Energy World Corporation Ltd · ASX:EWC

Energy World — Shareholder Meeting (October 2009)

60 slides from Energy World's shareholder meeting presentation, Nov 2, 2009

  1. Slide 1: ASX cover letter releasing AGM presentation

    ENERGY WORLD CORPORATION LTD. 9A Seaforth Crescent Tel. (61 2) 9247 6888 Seaforth, NSW, 2092 Fax (61 2) 9247 6100 2 November 2009 The Listing Manager The Listing Manager Company Announcement Platform Market Information Services Section ASX Limited New Zealand Stock Exchange URL http //www_asxonline

  2. Slide 2: Presentation to Shareholders, Annual General Meeting

    For personal use only ENERGY WORLD CORPORATION Presentation to Shareholders Annual General Meeting 30 October 2009

  3. Slide 3: Disclaimer

    Disclaimer For personal use only • These materials have been prepared by Energy World Corporation Limited (the "Company") solely for information use during this presentation. These materials may not be copied, reproduced, passed on or redistributed, directly or indirectly, to any other person (wheth

  4. Slide 4: 2009 Review

    2009 Review For personal use only — July 2008 – June 2009 will be remembered for the financial crisis resulting in the near collapse of the global financial markets. — Governments forced to step in to support banks and major industries. — The decline of the Australian dollar against the US dollar by

  5. Slide 5: 2009 Review (Con't)

    2009 Review (Con’t) For personal use only — Despite this difficult year EWC has moved forward on all fronts of its business plan and maintained a policy of prudent project and financial management, to ensure a strong cash position until there is a clear indication of future demand and reasonable pri

  6. Slide 6: Introduction - Asia's Appetite for Energy

    Introduction - Asia’s Appetite for Energy For personal use only kWh 0 2000 4000 6000 8000 10000 12000 14000 16000 United States: 13351 Australia: 11193 New Zealand: 8937 Singapore: 8170 Japan: 8072 South Korea: 7391 Germany: 7029 Energy World Corporation has always United Kingdom: 6206 positioned it

  7. Slide 7: Plan for Asia

    Our LNG Plan for Asia For personal use only Targeted LNG Consumption CHINA JAPAN INDONESIA THE PHILIPPINES LNG to ASIA Our Proposed LNG Production PAPUA NEW GUINEA and AUSTRALIA OTHER ASIA 2 MTPA modular LNG currently under 2 MTPA modular LNG currently under development (expansion to 5 MTPA) develop

  8. Slide 8: Our Target

    Our Target For personal use only To become a leader in modular LNG development and a significant supplier of natural gas to Asian markets Pagbilao Hub Terminal 300MW Power Station Sri Lanka 600MW Power Station LNG Hub Sengkang 2-5MTPA LNG Terminal Manila Papua New Guinea 2-5MTPA LNG Terminal and Dee

  9. Slide 9: Clean and Green Energy

    Clean and Green Energy For personal use only • Increasing concern over “global warming” has led to pollution and emission caps, LNG is reduction goals and carbon trading considered to be • Natural gas is a cleaner and more efficient fossil fuel a source of - For an equivalent amount of heat, burning

  10. Slide 10: Development of Modular LNG

    Development of Modular LNG For personal use only EWC developed EWC approached Australia’s first EWC decided LNG liquefaction EWC ordered a FEED domestic LNG plant was the best way to equipment makers Study to design a over 18 years ago supply Asia’s growing asking for their standard modular ½ (Alice

  11. Slide 11: Teaming Up with Industry Leaders on Modular LNG

    Teaming Up with Industry Leaders on Modular LNG For personal use only EWC has brought together distinguished global players and strong partners such as Chart Industries and Chemicals and Siemens to develop an efficient, electric drive modular LNG system that can be used in a variety of locations. EN

  12. Slide 12: Our Standard Modular LNG Landscape

    Our Standard Modular LNG Landscape For personal use only

  13. Slide 13: Benefits of All Electric LNG Trains

    Development of Modular LNG For personal use only Benefits of All Electric LNG Trains Continuous full load operation possible for 5 to 6 years Up to 25 days additional production each year Lower greenhouse gas and noise emissions OPEX, MAINTEX reduction Compressor string independent in size, speed an

