Perpetua Resources Corp. · TSX:PPTA

Perpetua Resources — Technical Presentation (May 2021)

48 slides from Perpetua Resources's technical presentation, May 2021

  1. Slide 1: SGP: Tailings Storage Facility

    S G P : TA I L I N G S S T O R A G E FA CI L I T Y May 2021 TSX :P P TA N A SDA Q:P P TA PERPETUA RESOURCES C r i t i c a l R e s o u r c e s . R e s p o n s i b l e M i n i n g . E n v i r o n m e n t a l R e s t o ra t i o n . www.perpetuaresou rc e s.c om

  2. Slide 2: Presentation Outline

    PRESENTATION OUTLINE 1. Stibnite Gold Project site overview. 2. What are tailings, and what does “managing” them mean? 3. How do we understand and manage a tailings facility throughout its lifecycle? 4. Stibnite Gold Project tailings storage facility (TSF) design.

  3. Slide 3: Stibnite Gold Project

    STIBNITE GOLD PROJECT Coeur d’Alene Stibnite Gold Project Perpetua Resources Au-Sb 3

  4. Slide 4: Historical Stibnite Mining District

    1890s The Thunder Mountain gold rush brings mining to the area 1900-1930 The town of Stibnite is established HISTORICAL STIBNITE 1938 Mining at Yellow Pine pit stops salmon migration upstream 1941-1950 The town of Stibnite booms when antimony & tungsten were declared critical & strategic minerals MI

  5. Slide 5: Legacy Environmental Impacts

    YELLOW PINE PIT HISTORICAL The East Fork of the South Fork dumps into a legacy mine pit. Currently, ~80 feet of sediment has collected at the bottom LEGACY FISH PASSAGE Fish migration After 100+ years of mining activity, many environmental legacies remain. is blocked by the Yellow TAILINGS & SPENT O

  6. Slide 6: Tailings Risk Management Introduction

    TAILINGS RISK MANAGEMENT INTRODUCTION 6

  7. Slide 7: Tailings Lifecycle

    TAILINGS LIFECYCLE TAILINGS: the materials left over after separating the valuable fraction from the uneconomic fraction of an SITE ore – typically a mixture of sand- and silt-size rock TEAM CHARACTERISTICS particles and water. Four areas comprise the lifecycle management of a LIFECYCLE Tailings Sto

  8. Slide 8: Risk Minimization

    RISK MINIMIZATION Goal of Tailings Management Team = minimize catastrophic and chronic risk No “one size fits all” in tailings management. The mining industry operates lots of different types of safe tailings storage facilities (TSFs).

  9. Slide 9: Design Types: Methods of Storing Tailings

    DESIGN TYPES Other methods include: DISCHARGED TO STREAM / RIVER / OCEAN Methods of Storing Tailings Vary RETENTION BY EMBANKMENT STORAGE IN A LAKE Most common, and proposed for SGP IN-PIT STORAGE SGP: Stibnite Gold Project

  10. Slide 10: Design Types: Liners

    DESIGN TYPES Liners Can Help Protect the Environment FULLY SYNTHETICALLY LINED Tailings characteristics: toxic versus non-toxic Lining types: composite, soil, none NO LINING

  11. Slide 11: Design Types: Climate and Topography

    DESIGN TYPES Consider Climate and Topography MINIMAL CATCHMENT, PADDOCK CONFIGURATION, COLD / WET CLIMATE LARGE CATCHMENT, VALLEY CONFIGURATION, COLD / DRY CLIMATE

  12. Slide 12: Team and Project Execution

    TEAM AND PROJECT EXECUTION 12

  13. Slide 13: Teams Matter

    TEAMS MATTER ✓ Internal management team: experienced versus inexperienced ✓ External design team: experienced versus STIBNITE GOLD PROJECT TEAM inexperienced • Experienced internal, external, and 3 rd party ✓ Regulatory environment: experienced and review teams comprehensive versus inexperienced and

  14. Slide 14: Construction & Ops Management

    CONSTRUCTION & OPS MANAGEMENT Promote Best Practices and Reduce Risk ✓ Construction execution: owner built versus specialty contractor ✓ Construction management: none versus third-party experienced ✓ Instrumentation, surveys, and monitoring: none, rudimentary, extensive ✓ Reviews and audits: none ve

