Chavda Infra Limited · NSE:CHAVDA

Chavda Infra — Q2 FY27 Earnings Presentation

53 slides from Chavda Infra's earnings presentation, Nov 6, 2026

  1. Slide 1: NSE filing cover letter for investor presentation

    November 6, 2026 National Stock Exchange of India Ltd. Listing Department, Exchange Plaza, Plot No. C-1, Block G, Bandra Kurla Complex, Bandra(E) Mumbai – 400051, Symbol: CHAVDA Dear Sir/Madam, Subject: Investor Presentation of the Unaudited Financial Results for the Quarter and Half Year ended Sept

  2. Slide 2: Investor Presentation – Q2 FY27 Earnings Update

    CHAVDA INFRA LIMITED Investor Presentation – Q2 FY27 Earnings Update The 31st 1

  3. Slide 3: Agenda

    Agenda 1. Executive 1. summary Executive Summary 2. About Chavda Infra limited 3. Competitive Moats 4. Ongoing & Completed Projects 5. Investment Rationale 6. Historical Business Performance 7. Select Financial Statement Data 8. Annexures Nirma University Old Building

  4. Slide 4: Executive Summary – Q2 FY27

    Executive Summary – Q2 FY27 Revenue & Profitability Return & Capital Client & People Revenue From Operations Return On Equity Orderbook ₹ 89.4 crores ^ 55.8% 7.9% vs 7.7% in ₹ 892.3 crores ^ 2.4% FY26 EBITDA Return On Capital Employed Order Inflow ₹ 14.4 crores v 14.2% 10.9% vs 11.5% in ₹ 144 crores

  5. Slide 5: Performance Update & Management Commentary – Q2 FY27

    Performance Update & Management Commentary – Q2 FY27 Business Updates ▪ Received a ₹54.72 crore work order from Weisdom Design Build LLP for the construction of a residential-cum-commercial building, including a five-star hotel, at Kudasan, Gandhinagar, with execution scheduled over 24 months. ▪ Str

  6. Slide 6: Strong Operational Growth With Stable Profitability

    Strong Operational Growth With Stable Profitability (₹ Crores) Revenue From Operations EBITDA PAT CAGR: 26% CAGR: 29% CAGR: 12% 321 21 58 19 56 261 17 242 43 12 162 27 FY23 FY24 FY25 FY26 FY23 FY24 FY25 FY26 FY23 FY24 FY25 FY26 View our business in blocks of 4 years. Aim to double our business and k

  7. Slide 7: Agenda

    Agenda 1. Executive Summary 2. About Chavda Infra limited 3. Competitive Moats 4. Ongoing & Completed Projects 5. Investment Rationale 6. Historical Business Performance 7. Select Financial Statement Data 8. Annexures Trogon Twin Towers

  8. Slide 8: About Chavda Infra Limited

    About Chavda Infra Limited About The Company ▪ Founded in 1990 by Mr. Mahesh Chavda, Chavda Infra Limited is a 4-YEAR CAGR(FY22-FY26) construction and allied services provider ▪ Headquartered in Ahmedabad, Gujarat, the company services India’s leading real estate developers and corporates Revenue Fr

  9. Slide 9: Our Journey: Transitioning From Repair Works Contractor To EPC Player

    Our Journey : Transitioning From A Repair Works Contractor To A Leading EPC Player ▪ Started with private bungalows and first-floor additions; quickly advanced to large-scale society projects ▪ Evolved into a mid-size EPC player in 2010, driven by inbound projects from leading architects and develop

  10. Slide 10: Providing Construction Services Across Multiple Business Verticals

    Providing Construction Services Across Multiple Business Verticals Residential projects Commercial projects Institutional projects1 Development of private residential buildings Construction of commercial and industrial Construction of hospitals, healthcare facilities, including group housing, townsh

