ShaMaran Petroleum Ltd. · OSL:SNM
ShaMaran Petroleum — Investor Presentation (March 2016)
21 slides from ShaMaran Petroleum's investor presentation, March 2016
Slide 1: Corporate Presentation
Corporate Presentation March 2016 ShaMaran – A Lundin Group Company
Slide 2: Strategy
Strategy Focus on project execution to get to Atrush first oil • Four wells ready for production • Pipeline work started and facilities construction progressing • First oil targeted for mid-2016 • Significant challenges remain in Kurdistan environment which may impact schedule Additional funding
Slide 3: Atrush block in Iraqi Kurdistan
Atrush block in Iraqi Kurdistan Awarded in 2007 Atrush ShaMaran acquired interest in 2010 Kurdistan Discovered Atrush in 2011 Partners / working interests • Shamaran / 26.8% • Taqa (Operator) / 53.2% • Marathon / 20% • KRG / up to 25% right to back in • In March 2013 the KRG gave notice of i
Slide 4: Atrush is a world class large oil discovery
Atrush is a world class large oil discovery Discovered in 2011 Jurassic fractured carbonate Large 25x3 km structure • fault bounded - 3 way dip closed 1.5 - 2.8 billion barrels in place FDP approved October 2013 7 wells drilled to date FDP Update presented in November 2015 Further ph
Slide 5: Reserves increase proves excellent potential
Reserves increase proves excellent potential Positive test results proved up a larger reserves area Reserves to be developed by 5 wells (4 existing wells plus CK-7) End 2015 Reserves and Resource increase • Gross 2P Reserves increased from 61.5 MMboe to 85.1 MMboe • Gross 2P + 2C Resources inc
Slide 6: Atrush Phase 1 development ongoing
Atrush Phase 1 development ongoing FDP Phase 1 approved in October Atrush block boundary 2013 30,000 bopd Central Processing Phase 1 Facilities under construction Further Phases 4 wells ready for production Saikhan block • CK-5 and CK-8 completed in Q3 2015 • AT-2 and AT-4 to be completed in Q
Slide 7: Well tests show excellent productivity
Well tests show excellent productivity Medium oil column • ~420 m 25o-27oAPI oil column 9,059 bopd 27oAPI • Excellent productivity • Communication east-west 8,200 bopd • No formation water on test 26oAPI • Good vertical communication • Proven in Upper Jurassic and Lower 4,200 bopd Jurassic Mus forma
Slide 8: Atrush Phase 1 production facilities
Atrush Phase 1 production facilities Modular concept with provisions to expand and replicate. Capable of handling liquid rates of 30,000 bopd, initially Maximize gas utilization. Minimize sour gas flaring with provisions for future sulphur recovery, power generation, etc. ShaMaran – A Lundin Gro
Slide 9: Project Status – Process area
Project Status – Process area Most equipment installed Flare installed ShaMaran – A Lundin Group Company 9
Slide 10: Project Status – Piping
Project Status – Piping All pipe racks have been installed Pipe installation ongoing ShaMaran – A Lundin Group Company 10
Slide 11: Project Status – Electrical and instrumentation
Project Status – Electrical and instrumentation Instrument cable pulling ongoing Central control room ShaMaran – A Lundin Group Company 11
Slide 12: Atrush export
Atrush export Feeder pipeline Kurdistan Export Pipeline Atrush crude to be exported via existing Kurdistan Export Pipeline to Fishkabur and on to Ceyhan in Turkey Sufficient pipeline capacity available to accommodate Atrush production ShaMaran – A Lundin Group Company 12
Slide 13: Positive Development of Kurdistan export
Positive Development of Kurdistan export KRG continues to export via Ceyhan • Established stable market for Kurdistan/Kirkuk blend FOB Ceyhan • KRG exports approx. 600,000 barrels per day according to monthly reports Since September 2015 contractors have been regularly paid for export Reduced
Slide 14: Atrush feeder pipeline
Atrush feeder pipeline Pipeline EPC contract with KAR Group signed on November 1, 2015 to include: • Pumping station • 6 km 10” section from Production facilities to intermediate pigging station (IPPR) • 2 km 12” section from IPPR to Atrush Block boundary Agreement with MNR • KRG to install 31km
Slide 15: Project schedule
Project schedule Four wells drilled and tested. Two wells completed and ready for production All main equipment items procured Most equipment now installed Piping installation ongoing Electrical and instrumentation work ongoing Feeder pipeline installation started Two well completions
Slide 16: Work ongoing to realise full field value
Work ongoing to realise full field value Submitted field development plan update in November 2015 • No commitment to further phases of development • Production data needed • Drill CK-7 to better define centre part of the field and provide additional producer • Potential further delineation drillin
Slide 17: Additional funding
Additional funding Proposed Financing Arrangement to provide additional USD 33 million liquidity in 2016 • USD 17 mln new Super Senior Bond • Underwritten by the Lundin family • Same terms as Existing Bond (11.5% interest, maturity November 2018) • Option to pay future interest payments in cash or
Slide 18: Corporate profile
Corporate profile Share capital SNM share price on TSX.V • Issued and outstanding 1,579,768,534 Market capitalisation • CAD 166M (@ March 11, 2015) Major shareholders • Lundin family trusts 19.1% • Lundin Petroleum 6.6% • Directors/Management 0.3% Trading information • Toronto Stock Exchan
Slide 19: The Lundin Group
The Lundin Group Combined market cap $12 Billion ShaMaran – A Lundin Group Company 19
Slide 20: Key points
Key points Robust Atrush development project progressing World class increased resource base • Gross 2P 85.1 MMBoe • Gross 2C 304 MMboe First oil target mid 2016 • Facilities construction ongoing • Pipeline installation started Further funding proposed Strong Lundin Group support ShaMaran
Slide 21: Cautionary statements
Cautionary statements This document contains statements about expected or anticipated future events and financial results that are forward-looking in nature and, as a result, are subject to certain risks and uncertainties, such as legal and political risk, civil unrest, general economic, market and
ShaMaran Petroleum — Investor Presentation (March 2016) on 6ix