  1. Slide 1: Boonanarring Mineral Sands Project: Marching to Production

    1 Boonanarring Mineral Sands Project: Marching to Production Finance News Network 19 June 2018 Sydney, NSW Patrick Mutz Managing Director Image Resources NL ASX: IMA

  2. Slide 2: Forward Looking Statements

    Forward Looking Statements 2 This presentation has been prepared by the management of Image Resources NL ("Image”, “IMA“ or the ‘Company’) in connection with meetings with investors and potential investors and not as specific advice to any particular party or person. The information is based on publ

  3. Slide 3: Forward Looking Statements

    Forward Looking Statements 3 All such forward-looking information and statements are based on certain assumptions and analyses made by the Company’s management in light of their experience and perception of historical trends, current conditions and expected future developments, as well as other fact

  4. Slide 4: Image Resources NL ASX: IMA

    Company Forward Description Looking and Focus Statement 4 Image Resources NL ASX: IMA Emerging mineral sands producer Totally focused on fast-tracking the development of its 100%-owned, high-grade, zircon-rich flagship Boonanarring mineral sands project located 80km north of Perth in Western Austral

  5. Slide 5: Investor Snapshot

    Investor Snapshot 5 Opportunity to invest in a company transitioning from advanced explorer to profitable miner before it realises full valuation  Company fully funded to positive cashflow  $50M as debt; $25M as equity  Project construction underway (only $52M project capital1)  Plant and equipm

  6. Slide 6: Investor Snapshot

    Investor Snapshot 6 Opportunity to invest in a company transitioning from advanced explorer to profitable miner before it realises full valuation  Binding off-take agreement in place for 100% of production  Project NPV A$197 million1; IRR 104%1; <2 year payback1  metrics do not include 1 April 20

  7. Slide 7: Project Location

    ProjectLooking Forward Location Statement 7  LOCATION  North Perth Basin in Western Australia  80 km north of Perth CBD  Proven mineral sands address  Including majors Iluka and Tronox  Infrastructure rich  paved roads, power, gas pipeline water, telecommunications etc.  Local communities an

  8. Slide 8: Projects Types and Locations

    Projects Types and Locations 8  1,000 km2 tenements portfolio Atlas Ore Reserves  100% focus on mineral sands Probable: 9.5Mt @ 8.1% HM  Strandline projects (dry mining)  Dredge mining prospects Boonanarring Ore Reserves Proved: 9.3 Mt @ 8.6% HM Probable: 10.5Mt @ 5.9% HM

  9. Slide 9: Boonanarring Project Comparison

    Boonanarring Project Comparison 9 High HM and Zircon grades relative to peers HM grade Zircon grade* VHM HM Grade (%) Zircon (%) 14.0% 25% VHM Grade Zircon % Image Resources (IMA) Boonanarring project 12.0% 21.5Mt @ 8.3% HM and up to 24.5% Zircon 20% 10.0% 15% 8.0% 6.0% 10% 4.0% H 5% 2.0% 0.0% 0% SF

  10. Slide 10: Ore Reserves

    Ore Reserves Forward Looking Statement 10  QUALITY ORE RESERVES  JORC Code (2012) Compliant  High HM, VHM and very high zircon at Boonanarring High Grade Ore Reserves ‐ Strand Deposits; in accordance with the JORC Code (2012) Project/Deposit Category Volume Tonnes % HM % Slimes HM Tonnes VHM Ilme

  11. Slide 11: Ore Reserves Comparison

    Ore Reserves Forward LookingComparison Statement 11 IMAGE X Mined‐out Grade decreasing Source: TZMI; May 2017

  12. Slide 12: Products and Prices

    Products and Prices 12 Notes: VHM assemblages and commodity prices are estimates based on Boonanarring project heavy mineral concentrate product.