  11. Slide 11: Worked With More Than 75+ Clients Across Gujarat

    Worked With More Than 75+ Clients Across Gujarat GANDHINAGAR AHEMDABAD RAJKOT 10

  12. Slide 12: Top-Tier Projects From Key Clients

    Top-Tier Projects From Key Clients Outstanding Contract Value of Key projects as of Q2 FY27 = ₹ 633+ crores 143 138 109 80 50 44 37 31 Project Name The Indentity Arvind Smartspaces A Shridhar ADI Shantigram Nirma Limited Kalrav Nest Trogon Ample & Ampleton Abode Llp Rashmi Kalyangadh A Shridhar Rain

  13. Slide 13: Leadership Team

    Leadership Team Mr. Mahesh Chavda Mr. Johil Chavda Mr. Jeet Chavda Mr. Parth Gurjar Mr. Gopal Rami (MD & Chairman) Director Promoter Group CEO Chief Financial Officer Industry experience: 40+ years Industry experience: 12+ years Industry experience: 12+ years Industry experience: 20+ years Industry

  14. Slide 14: Construction Project Life Cycle At Chavda

    Construction Project Life Cycle At Chavda Sourcing And Evaluation Planning And Mobilization Material Procurement Handover Retention Money Release Secure projects from private sector clients, Mobilize manpower and equipment and Procure high-quality materials and monitor Jointly inspect project with c

  15. Slide 15: Agenda

    Agenda 1. Executive Summary 2. About Chavda Infra Limited 3. Competitive Moats 4. Ongoing & Completed Projects 5. Investment Rationale 6. Historical Business Performance 7. Select Financial Statement Data 8. Annexures Mondeal One 14

  16. Slide 16: Key Drivers Behind Chavda's Growth Since Inception

    Key Drivers Behind Chavda’s Growth Since Inception Repeatedly Serviced India’s Leading Developers One-Stop-Shop EPC Player And Corporates Transforming Ahmedabad’s Real Estate Industry Value-Accretive Payment Terms With Global Leading Technology Creating An Ecosystem To Deliver Holistic Internal Tale

  17. Slide 17: One-Stop-Shop EPC Player

    One-Stop-Shop EPC Player One stop solution Client Technology ▪ Transitioned from repairs work ▪ End-to-end execution capabilities ▪ Positioned ourselves as a leading ▪ Well diversified experience of contractor to a leading EPC coupled with in-house resources EPC service provider, as constructing tow

  18. Slide 18: Repeatedly Serviced India's Leading Developers & Corporates

    Repeatedly Serviced India’s Leading Developers & Corporates One stop solution Received inbound business from top architectures, developers, and corporates due to our work-ethic, construction quality, ethos, and faster project turnaround Client Technology 7 6 6 4 4 4 2 2 2 Ecosystem Shivalik Group A

  19. Slide 19: Value-Accretive Payment Terms

    Value-Accretive Payment Terms One stop solution Invoice raised after slab is casted, ensuring steady Milestone-based Payment cash conversion Client Pass-Through Clause Mitigate fluctuating commodity prices Technology Flexible Payment Terms Limiting downside execution risk Ecosystem ~3% of project re

  20. Slide 20: Transforming Ahmedabad's Real Estate Market With Global Leading Technology

    Transforming Ahmedabad’s Real Estate Market With Global Leading Technology One stop solution Client Technology Ecosystem Equipment name : Aluminum Monolithic Formwork Equipment name : Peri Up MI System for Beam Bottom Equipment name : Peri Handset Alpha Country of origin : Malaysia Country of origin

  21. Slide 21: Deploying Our Logistics Fleet To Efficiently Mobilize Resources

    Deploying Our Logistics Fleet To Efficiently Mobilize Resources One stop solution Client Technology Ecosystem Number Of Mixers : 18 Number Concrete Pump : 7 Number Of Jcbs : 3 Number Of Boom Placer : 1 People Number Of Static Boom : 4 Number Of Transport Vehicle : 5 Number Of Loader : 4 Passenger &

