Bci Minerals Ltd · ASX:BCI

Bci Minerals — BC Iron — Global Iron Ore and Steel Conference (March 2016)

21 slides from Bci Minerals's conference presentation, Mar 9, 2016

  1. Slide 1: BC Iron and the Buckland Project

    For personal use only Global Iron Ore and Steel Conference BC Iron and the Buckland Project Morgan Ball – Managing Director ASX:BCI 9-Mar-16

  2. Slide 2: BC Iron Key Assets

    BC IRON KEY ASSETS For personal use only Cape Preston East Port Tenure 20 year lease Status Optimising feasibility study Capacity 20Mtpa Nullagine JV Ownership 75% Temporary Status Suspension Bungaroo South Capacity 6 Mtpa DSO Reserves1 21Mt @ 56.9% Fe Buckland Project Ownership 100% DSO Resources1

  3. Slide 3: Corporate Overview

    CORPORATE OVERVIEW For personal use only Capital Structure Board and Management Ordinary Shares 196.2m Tony Kiernan Non-Executive Chairman Share Price (at 8-Mar-16) $0.215 Morgan Ball Managing Director Market Capitalisation $42.2m Martin Bryant Non-Executive Director Cash (at 31-Dec-15) $42.9m Andy

  4. Slide 4: Iron Valley

    IRON VALLEY For personal use only Operating mine that is generating cash flows via iron ore sale agreement with MIN.  Iron ore sale agreement with Mineral Resources Limited (MIN)  BC Iron retains tenement ownership and statutory obligations (incl. government royalties)  MIN operates the mine at M

  5. Slide 5: Nullagine Joint Venture

    NULLAGINE JOINT VENTURE For personal use only Mine with access to world-class infrastructure. Currently in temporary suspension.  Located ~55km north of FMG’s Christmas Creek  Unincorporated joint venture – 75% BCI, 25% FMG  BC Iron is the manager of the NJV  FMG provides rail & port and marketi

  6. Slide 6: Buckland

    BUCKLAND For personal use only Strategic mine-to-port development project located in the West Pilbara.  Wholly owned project located in the West Pilbara region  Ore Reserve of 134.3 Mt at 57.6% Fe1 and Mineral Resource of 283.2 Mt at 56.5% Fe1  Feasibility study (“FS”) completed by IOH in June 20

  7. Slide 7: Cape Preston East

    CAPE PRESTON EAST For personal use only Proposed low capital cost transhipment port with capacity for additional tonnes.  Existing port lease agreements with the Pilbara Ports Authority (“PPA”)  Right to construct and operate onshore & marine facilities (subject to the satisfaction of certain cond

  8. Slide 8: Recent Work on Buckland

    RECENT WORK ON BUCKLAND For personal use only  Cape Preston East construction approvals being advanced with the PPA Approvals  Bungaroo South mining proposal submitted – approval anticipated in Jun-16 quarter  Road haulage optimisation studies Optimisation  Re-pricing of select value capital wor

  9. Slide 9: Current Capex and Opex Estimates

    CURRENT CAPEX AND OPEX ESTIMATES For personal use only Optimisation work to date has materially improved the economics for an independent 8 Mtpa mine-to-port operation at Buckland. Capital Cost Estimate (± 25%) Jun-14 Estimate1 Dec-15 Estimate (A$M) (A$M) Upfront Capital Cost 826 879 Deferred Capita

  10. Slide 10: Road Haulage Optimisation Studies

    ROAD HAULAGE OPTIMISATION STUDIES For personal use only Optimsation studies reduced haulage cost estimate by nearly 50% to A$7.9/wmt.  Haulage costs were ~40% of the Jun-14 C1 cash costs  Optimisation studies considered prime movers, trailer configurations and autonomous technology  Revised road

  11. Slide 11: API Co-operative Mining Study

    API CO-OPERATIVE MINING STUDY For personal use only  Joint study undertaken by API and BC Iron relating to the contiguous Buckland Hills and Bungaroo South deposits  Study results highlighted the benefits of co-operation – mainly, accessing ore up to the tenement boundaries  BC Iron and API have