  13. Slide 13: Bankable Feasibility Study

    Bankable Forward Feasibility Looking Study Statement 13 Base Assumptions  Start mining at Boonanarring  Dry, open-cut mining  Production rate - 500 dry tonnes per hour • 3.7M dry tonnes per year  Conventional gravity separation using spirals  Product: Heavy Mineral Concentrate (HMC) • Productio

  14. Slide 14: Bankable Feasibility Study

    Bankable Forward Feasibility Looking Study Statement 14 Key Financial Metrics Original BFS* Updated BFS**  Pre-Tax NPV (@ 8%) A$135M A$197M  Pre-Tax IRR 64% 104%  Payback period (months) 22 16  Mine life 8+ years  Project capital cost A$52M  includes ~$8M for land * ASX Announcement 30 May 201

  15. Slide 15: Project Capital Comparison

    Project Forward Capital Looking Comparison Statement 15 Source: TZMI; May 2017

  16. Slide 16: Boonanarring – Production Statistics

    Boonanarring – Production Statistics 16 Note: 2023 information includes the start of production at Atlas.

  17. Slide 17: Boonanarring Project EBITDA Summary

    Boonanarring – Project EBITDA 17 Boonanarring Project EBITDA Summary (AU$'000) 2018 2019 2020 2021 2022 2023 Total Revenue 8,880 132,600 186,900 97,200 127,200 77,400 630,180 Revenue/tonne HMC 475 589 584 512 578 455 551 Operating Costs Mining 22,400 43,800 40,100 39,300 40,900 36,700 223,200 Proces

  18. Slide 18: Commodity Prices – Actual and Projected

    Forward Looking Commodity PricesStatement – Actual and Projected 18 Projected price increase prior to first production Latest price rise not included in financial metrics

  19. Slide 19: Image Wet Concentration Plant

    Image Wet Forward Concentration Looking Statement Plant 19

  20. Slide 20: Site Construction Photos

    Site Construction Photos 20 Overburden stockpile Overburden removal Wet Concentration Plant construction

  21. Slide 21: Project Development Schedule

    Project Development Schedule 21 Targeting first production 4th Quarter 2018 Simplified Boonanarring Project Construction Schedule ‐ (high level) 2018 2019 May Mar Mar Nov Aug Dec Apr Oct Feb Sep Feb Jan Jun Jan Jul WCP & Equipment Relocation Project Construction Pre‐Stripping Ore Mining Plant Commis

  22. Slide 22: Upside Potential

    Upside Looking Forward Potential Statement 22 Upside potential at and near Boonanarring  Confirmed potential to extend mine life with high grade mineralisation (ASX announcement 13 March & 26 June 2017);  Assuming mineralisation in extension area is identical to known Ore Reserves in all aspects a

  23. Slide 23: Boonanarring Deposit Extensions

    Boonanarring Deposit Extensions 23 ASX - 13 March & 26 June 2017 New Drilling Results (Feb 2017)  Confirm 5.6km northern extension of Boonanarring mineralisation  Outstanding high grade intersections:  8m @ 23.8% HM in IX00245  8m @ 21.1% HM in IX00244 and  8m @ 16.3% HM in IX00250 Importantly

  24. Slide 24: Projects Pyramid – Strand Deposits

    ProjectsLooking Forward Pyramid – Strand Deposits Statement 24 Mineral Resources – Accessible by Dry Open‐Cut Mining BFS assumes Projects ranked by combined mining at Zircon (Zr) plus Rutile (Ru) Boonanarring followed by Tonnes-grades are for Mineral Resources; Boonanarring and Atlas per JORC Code (

  25. Slide 25: Projects Pyramid – Dredge Deposits

    ProjectsLooking Forward Pyramid – Dredge Deposits Statement 25 Mineral Resources – Accessible by Dredge Mining Projects ranked by HM Grade Potential focus area for phase two growth strategy. Positive attributes: Bidaminna • 90+%VHM; Tonnes-grades are for historic Mineral Resources per JORC Code (200

  26. Slide 26: Potential Royalty from Tronox

    Potential Royalty from Tronox 26 Royalty agreement in place as of 2014  Small cash payment (already received)  Sliding-scale royalty on production Avg. HM Grade Royalty 2.5% 1.25% 3.0% 2.50% 3.5% 3.75% 4.0% 5.00%  Indefinite production schedule  Potential for future arrangements with Tronox or o