  22. Slide 22: Leverage Refurbishing Yard To Enhance Margins (1/2)

    Leverage Refurbishing Yard To Enhance Margins (1/2) One stop solution Client Technology Ecosystem People Increase Life Of Construction Materials Through Our State-Of-The-Art Refurbishing Yard 21

  23. Slide 23: Leverage Refurbishing Yard To Enhance Margins (2/2)

    Leverage Refurbishing Yard To Enhance Margins (2/2) One stop solution Client Technology Ecosystem People Balance use of new and refurbished material without compromising on quality, thereby enhancing margins 22

  24. Slide 24: Internal Talent & Long-term Leadership: Our Execution Backbone

    Internal Talent & Long-term Leadership: Our Execution Backbone One stop solution Client ▪ Believe in promoting internal ▪ Senior management team has talent over hiring senior been with the company for external candidates, resulting over 25 years in low attrition Technology Ecosystem ▪ Professional o

  25. Slide 25: Our Focus On Manpower Safety

    Our Focus On Manpower Safety One stop solution Client Technology ▪ Reported zero casualties in FY26 reflecting our commitment to strict safety protocols ▪ All our employees, including workers, are covered by robust insurance policies Ecosystem ▪ Enable advanced safety system like EPS (Edge Protectin

  26. Slide 26: Agenda

    Agenda 1. Executive Summary 2. About Chavda Infra Limited 3. Competitive Moats 4. Ongoing & Completed Projects 5. Investment Rationale 6. Historical Business Performance 7. Select Financial Statement Data 8. Annexures The Park 25

  27. Slide 27: Our Ongoing High-Rise Projects (1/3)

    Transforming Ahmedabad’s Skyline With Our Ongoing High-Rise Projects (1/3) The Identity Trogon Twin Towers Nirma Corporate House Height : 119.8 meters Height : 125.8 meters Height : 145.0 meters Order Value : ₹219.0 crores Order Value : ₹147.0 crores Order Value : ₹72.0 crores 26

  28. Slide 28: Our Ongoing High-Rise Projects (2/3)

    Transforming Ahmedabad’s Skyline With Our Ongoing High-Rise Projects (2/3) The Park WYNN Anantara Alora Height : 123.0 meters Height : 152.0 meters Height : 72.4 meters Order Value : ₹30.0 crores Order Value : ₹131.0 crores Order Value : ₹33.7 crores 27

  29. Slide 29: Our Ongoing High-Rise Projects (3/3)

    Transforming Ahmedabad’s Skyline With Our Ongoing High-Rise Projects (3/3) Centroid La Marque Anantara Imperial Height : 74.0 meters Height : 124.8 meters Height : 74.9 meters Order Value : ₹22.9 crores Order Value : ₹21.6 crores Order Value : ₹13.4 crores 28

  30. Slide 30: Other Ongoing High-value Projects

    Other Ongoing High-value Projects Kalrav Nest Nirma Hostel H5 Arvind Aqua City Order Value : ₹125.0 crores Order Value : ₹57.3 crores Order Value : ₹150.0 crores 29

  31. Slide 31: Completed Landmark Projects (1/5)

    Completed Landmark Projects (1/5) Amara Zaveri Solitaire Sky Straft Luxuria Developer name : Zaveri Realty Developer name : Kraft Infrastructures Developer name : Straft 30

  32. Slide 32: Completed Landmark Projects (2/5)

    Completed Landmark Projects (2/5) Solitaire Connect Binori B Square 3 Manor Greenz Developer name : ARK Infra Developer name : Binori Group Developer name : Winsome Realty 31

  33. Slide 33: Completed Landmark Projects (3/5)

    Completed Landmark Projects (3/5) Apurva Amin Corporate House Nirma University – Old Building Shivalik Sharda Harmony Client name : Apurva Amin Architects Client name : Nirma Developer name : Shivalik 32

  34. Slide 34: Completed Landmark Projects (4/5)

    Completed Landmark Projects (4/5) Avani Aayam Abhishek Rajshree Regalia Developer name : Dev Shree Developer name : Chavda Developers Developer name : Rajshree Developers Proinfra