  14. Slide 14: Development of Modular LNG

    Development of Modular LNG For personal use only E-LNG allows for a simple, elegant Liquefaction setup with a relatively small footprint. Through innovative design, EWC has downsized typical LNG train sizes – we are moving from the grandfather clock to the pocket watch. By using a standard design, m

  15. Slide 15: Development of Modular LNG

    Development of Modular LNG For personal use only

  16. Slide 16: Development of Modular LNG

    Development of Modular LNG For personal use only

  17. Slide 17: Development of Modular LNG

    Development of Modular LNG For personal use only

  18. Slide 18: Development of Modular LNG

    Development of Modular LNG For personal use only Standard, shop-fabricated liquefaction plants will grow less expensive per ton of capacity, whereas mega-scale projects have leapt in cost from $500 per metric §Supplies of LNG are ton to more than $1,000 per ton. going to grow in the next few years,

  19. Slide 19: LNG Marine Loading Arms

    Development of Modular LNG For personal use only LNG Marine Loading Arms

  20. Slide 20: Development of Modular LNG

    Development of Modular LNG For personal use only EWC has secured a License from GTT – Gaztransport & Technigaz to §Energy agencies use its LNG tank technology for land based membrane tanks are forecasting significant increases in natural gas demand during the next 20 years. §The largest increments i

  21. Slide 21: Development of Modular LNG

    Development of Modular LNG For personal use only

  22. Slide 22: Economic and HSE Benefits of E-LNG

    Development of Modular LNG For personal use only Economic Benefits of E-LNG Operational & HSE Benefits of E-LNG Maximize productivity & asset utilization Adjustable throughput &load distribution Production capacity independent of Motors & compressors are inherently ambient temperature adjustable Thr

  23. Slide 23: Advantages of Our Modular LNG Model

    Advantages of Our Modular LNG Model For personal use only Conventional VS. Our Modular LNG Train Configuration Large-scale LNG facility of 4 MTPA or above Mid-scale LNG facility incorporated in 0.5 MTPA LNG trains Capital cost about US$100-125 million per 0.5 MTPA (excluding Capital cost currently i

  24. Slide 24: Indonesia - Sengkang LNG Project

    Our LNG Projects Indonesia – Sengkang LNG Project For personal use only Electric Motor Compressor Drive Gear South Sulawesi LNG: Box §Site acquired §Major equipment purchased §Shipments commenced

  25. Slide 25: Indonesia - Sengkang LNG Project

    Our LNG Projects Indonesia – Sengkang LNG Project For personal use only Compressor Electric Motor Drive Gear Box

  26. Slide 26: Indonesia - Sengkang LNG Project

    Our LNG Projects Indonesia – Sengkang LNG Project For personal use only Siemens – Factory Acceptance Test (FAT) for Sengkang LNG Direct Control System (DCS)

  27. Slide 27: Indonesia - Sengkang LNG Project

    Our LNG Projects Indonesia – Sengkang LNG Project For personal use only Sengkang 2-5MTPA LNG Terminal CPP LNG Loading Kampung Baru Terminal LNG Plant Site Bongo 01 Walanga 02 Power Plant SENGKANG Power Station For LNG Plants

  28. Slide 28: Our Gas and LNG Projects

    Our Gas and LNG Projects Indonesia – Sengkang Drilling Rig on site Well Workovers and Production Gas Well Drilling, August - October 2009 For personal use only

  29. Slide 29: Our Gas and LNG Projects

    Our Gas and LNG Projects Indonesia – Sengkang Drilling Rig on site Well Workovers and Production Gas Well Drilling, August - October 2009 For personal use only

  30. Slide 30: Sengkang LNG Terminal Site - Access Road and Seafront Filling

    Our LNG Projects Sengkang LNG Terminal Site – Construction of Access Road and Filling of the Seafront Site for the LNG Plant at Keera, South Sulawesi, August - October 2009 For personal use only Outlook to LNG Plant Site Road Construction Access Road Progress