  12. Slide 12: Infrastructure Expansion Studies

    INFRASTRUCTURE EXPANSION STUDIES For personal use only Preliminary work on an expanded 20 Mtpa road and port infrastructure operation expected to underpin attractive tariffs for potential third party users.  Current Cape Preston East lease agreements envisage Capital Cost Estimate (± 35%) BC Iron c

  13. Slide 13: Buckland – Next Steps

    BUCKLAND – NEXT STEPS For personal use only BC Iron plans to continue to de-risk and improve the Buckland Project.  Continue to the Cape Preston East approvals process with the PPA  Further improve economics of the independent 8 Mtpa mine- to-port operation  Target further capital and operating c

  14. Slide 14: Exploration Projects

    EXPLORATION PROJECTS For personal use only  Portfolio of exploration projects  Prospective for commodities other than iron ore – base metals, gold and salt  Identifying highest priority targets  Considering a modest greenfields exploration programme  Focus on Mt Fraser, Peak Hill, Black Hill an

  15. Slide 15: Summary

    SUMMARY For personal use only  Operating mine that is generating cash flows via iron ore sale agreement with MIN Iron Valley  Currently being operated as a ~6 Mtpa DSO, truck haulage operation  MIN evaluating potential expansion to 16 Mtpa via construction BOTS  Strategic mine-to-port developmen

  16. Slide 16: Iron Valley Reserves & Resources

    IRON VALLEY RESERVES & RESOURCES For personal use only Mineral Resource at 30 June 2015 (100% BC Iron, subject to iron ore sale agreement with MIN) Classification Cut-off (% Fe) Tonnes (Mt) Fe (%) CaFe (%) SiO2 (%) Al203 (%) P (%) LOI (%) Measured 50 34.9 59.4 63.8 4.7 2.8 0.17 6.9 Indicated 50 172.

  17. Slide 17: Buckland Reserves & Resources

    BUCKLAND RESERVES & RESOURCES For personal use only Mineral Resource at 30 June 2015 (100% BC Iron) Deposit Classification Cut-off (%Fe) Tonnes (Mt) Fe (%) CaFe (%) SiO2 (%) Al2O3 (%) P (%) LOI (%) Bungaroo Measured 50 30.9 57.4 62.1 6.7 3.0 0.15 7.6 South Indicated 50 214.9 56.6 61.6 7.8 2.4 0.15 8

  18. Slide 18: NJV Reserves & Resources

    NJV RESERVES & RESOURCES For personal use only CID Mineral Resource at 30 June 2015 (BC Iron 75%, FMG 25%) Classification Mt Fe% CaFe% Al2O3% SiO2% P% S% LOI Measured 10.2 52.7 60.1 4.5 5.1 0.017 0.012 12.4 Indicated 34.1 54.2 62.0 3.2 4.3 0.017 0.011 12.5 Inferred 47.6 51.9 58.6 5.5 6.7 0.023 0.019

  19. Slide 19: Important Notices

    IMPORTANT NOTICES For personal use only This document has been prepared by BC Iron Limited (“BC Iron”) to provide an update regarding the companies to investors. Past performance Past performance information given in this document is given for illustrative purposes only and should not be relied upon

  20. Slide 20: Important Notices

    IMPORTANT NOTICES For personal use only Ore Reserves and Mineral Resources Disclosures The information in this announcement that relates to Mineral Resources and Ore Reserves at the Nullagine Joint Venture is extracted from the ASX announcement entitled NJV Ore Reserves and Mineral Resources dated 2

  21. Slide 21: For personal use only

    For personal use only Level 1, 15 Rheola Street West Perth, WA, Australia Phone : +61 8 6311 3400 Email : info@bciron.com.au Web : www.bciron.com.au

BC Iron — Global Iron Ore and Steel Conference (March 2016) on 6ix