Sbm Offshore Nv — H1 2008 Earnings Presentation

25 slides from Sbm Offshore Nv's earnings presentation, Aug 20, 2008

  1. Slide 1: Half-Year Results 2008 Analysts Presentation

    HALF-YEAR RESULTS 2008 Analysts Presentation August 20, 2008 T. Mace, CEO and M. Miles, CFO

  2. Slide 2: Disclaimer

    DISCLAIMER Some of the statements contained in this presentation that are not historical facts are statements of future expectations and other forward- looking statements based on management’s current views and assumptions and involve known and unknown risks and uncertainties that could cause actual

  3. Slide 3: Summary

    SUMMARY ƒ 2005 decision to grow the Company in buoyant conditions ƒ Several large contracts awarded 2005/2006 & delivered in 2008 ƒ Coincidental overheating of suppliers & yards ƒ Budget & schedule overruns affect 2007/2008 results ƒ Tighter bidding controls implemented ƒ Subsequent projects under c

  4. Slide 4: 2005/2006 Projects

    2005/2006 PROJECTS ƒ Equipment ƒ Long bid phase - escalating costs ƒ Long delivery - capacity overbooked ƒ Yard ƒ Growth in scope (late deliveries) - escalating costs ƒ Manpower constrained ƒ Schedule acceleration costs ƒ SBM manhours ƒ Engineering - most complex FPSO (Frade) ƒ Project team - extend

  5. Slide 5: Enhanced Project Controls

    ENHANCED PROJECT CONTROLS Bid Process: ƒ Quality of proposal - Technical definition / scope ƒ Back to back validity with suppliers / client ƒ Pass through of the costs / risks to client ƒ Confirmed yard capacity ƒ Contractual terms and conditions Execution Phase: ƒ Budget control - Cost Engineers -

  6. Slide 6: Major Project Schedules

    MAJOR PROJECT SCHEDULES 2004 2005 2006 2007 2008 2009 2010 Lease Petrobras - Capixaba Murphy - Kikeh ExxonMobil - Mondo ExxonMobil - Saxi Batuque Shell - BC-10 Murphy - Thunder Hawk Talisman - Yme Encana - Deep Panuke Petrobras - Cachalote Turnkey Chevron - Frade Rigs 1,2,3 Woodside - CWLH Petrobras

  7. Slide 7: Current Order Portfolio

    CURRENT ORDER PORTFOLIO Lease Shell – BC10 FPSO on lease for Shell in BC-10 field offshore Brazil Contract award: Q3, 2006 Completion: Q4, 2008 Murphy – Thunder Hawk Semi-Submersible oil & gas production facility in GOM Contract award: Q4, 2006 Completion: Q4, 2008 Talisman – Yme MOPUstor in Norwegi

  8. Slide 8: Current Order Portfolio

    CURRENT ORDER PORTFOLIO Lease Encana – Deep Panuke Mopu offshore Nova Scotia, Canada Contract Award: Q4, 2007 Completion: Q3, 2010 Petrobras – Cachalote Upgrade and relocation of Capixaba FPSO to Cachalote field, Brazil Contract award: Q2, 2008 Completion: Q4, 2009 8

  9. Slide 9: Current Order Portfolio

    CURRENT ORDER PORTFOLIO Turnkey Chevron – Frade Supply of an FPSO Contract award: Q2, 2006 Completion: Q4, 2008 Odebrecht - Delba – QGP Supply of Drilling Rigs x 3 Contract award: Q4, 2006 - Q1, 2007 Completion: Q2, 2009 – Q3, 2009 – Q1, 2010 Woodside – CWLH redevelopment Supply of an FPSO Contract

  10. Slide 10: Current Order Portfolio

    CURRENT ORDER PORTFOLIO Turnkey Petrobras – P57 Supply of an FPSO and three year operation. Contract Award: Q1, 2008 Completion: Q4, 2010 BP Angola Frame agreement for supply of FPSOs on a call off basis First Project Sanction: H2, 2009 Completion: 36 months after project sanction 10

  11. Slide 11: Milestones First Half 2008

    MILESTONES FIRST HALF 2008 ƒ FPSO Mondo started operation offshore Angola ƒ Contract with Petrobras for supply of the P-57 FPSO for Brazil ƒ Letter of Intent with Woodside for supply of an FPSO to replace the existing Cossack Pioneer, offshore Australia ƒ Contract for the upgrade and relocation of t

  12. Slide 12: Financial Overview First Half 2008

    FINANCIAL OVERVIEW FIRST HALF 2008 P&L Total Group In millions of US Dollars 30/06/08 30/06/07 Change Comment Turnover 1,497 1,388 8% 73% Turnkey, 27% Lease & Operate Gross Margin 176 220 Cost overruns on Turnkey; Mystras (20%) sale; Increasing Lease & Operate (%) (11.8%) (15.8%) contribution EBITDA