  31. Slide 31: Sengkang LNG Terminal Site - Access Road and Seafront Filling

    Our LNG Projects Sengkang LNG Terminal Site – Construction of Access Road and Filling of the Seafront Site for the LNG Plant at Keera, South Sulawesi, August - October 2009 For personal use only Road and Embankment Around Fish Pond and Along the Coast Line

  32. Slide 32: Sengkang LNG Terminal Site - LNG Storage Tank Location

    Our LNG Projects Sengkang LNG Terminal Site – LNG Storage Tank Location at Keera, South Sulawesi For personal use only

  33. Slide 33: Indonesia Meeting with Vice President Jusuf Kalla

    Indonesia Meeting with His Excellency Vice President Dr. H. Mohammad Jusuf Kalla For personal use only

  34. Slide 34: Indonesia Meeting with Minister of Energy and Mineral Resources

    Indonesia Meeting with H.E. Purnomo Yusgiantoro – Minister of Energy and Mineral Resources, June 2009 For personal use only

  35. Slide 35: Indonesia Meeting with the Governor of South Sulawesi

    Indonesia Meeting with the Governor of South Sulawesi, His Excellency Dr. Syahrul Yasin Limpo For personal use only

  36. Slide 36: Australia - ATP-549P Cuban Drilling Project

    Our LNG Projects Australia – ATP-549P Cuban 1 Drilling Project For personal use only Cultural Heritage Team On Site Rig Site – Erection of Drill Mast 16th March 2009 Rig Site - Connection of Water Pump Rig Site - Halliburton Pump Truck & Bulk Cement Tanker of Cementing

  37. Slide 37: Australia - Abbot Point LNG Project

    Our LNG Projects Australia – Abbot Point LNG Project For personal use only Australia Unlocking Queensland Gas Assets Queensland • Port of Abbot Point Location • Existing deep-water coal export terminal Community • An opportunity for many smaller gas exploration companies in Opportunity Queensland to

  38. Slide 38: Australia - Queensland Gas Highway

    Our LNG Projects Australia – Queensland Gas Highway For personal use only

  39. Slide 39: Our Projects - Pipelines - Diversified Construction Corporation

    Our Projects – Pipelines – Diversified Construction Corporation For personal use only

  40. Slide 40: Our Proposed LNG Plant and Power Station

    Our Proposed LNG Plant and Power Station For personal use only Abbot Point Proposed LNG Plant & Power Station: Proposed §Initial capacity 2 MTPA LNG Jetty Water Depth 13 M+ §Future expansion to 5 MTPA §Gas supply from EWC owned and operated gas fields via the Qld Gas Highway Proposed LNG Plant Propo

  41. Slide 41: Abbot Point: Developing The Northern Triangle

    Our LNG Projects Australia – Abbot Point: “Developing The Northern Triangle” For personal use only Northern Economic Triangle Vision To foster sustainable economic, social and community development and growth through the emergence of Mount Isa, Townsville and Bowen as a triangle of mineral processin

  42. Slide 42: Australia - Other Gas and Oil Interests

    Australia – Other Gas and Oil Interests Southern Cooper Project (PEL 96) For personal use only PEL 96 (Block K) Percentage • 33.3% Interest of EWC Gas / Oil • Gas potential of 8 – 20 TCF Operating • Strike Oil Limited Party EWC portion 2.50 - 6.50 TCF Production • PEL obtained 13 May 2009 Status Fut

  43. Slide 43: Papua New Guinea - Gulf Province LNG Project

    Our LNG Projects Papua New Guinea – Gulf Province LNG Project – Signing Agreement In Conjunction with Energy World International Limited (EWI) For personal use only Gulf Province Developments: • Natural gas supply pipeline • 2 - 5 MTPA LNG production facility • LNG Terminal will be developed in conj

  44. Slide 44: Papua New Guinea - Development Projects in Gulf Province

    Our LNG Projects Papua New Guinea – Development Projects in Gulf Province For personal use only EWC - Proposal LNG Terminal EWI - Deep Water Port EWI - Petroleum Refinery EWI - Power Station

  45. Slide 45: Papua New Guinea - Western Province LNG Project

    Our LNG Projects Papua New Guinea – Western Province LNG Project Energy World International Limited (EWI) For personal use only Parama Island LNG: • Initial capacity 2 MTPA • Future expansion to 5 MTPA • LNG Terminal will be developed in conjunction with a deep water port and power station.