  27. Slide 27: Corporate Snapshot

    Corporate Image Snapshot Corporate Snapshot 27 Diverse and experienced Board and Management ASX Code: IMA Board of Directors Share Price: A$0.12* Bob Besley – Independent Chairman 12-Month Price Range: A$0.07– 0.17 Patrick Mutz – Managing Director Shares on Issue: 953m Chaodian Chen - Non-Executive

  28. Slide 28: Relative Value: Transition from Explorer to Producer

    Contact from Explorer to Producer Transition 28 Generalisation of Transition from Explorer to Producer 10 9 Project Production 8 Development (realisation Discovery (feasibility 7 of full value) & Resource results; Relative Value 6 Delineation Study Period mine decision; 5 (excitement; (uncertainty;

  29. Slide 29: Corporate Snapshot: Use of Solar Energy

    Corporate Snapshot Use of Solar Energy 29 Heads of Agreement with Sunrise Energy Group Pty Ltd to provide 3-4 MWAC solar farm to be:  Constructed and operated by Sunrise Energy;  Located on Image owned land adjacent to Boonanarring mine site; and  Providing 25% of total electricity requirements f

  30. Slide 30: Contact

    Contact For further information 30 Patrick Mutz Managing Director Image Resources NL info@imageres.com.au Office: +61 8 9485 2410 Ground Floor, 23 Ventnor Avenue West Perth, WA 6005 PO Box 469, West Perth, WA 6872 www.imageres.com.au

  31. Slide 31: Additional Information

    Forward Looking Statement 31 Additional Information

  32. Slide 32: Project Funding

    Project Funding 32 Boonanarring is now fully funded to positive cashflow and construction has begun  Overall capital requirement: A$75 million  Includes project capital, corporate, exploration, working capital and fund raising costs  Equity Capital: A$25 million  A$25 million fully-underwritten

  33. Slide 33: Compliance Statements

    Compliance Statements Forward Looking Statement 33 COMPLIANCE STATEMENT FOR EXPLORATION Information in this presentation that relates to Exploration Results is based on information compiled by George Sakalidis BSc (Hons) who is a member of the Australasian Institute of Mining and Metallurgy. At the

  34. Slide 34: Mineral Resources – Strand Deposits

    Mineral Forward Resources – Strand Deposits Looking Statement 34 Strand Deposits 1 of 2 High Grade Mineral Resources ‐ Strand Deposits; in accordance with the JORC Code (2012) @ 2.0% HM Cut‐off Project/Deposit Category Volume Tonnes % HM % Slimes HM Tonnes VHM Ilmenite Leucoxene Rutile Zircon (%) (%

  35. Slide 35: Mineral Resources – Strand Deposits

    Mineral Forward Resources – Strand Deposits Looking Statement 35 Strand Deposits 2 of 2 Previously Reported Mineral Resources ‐ Strand Deposits; in accordance with JORC Code (2004) @ 2.5% HM Cut‐off Project/Deposit Category Volume Tonnes % HM % Slimes HM Tonnes VHM Ilmenite Leucoxene Rutile Zircon (

  36. Slide 36: Mineral Resources – Dredge Deposits

    Mineral ForwardResources – Dredge Deposits Looking Statement 36 Dredge Deposits 1 of 1 Previously Reported Mineral Resources ‐ Dredge deposits; in accordance with JORC Code (2004) @ 1.0% HM Cut‐off Project/Deposit Category Volume Tonnes % HM % Slimes HM Tonnes VHM Ilmenite Leucoxene Rutile Zircon (%

  37. Slide 37: Compliance Statements

    Forward Looking Compliance Statement Statements 37 COMPLIANCE STATEMENT FOR MINERAL RESOURCES 1. COMPLIANCE STATEMENT Boonanarring/Atlas Mineral Resources The information in this presentation that relates to the estimation of Mineral Resources is based on information compiled by Mrs Christine Standi