  13. Slide 13: Financial Overview First Half 2008: Turnkey Systems & Services

    FINANCIAL OVERVIEW FIRST HALF 2008 Turnkey Systems & Services In millions of US Dollars 30/06/08 30/06/07 Change Comment Includes Mystras sale US$ 60 mln. Turnover 1,088 1,055 3% Growing Services Gross Margin 41 120 Cost overruns – mainly Frade & Saxi Batuque FPSOs; (%) (3.8%) (11.4%) (66%) Includes

  14. Slide 14: Financial Overview First Half 2008: FPSO Lease and Operate

    FINANCIAL OVERVIEW FIRST HALF 2008 FPSO Lease and Operate In millions of US Dollars 30/06/08 30/06/07 Change Comment Kikeh and Mondo FPSOs full six Turnover 409 334 22% months; V.O.s Turkmenistan and OKHA; Trading Fleet Gross Margin 134 100 As above; High bonus levels; Low 34% operating costs; Relea

  15. Slide 15: Financial Overview First Half 2008: Ratios Total Group

    FINANCIAL OVERVIEW FIRST HALF 2008 Ratios Total Group In millions of US Dollars 30/06/08 31/12/07 Change Comment 551 (12 m) Yme MOPUstor, Thunder Hawk semi, BC-10 Capital Expenditure 516 x 2.4 FPSO 219 (6 m) Accelerating capex. New loans arranged for Long-Term Debt 1,526 1,149 33% Saxi Batuque and B

  16. Slide 16: Expectations 2008

    EXPECTATIONS 2008 FINANCIAL ƒ Full year 2008 forecast profit below original target by up to 20% (i.e US$ 225 million) ƒ Capital expenditure of US$ 1 billion ƒ Intention to maintain dividend at 2007 level (US$ 0.93 per share) ACTIVITIES ƒ Delivery of Frade, BC-10 and Thunder Hawk ƒ End of charters fo

  17. Slide 17: Remaining Duration of Lease Contracts

    REMAINING DURATION OF LEASE CONTRACTS 09/20 17

  18. Slide 18: FPSO Prospects

    FPSO PROSPECTS Nsiko Bonga SW UGE Bosi Shtokman Chevron Shell ExxonMobil ExxonMobil Gazprom Nigeria Nigeria Nigeria Nigeria Russia Carioca Petrobras Brazil BS-4 Shell Brazil HaiSu Trang TLJOC Papa Terra Vietnam Petrobras Brazil Benita Tupi Noble Energy Petrobras Equatorial Guinea Brazil Jupiter Petr

  19. Slide 19: Non-FPSO Prospects

    NON-FPSO PROSPECTS Semi-sub FSRU Turret FSO / Turret Big Foot (Components) Shtokman Bouri Chevron New York Gazprom ENI Libya TLP PONY HESS Semi-sub Semi / TLP K2 Malikai Anadarko Shell TLP Knottyhead Turret Nexen Cepu ExxonMobil Semi-sub TLP FSRU FSRU DW CALM Turret Jack Papa Terra Suapeto RSA Usan

  20. Slide 20: FPSO Orders 2008

    FPSO ORDERS 2008 LEASE ƒ Urugua/Tambau in Brazil for Petrobras - Modec (SBM no.3) ƒ Cachalote in Brazil for Petrobras - SBM Offshore ƒ Tupi in Brazil, Pilot for Petrobras - Modec (SBM no. 2) ƒ Jubilee in Ghana, for Tullow Oil - Modec (SBM no.3) ƒ Tupi in Brazil, EPS for Petrobras - BW Offshore ƒ Ath

  21. Slide 21: Lease Contractors

    LEASE CONTRACTORS Units in Operation or Under Construction 21 Status: August 15, 2008

  22. Slide 22: SBM/Linde LNG FPSO

    SBM/Linde LNG FPSO Floating Production, Liquefaction, Storage and Offloading Unit ƒ Generic design completed ƒ Yard slot under negotiation ƒ Pursuing prospects ƒ Competition: - Hoegh / CBI - Golar / LNGL - JGC / Modec - BW Offshore / Mustang - Flex LNG - Shell 22

  23. Slide 23: New Technology

    NEW TECHNOLOGY MoorsparTM Riser Buoy FourStarTM TLP LNG Hose Wave energy conversion systems 23

  24. Slide 24: Strategy

    STRATEGY ƒ Expand the lease business model to cover more products and geographical areas ƒ Develop a pole position in the gas sector and particularly offshore LNG ƒ Maintain a position of leader in the Group’s current markets ƒ Develop innovative technical solutions, in particular for deepwater tech

  25. Slide 25: Questions and Answers

    HALF-YEAR RESULTS 2008 Analysts Presentation August 20, 2008 QUESTIONS AND ANSWERS