  1. Slide 1: Community Consultative Committee

    Community Consultative Committee November 2016

  2. Slide 2: Agenda item 3 - Correspondence

    Agenda item 3 - Correspondence Environment Protection Licence – Annual return paperwork issued Notice Response to Notice Issued 2013 and 2014 AEMR to Department of Planning Independent Audit issued to Department of Planning Modified conditions of consent for modification 4 received Management plans

  3. Slide 3: Agenda item 4 – Operations

    Agenda item 4 – Operations Safety - Achieved zero LTI’s throughout the last 3 months including zero harm to our employees and contractors in both August and October. Overburden - No further overburden works until July/August 2017 Pit update - Commenced additional hours of operation for the pit - Com

  4. Slide 4: Agenda item 5 – OH&S Performance

    Agenda item 5 – OH&S Performance No loss time injuries Zero Harm across the quarry business for October – no injuries Audiometric testing for employees conducted Testing of Clean space air respirators Personal dosimetry dust testing Internal audit and testing of fire suppression systems 4

  5. Slide 5: Environmental Performance: Incidents

    Agenda Item 6 - Environmental Performance Incidents (EPL period June 2014 – July 2015) Environmental Incidents (EPL July 14to 16) 6.00 5.00 # of incidents 4.00 3.00 2.00 1.00 0.00 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 D

  6. Slide 6: Environmental Complaints

    Agenda item 6 – Environmental Performance Complaints Environmental Complaints (EPL July 14 to 16) 14.00 No. of complaints 12.00 10.00 8.00 6.00 4.00 2.00 0.00 Jul-14 Aug- Sep- Oct-14 Nov- Dec- Jan-15 Feb- Mar- Apr-15 May- Jun-15 Jul-15 Aug- Sep- Oct-15 Nov- Dec- Jan-16 Feb- Mar- Apr-16 May- Jun-16 J

  7. Slide 7: Air: Deposited Dust, Onsite (NW boundary)

    Agenda item 6 – Environmental Performance Air Peppertree Quarry Deposited Dust 2015-2016 Onsite (NW boundary) 14 12 10 g/m2/month 8 6 4 2 0 Jul-2016 Aug- Sep- Oct- Nov- Dec- Jan- Feb- Mar- Apr- May- Jun- Annual 2016 2016 2016 2016 2016 2017 2017 2017 2017 2017 2017 average Month Insoluble solids Ash

  8. Slide 8: Air: Deposited Dust, Marulan South Road

    Agenda item 6 – Environmental Performance Air Peppertree Quarry Deposited Dust 2015 - 2016 683 Marulan South Road 14 12 10 g/m2/month 8 6 4 2 0 Jul-2016 Aug- Sep- Oct- Nov- Dec- Jan- Feb- Mar- Apr- May- Jun- Annual 2016 2016 2016 2016 2016 2017 2017 2017 2017 2017 2017 average Month Insoluble solids

  9. Slide 9: Air: Deposited Dust, Long Point Road, Tallong

    Agenda item 6 – Environmental Performance Air Peppertree Quarry Deposited Dust 2015-2016 432 Long Point Road, Tallong 14 12 10 g/m2/month 8 6 4 2 0 Jul-2016 Aug- Sep- Oct- Nov- Dec- Jan- Feb- Mar- Apr- May- Jun- Annual 2016 2016 2016 2016 2016 2017 2017 2017 2017 2017 2017 average Month Insoluble so

  10. Slide 10: Air – Particulate Matter <10 microns

    Agenda item 6 – Environmental Performance Air – Particulate Matter <10 microns (EPL period July 2016 – July 2017) Peppertree Quarry PM10 (EPL 2015-2016) 60 50 40 PM10 (ug/m3) PM10 30 PM10 24 hour goal PM10 annual average goal 20 10 0 sampling date PM10 below annual average goal 10

  11. Slide 11: Air - Total Suspended Particulates

    Agenda item 6 – Environmental Performance Air - Total Suspended Particulates (EPL period July 2016 – July 2017) Peppertree Quarry TSP (EPL 2015-2016) 100 90 80 TSP (ug/m3) 70 60 TSP 50 40 TSP annual average goal 30 20 10 0 sampling date TSP below Annual average goal 11