  35. Slide 35: Completed Landmark Projects (5/5)

    Completed Landmark Projects (5/5) Mondeal One Rajul Greens The 31st Developer name : HN Safal Infra Developer name : Lilamani Group Developer name : Beverly Buildcon Developers

  36. Slide 36: Agenda

    Agenda 1. Executive Summary 2. About Chavda Infra Limited 3. Competitive Moats 4. Ongoing & Completed Projects 5. Investment Rationale 6. Historical Business Performance 7. Select Financial Statement Data 8. Annexures Kalrav Nest 35

  37. Slide 37: Investment Rationale: Chavda Infra Limited

    Investment Rationale: Chavda Infra Limited Capitalizing On Gujarat's Laser Sharp Focus On Private Prudent Expansion Enhance Execution Growth Momentum Sector Projects Strategy Capabilities ▪ Leverage our operational ▪ Preferred contractors of India’s ▪ Not focused solely on order ▪ Continue to improv

  38. Slide 38: Agenda

    Agenda 1. Executive Summary 2. About Chavda Infra Limited 3. Competitive Moats 4. Ongoing & Completed Projects 5. Investment Rationale 6. Historical Business Performance 7. Select Financial Statement Data 8. Annexures Nirma Corporate House 37

  39. Slide 39: Historic Business Performance (1/2) – H1 FY27

    Historic Business Performance (1/2) – H1 FY27 Revenue From Operations (₹ Cr) EBITDA (₹ Cr) PAT (₹ Cr) 320.6 56.0 58.0 20.7 241.7 261.0 18.8 17.0 42.9 173.4 25.8 9.0 FY24 FY25 FY26 H1 FY27 FY24 FY25 FY26 H1 FY27 FY24 FY25 FY26 H1 FY27 Total Workforce (No.) EBITDA Margin (%) PAT Margin (%) 318 21.6% 7

  40. Slide 40: Historic Business Performance (2/2) – H1 FY27

    Historic Business Performance (2/2) – H1 FY27 Debtor Days Inventory Days Payable Days 134 162 164 125 240 100 101 102 157 159 137 70 FY24 FY25 FY26 H1 FY27 FY24 FY25 FY26 H1 FY27 FY24 FY25 FY26 H1 FY27 Cash Conversion Days Working Capital Days Net Debt To Equity (In Times) 180 152 135 1.4 148 136 12

  41. Slide 41: Historic Business Performance – Q2 & H1 FY27

    Historic Business Performance – Q2 & H1 FY27 Return On Equity (ROE)1 Return On Capital Employed (ROCE)1 Completed Projects (No.) 20.3% 29.8% 8 18.8% 5 5 14.1% 11.5% 7.7% 7.9% 10.9% 1 FY24 FY25 FY26 H1 FY27 FY24 FY25 FY26 H1 FY27 FY24 FY25 FY26 Q2 FY27 Orderbook (₹ Cr) Order Inflow (₹ Cr) Orderbook T

  42. Slide 42: Historic Business Performance – Q2 FY27

    Historic Business Performance – Q2 FY27 Revenue From Operations (₹ Cr) EBITDA (₹ Cr) PAT (₹ Cr) 320.6 56.0 58.0 20.7 241.7 261.0 18.8 17.0 42.9 89.4 14.4 5.1 FY24 FY25 FY26 Q2 FY27 FY24 FY25 FY26 Q2 FY27 FY24 FY25 FY26 Q2 FY27 Total Workforce (No.) EBITDA Margin (%) PAT Margin (%) 318 21.6% 7.8% 8.1

  43. Slide 43: Agenda

    Agenda 1. Executive Summary 2. About Chavda Infra Limited 3. Competitive Moats 4. Ongoing & Completed Projects 5. Investment Rationale 6. Historical Business Performance 7. Select Financial Statement Data 8. Annexures Be Free 42

