Hydro One Limited · TSX:H

Hydro One — Hydro One Networks — Corporate Update (June 2008)

8 slides from Hydro One's corporate update, Jun 23, 2008

  1. Slide 1: Hydro One Networks Supply to Essex County Next Steps

    Hydro One Networks Supply to Essex County Next Steps Ajay Garg Manager, Investment Policies & Approvals June 23, 2008 1

  2. Slide 2: Next steps

    Next steps • Continue with Class EA process and public consultation activities • Continue work on the Ontario Energy Board “Leave to Construct” submission (Section 92) • Project timelines are critical 2

  3. Slide 3: Target Project Timelines

    Target Project Timelines Next Steps Dates Identify and announce recommended transmission alternative July 2008 Identify preferred TS site (Leamington) and transmission line route September 2008 Draft Environmental Study Report (ESR) available for public/stakeholder review & comment Fall 2008 Anticip

  4. Slide 4: Project Approvals Process

    Project Approvals Process Ontario Energy Post OEB and MoE Board (OEB) Approvals Section 92 OEB Filing Build In & Service Construct Consultations Public Environmental with Key Information Study Report MoE Stakeholders Centre(s) (ESR) Pre-Application Ministry of the Environment (MoE) 4

  5. Slide 5: Upcoming Public Consultation Activities

    Upcoming Public Consultation Activities July 2008 • Council presentations, at your request • Briefings for local MPPs • Announce recommended transmission alternative (Alternative 2) via newspaper ads and flyers to property owners • Second round of Public Information Centres (PICs) in Tecumseh and Le

  6. Slide 6: Subsequent Public Consultation Activities

    Subsequent Public Consultation Activities • Third PIC in Leamington area (September 2008) to present and seek input on preferred TS site and transmission line route • Public review and comment on Hydro One’s draft Environmental Study Report (ESR) • Opportunity for public participation in the Ontario

  7. Slide 7: We value your assistance and support

    We value your assistance and support • Assistance with: – planning/land use data and other information to assist our project team in evaluating options – property owner mailing information for public notification at next stages – making the draft ESR available to the public at your Clerk’s Office /P

  8. Slide 8: Project and Contact Information

    Project and Contact Information • Website: www.HydroOneNetworks.com • Toll Free Project Line: 1-877-345-6799 • Email: Community.Relations@HydroOne.com 8

Hydro One Networks — Corporate Update (June 2008) on 6ix