  46. Slide 46: The Philippines - LNG Hub Terminal and Power Station

    Our LNG Projects The Philippines – LNG Hub Terminal and Power Station For personal use only

  47. Slide 47: The Philippines - LNG Hub Terminal and Power Station

    Our LNG Projects The Philippines – LNG Hub Terminal and Power Station For personal use only The Philippines Pagbilao Grande Island, Quezon Province Philippines LNG Terminal Sengkang LNG Project 1,100 nautical Strategic Location miles Regional Play • Located between key developing markets in coastal

  48. Slide 48: The Philippines - LNG Hub Terminal and Power Station

    Our LNG Projects The Philippines - LNG Hub Terminal and Power Station For personal use only Philippines Hub LNG Terminal The ground breaking ceremony for the LNG Hub Terminal and 300MW gas fired power plant was held on the site of Pagbilao Grande Island in Quezon Province on 28 August 2009. The cere

  49. Slide 49: Quezon Province Developments

    QUEZON PROVINCE DEVELOPMENTS For personal use only HON. HON. RAFFY P. P. NANTES GOVERNOR QUEZON PROVINCE DELIVERING CLEAN HOTEL AND RESORT ENERGY FOR QUEZON LNG CARRIER VESSEL 300MW 300MW GAS FIRED FERRY PASSENGER POWER STATION TERMINAL ENERGY WORLD GROUP

  50. Slide 50: Ground Breaking Ceremony 28 August 2009

    Our LNG Projects The Philippines - LNG Hub Terminal and Power Station Ground Breaking Ceremony 28 August 2009 For personal use only

  51. Slide 51: The Philippines - LNG Hub Terminal Site Preparation

    Our LNG Projects The Philippines - LNG Hub Terminal Site Preparation For personal use only

  52. Slide 52: The Philippines - LNG Hub Terminal and Power Station

    Our LNG Projects The Philippines - LNG Hub Terminal and Power Station For personal use only Pictured Left to Right. Former Governor of Quezon Province Eduardo Rodriguez, current Governer of Quezon Province Rafael Nantes, the Secretary for Energy, The Hon. Angelo Reyes, the undersecretary for Energy

  53. Slide 53: Sri Lanka - Hambantota LNG Hub

    Our LNG Projects Sri Lanka – Hambantota LNG Hub For personal use only Hambantota LNG Hub: • This terminal will act as a hub for onward distribution of LNG throughout Sri Lanka • EWC will develop a CCGT power station at this site • Substantial development of this port is already underway

  54. Slide 54: Development of Floating Modular LNG

    Development of Floating Modular LNG For personal use only LNG Storage Ship

  55. Slide 55: Ship Solution for Floating LNG

    3 Ship Solution for Floating LNG For personal use only Based on the standard EWC LNG ship – EWC developed 3 ship solution for Floating LNG. LNG Support Ship - Gas pretreatment and power generation is located on the first ship. LNG Liquefaction Ship - Liquefaction (2 x 500,000 TPA) trains the standar

  56. Slide 56: Development of Floating Modular LNG

    Development of Floating Modular LNG For personal use only LNG Liquefaction Ship 2 x 500,000 TPA

  57. Slide 57: Benefits of the Ship Floating Modular LNG

    Benefits of the 3 Ship Floating Modular LNG For personal use only ü This is a buildable solution based around well developed technology ü Smaller ships with shallower draft allow for greater flexibility in location ü In the event of bad weather, all 3 ships can be moved to a safe harbour ü Insurance

  58. Slide 58: Key Attributes of Our Company

    Key Attributes of Our Company For personal use only Ownership of Strategic Gas and Power Resources in Strategic Locations 1 Market Leading Position to Exploit Stranded Gas Fields Using Modular LNG Train 2 Configuration 3 Committed LNG Project to be Commissioned from 2010 4 Stable Revenue Stream from

  59. Slide 59: LNG to the Asian Market

    LNG to the Asian Market For personal use only

  60. Slide 60: Thank You!

    For personal use only Thank You! 20 Oct 2009