  12. Slide 12: Noise - quarterly noise monitoring, daytime

    Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring July (august) 2016 All sensitive receiver sites monitored In compliance – daytime Predicted Site Noise Level Receiver Date Contribution Operational Criteria (dB(A)) EPL ID Name LAeq, 15 minute (dB(A)) daytime 16th August 20

  13. Slide 13: Noise - quarterly noise monitoring, evening

    Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring July (August) 2016 All sensitive receiver sites monitored In compliance - evening Operational Criteria Receiver Date Site Noise Level Contribution (dB(A)) EPL ID Name Leq, 15 minute (dB(A)) evening 18th August 2016 2 Ordasi

  14. Slide 14: Noise - quarterly noise monitoring, evening 1min

    Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring July (August) 2016 All sensitive receiver sites monitored In compliance – evening 1min Receiver Date Site Noise Level Contribution Operational Criteria (dB(A)) EPL ID Name LA1, 1 minute (dB(A)) evening 17th August 2016 34 5

  15. Slide 15: Noise - quarterly noise monitoring October 2016

    Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring October2016 Monitoring was conducted in October 2016 New conditions of consent in place for Modification 4 Site #2 no longer to be monitored as property now owned by Boral 2 new additional sensitive receivers to be monitore

  16. Slide 16: Blast monitoring: Overpressure

    Agenda item 6 – Environmental Performance Blast monitoring (EPL 2016-2017) Overpressure 140 120 100 north west boundary 80 north east boundary 60 683 Marulan sth road 40 Pace criteria 5% 20 criteria 100% 0 29/07/2016 18/08/2016 7/09/2016 27/09/2016 17/10/2016 6/11/2016 26/11/2016 All in compliance 1

  17. Slide 17: Blast monitoring: Vibration

    Agenda item 6 – Environmental Performance Blast monitoring (EPL 2016-2017) vibration 12 10 8 ppv 6 north west boundary 4 north east boundary 683 Marulan sth road 2 Pace criteria 5% criteria 100% 0 29/07/2016 18/08/2016 7/09/2016 27/09/2016 17/10/2016 6/11/2016 26/11/2016 date All in compliance 17

  18. Slide 18: Surface water

    Agenda item 6 – Environmental Performance Surface water surface water samples taken quarterly from 3 sites and after large rainfall events U1 – upstream / dam – pump in the main dam / T1 – Tangarang creek Quarterly monitoring round undertaken on 5th September 2016 All sites sampled. Analyses compare

  19. Slide 19: Ground water elevation

    Agenda item 6 – Environmental Performance Ground water Ground water Elevation – sentinel well (MW05) 19

  20. Slide 20: Ground water monitoring wells

    Agenda item 6 – Environmental Performance Ground water 12 groundwater monitoring wells installed Monitored quarterly by consultant 4 rounds monitored to date Results compared to ANZECC guidelines Last round of monitoring conducted 20th October 2016. All results are in compliance with some exceptions

  21. Slide 21: Ground water

    Agenda item 6 – Environmental Performance Ground water 21

  22. Slide 22: Environmental flow

    Agenda item 6 – Environmental Performance Environmental flow 35 2016 Main Dam flow 30 25 flow in megalitres 20 total in flow 15 10% criteria total outflow 10 5 0 Jan Feb March April May June July Aug Sept Oct Nov dec annual total to date date 22

  23. Slide 23: Heritage

    Agenda item 6 – Environmental Performance Heritage Management plan revised and issued for approval 23

  24. Slide 24: Ecology

    Agenda item 6 – Environmental Performance Ecology Rehab maintenance work ongoing Review of the success and replacement plantings to be undertaken in December with proposed planting in March 2017 24

  25. Slide 25: Stakeholder Engagement

    Agenda item 6 – Stakeholder Engagement HASP project CVA schools program – Tallong Marulan Kite festival Bloody Long walk Outward Bound - projects - Next program February 2017 Movember 25

  26. Slide 26: Plans for the next three months

    Agenda item 7 – Plans for the next three months Safety - Maintain zero harm to our employees and contractors Overburden - No further overburden works until July/August 2017 Pit update - Continue to develop the drop cut with target of April for completion Processing - Continue to increase output to a

  27. Slide 27: General Business

    Agenda item 8 – General Business Weather station update - Review of data provided for the last 12 months Marulan South Limestone update - Still being prepared Next meeting dates – February 2017 27

  28. Slide 28: END

    END 28