SUMMARY Short term next 18 months ● Temporary tank farm - 40 ML - 3 installed and approved for use 40ML ● Temporary TAnk farm tank 4 - Installed by mid December 2024 - 13.5ML ● Permanent tank farm 1 - 54ML - Approvals submitted ● Permanent tank farm 2 - up

  15. Slide 15: Operational Update Bio-Energy

    ECO-PRECINCT OPERATIONAL UPDATE BIO-ENERGY Bioenergy 2024 Biogas Capture ● Gas collected in last 12 months (11/23-10/24) 43,490,528 m3 ● Energy Generation 57,000 MWh in last 12 months ● In last 12 months, the captured emission is equivalent to removing 82,000 cars off the road through the year

  16. Slide 16: Operational Update Odour Management

    ECO-PRECINCT OPERATIONAL UPDATE ODOUR MANAGEMENT Completed ● Waste and rock interface gas collection in the bioreactor along the void perimeter (1000 m of horizontal gas collection) installed and connected to gas capture system - August 2024. These system are now operating ● Monthly surface monitori

  17. Slide 17: Operational Update Odour Complaints

    ECO-PRECINCT OPERATIONAL UPDATE ODOUR COMPLAINTS ● Odour complaints and events have decreased between August to November ● Odour movement is heavily dependant on weather conditions. ● Colder weather conditions show an increase in odour complaints ● Focus on implementing improvements for next winter

  18. Slide 18: ARC Project Update

    ARC PROJECT UPDATE

  19. Slide 19: Meet the Experts Overview

    MEET THE EXPERTS OVERVIEW Summary • 26 event attendees including neighbours, community representatives and Councillors • 7 informational boards covering key project aspects: ARC overview, How EfW works, Planning Process Post EIS submission, Proposed Amendment, Air quality assessment updates, Human h

  20. Slide 20: Upcoming Engagement and Timing

    UPCOMING ENGAGEMENT AND TIMING Ongoing Engagement 1:1 Briefings Engagement activities will continue in 2025, following a similar format to events held this Briefings will continue to be held with key year. community groups and councillors before the Christmas holidays. A new edition of the ARC newsl

  21. Slide 21: Environmental Compliance Update

    ENVIRONMENTAL COMPLIANCE UPDATE

  22. Slide 22: EPA Clean Up Notice

    OPERATIONAL UPDATE EPA CLEAN UP NOTICE EPA Clean Up Notice EPA issued Woodlawn a Clean Up Notice on 8 October 2024 ○ The clean up notice is Status of Clean Up Notice Woodlawn achieved compliance requirements of Clean Up Notice on 20 November ● All dams below freeboard ● 3 temporary tanks constructed

  23. Slide 23: Independent Odour Audit Updates

    INDEPENDENT ODOUR AUDIT UPDATES ACTION STATUS COMPLETION DATE ● Odour mitigation from the void Veolia have engaged a landfill engineer to undertake a review of Engaged Tonkin to undertake the landfill operating practices. ● Active tipping face Site visit 15 May This review will address odour mitigat

  24. Slide 24: PA Modifications & Post Approval Applications

    ENVIRONMENTAL COMPLIANCE UPDATE PA MODIFICATIONS & POST APPROVAL APPLICATIONS APPROVAL TYPE DESCRIPTION STATUS MP 10_0012 Modification Modify the existing project approval for the Bioreactor and MBT to: Revised submission ongoing AWT 06_0239 • Construct an approximately 15 megalitre (ML) dam at the

  25. Slide 25: Compliance Items

    Compliance items WRITTEN CONSULTATION EPL/PA DATE FACILITY DESCRIPTION CONTEXT ACTION EPL 11436 26/9/2023 Woodlawn Prevention Notice Gas Veolia has engaged a third party to undertake a review and Bioreactor characterization propose an area monitoring program. This was undertaken on analysis some of

  26. Slide 26: CLC Meeting Administration

    CLC MEETING ADMINISTRATION

  27. Slide 27: CLC Meeting Administration

    CLC MEETING ADMINISTRATION • Comment attribution in minutes • Member composition • Renomination of members after 2 years • Request to change CLC to CCC

  28. Slide 28: Vision for Woodlawn

    VISION FOR WOODLAWN

  29. Slide 29: 20 Year Vision for Woodlawn

    ECO-PRECINCT 20 YEAR VISION FOR WOODLAWN We will shortly be releasing a community flyer to show what we’ve achieved in the past 20 years of Woodlawn and to highlight our key areas of focus for the next 20 years. These areas of future focus include: • Operational improvements: We’ll continue to devel

  30. Slide 30: Community Q&A

    COMMUNITY Q&A

  31. Slide 31: CLC Questions

    CLC QUESTIONS ● Are there any questions for Veolia from the CLC ● Review emailed questions if time

  32. Slide 32: CLC New Actions

    CLC NEW ACTIONS ACTION STATUS COMPLETION DATE ● INSERT TEXT Insert text Insert tex

  33. Slide 33: Next Meeting

    NEXT MEETING The next Community Liaison Meeting will be held at the Tarago Town Hall - TBC agreed.