  44. Slide 44: Income Statement

    Income Statement ₹ Crores Unless Otherwise Mentioned Particulars Q2 FY27 Q2 FY26 YoY change H1 FY27 H1 FY26 YoY change Revenue from operations 89.4 57.3 55.8% 173.4 103.7 67.1% Cost of materials consumed including finished goods and WIP -13.3 -6.7 99.2% -13.4 -17.9 -25.4% Construction expenses 79.6

  45. Slide 45: Balance Sheet

    Balance Sheet ₹ Crores Unless Otherwise Mentioned Assets H1 FY27 FY26 FY25 Property, plant & equipment 115.6 110.3 74.2 Net deferred tax asset 1.9 2.6 2.3 Other non-current assets 1.6 1.9 3.2 Inventories 111.3 98.0 74.3 Trade receivables 107.4 117.7 89.4 Cash and bank balance 9.7 10.6 8.9 Short-term

  46. Slide 46: Cashflow Statement

    Cashflow Statement ₹ Crores Unless Otherwise Mentioned Particulars H1 FY27 FY26 FY25 Profit / (Loss) before tax 12.6 24.3 28.4 Depreciation 5.7 16.7 17.9 Other adjustments 7.6 16.4 10.6 Inventories -13.4 -23.7 -0.2 Trade receivables 7.1 -77.1 -96.9 Trade payables -28.2 45.3 5.6 Income tax expense -3

  47. Slide 47: Agenda

    Agenda 1. Executive Summary 2. About Chavda Infra Limited 3. Competitive Moats 4. Ongoing & Completed Projects 5. Investment Rationale 6. Historical Business Performance 7. Select Financial Statement Data 8. Annexures Anantara Alora 46

  48. Slide 48: Key Drivers Behind Ahmedabad's Spatial Growth

    Key Drivers Behind Ahmedabad’s Spatial Growth 2000 2010 2015 2020 Structural Drivers Influencing Ahmedabad’s Urban Spread City’s Existing Infrastructure Migration & Planned Urban Population Growth Development International 1,517 km 2,380 km 40.03 km Airport Sardar Vallabhbhai Length of railway Lengt

  49. Slide 49: Ahmedabad's Residential Real Estate Market

    Ahmedabad’s Residential Real Estate Market 50, 000 Supply, Absorption & Inventory Trends 55 45,385 42,313 45, 000 40,016 45 40, 000 46 36,515 37,417 34,122 31,445 35, 000 29,827 35 29,008 26,887 30, 000 25, 000 28 22,850 25 20, 000 23 17,192 22 17,360 20 15, 000 18 13,812 17 15 10, 000 5 5,0 00 0 -5

  50. Slide 50: Can Ahmedabad Become The Next Hyderabad?

    Can Ahmedabad Become The Next Hyderabad? Planned Infrastructure Unlocking Policy Push Transformed Hyderabad’s Real Estate Industry Ahmedabad’s Potential ▪ Government gave policy support to place it as an IT hub by promoting IT institutes, Hi-Tech city, software technology park and establishing a fin

  51. Slide 51: About Chavda Group

    About Chavda group Lead the construction industry by exemplifying excellence, integrity, and innovation Our mission extends beyond construction to creating and uplifting communities. We in every project we undertake. By adapting cutting-edge technologies and practices, are dedicated to reaching new

  52. Slide 52: Safe Harbor Statement

    Safe Harbor Statement This presentation is for information purposes only and does not constitute an offer or invitation to sell or the solicitation of an offer or invitation to purchase any securities (“Securities”) of Chavda Infra Limited (“Chavda” or the “Company”) in India or any other jurisdicti

  53. Slide 53: For Any Further Information/Queries, Please Contact

    For Any Further Information/Queries, Please Contact: Company Investor Relations Consultant Chavda Infra Limited Capital Bridge Advisory Service Private Ltd Mr. Gopal Rami Raj Shah, CFA Hrishit Jhaveri, CFA Chief Financial Officer raj@capbridge.in hrishit@capbridge.in compliance@chavdainfra.com +91 9

Chavda Infra — Q2 FY27 Earnings Presentation on 6ix