  15. Slide 15: Site Characteristics and Design Considerations

    SITE CHARACTERISTICS and DESIGN CONSIDERATIONS 15

  16. Slide 16: TSF Configuration Considerations

    TSF CONFIGURATION CONSIDERATIONS Key Aspects of Facility Design and Construction ✓ Embankment/containment type: downstream, upstream, centerline, no embankment ✓ Geotechnical design criteria: foundation conditions, static/dynamic analyses and factors of safety ✓ Embankment design: filter compatibili

  17. Slide 17: Location Considerations

    LOCATION CONSIDERATIONS Identifying the Best Location • Finite number of alternatives to store tailings at a given site • Process involves iterating between pit sizes, infrastructure layouts, and development rock storage facility locations • Many considerations involved in establishing the preferred

  18. Slide 18: Tailings Storage Site

    TAILINGS STORAGE SITE Selected TSF Site: • Readily buttressed for stability • Lowest elevation • 2nd least impact on fish access • 2nd smallest embankment • Most prior disturbance • Half the stream disturbance of 2 nd place contender • Reprocess/reuse legacy waste Buttress TSF Site 45% of proposed p

  19. Slide 19: Legacy Spent Ore Mitigation

    LEGACY SPENT ORE MITIGATION DISPOSAL AREA Older tailings (beige) were covered with spent heap (1980s) leach ore (brown) after being deposited, unlined, in the Meadow Creek valley. TODAY Revegetation attempts have been made; however, legacy materials continue to degrade water quality and leach metals

  20. Slide 20: Site Characteristics: Geology and Soil Types

    SITE CHARACTERISTICS Geology and Soil Types Inform Design Foundation geotechnical characteristics: dense/competent/uniform versus loose/liquefiable/nonuniform Construction material availability: abundant broad range of construction materials versus high degree of effort needed to manufacture materia

  21. Slide 21: Site Characteristics: Well-studied Soils and Geology

    SITE CHARACTERISTICS Well-studied Soils and Geology Glacial, fluvial, talus + mostly granitic rock → variety of competent construction materials, modest processing 99 holes, 8 years, 3 drilling methods + lab and modeling work → well understood foundations for TSF/Buttress

  22. Slide 22: Site Characteristics: Seismicity and Geohazards

    SITE CHARACTERISTICS Seismicity and Geohazards Recent Idaho quake was ~1/6th the strength of SGP TSF embankment design event. SGP site-specific study update in progress; no design changes anticipated. Seismicity: high seismicity and poorly understood versus low seismicity and well understood Topogra

  23. Slide 23: Site Characteristics

    SITE CHARACTERISTICS Climate: wet/dry, cold/hot, windy/calm Hydrology: large catchment versus paddock Hydrogeology: depth to groundwater, flow patterns Vegetation, wetlands, soils, streams, seeps STIBNITE • Seasonally wet; cold snowy winters/dry summers • Potential TSF site catchments a few square m

  24. Slide 24: Water Recovery and Management Elements

    At Stibnite DESIGN TYPES Need all listed elements Water Recovery and Management Elements Water supply, recycled water (reclaim) recovery, underdrains, stream diversions Water recovery (reclaim) is a key operational practice, potentially implemented several ways

  25. Slide 25: Water Balance and Sizing

    DESIGN CONSIDERATIONS Water Balance and Sizing of Water Management Elements • Hydrologic avg. recurrence intervals for diversions/spillways • Store vs. pass storms • Water supply and disposal of excess • Pool volume and freeboard confirmation

  26. Slide 26: Design Considerations: Tailings Characteristics

    DESIGN CONSIDERATIONS Tailings Characteristics Tailings physical and chemical characteristics: coarse, rapidly consolidating, benign versus fine, poorly consolidating, high toxicity

  27. Slide 27: Design Considerations: Consolidation

    DESIGN CONSIDERATIONS Tailings Characteristics Consolidation Tailings settle after deposition, increasing in density and strength and expelling water. Some factors affecting consolidation: • Grind (gradation) • Rise rate • Dewatering method • Pool management and additives • Drainage condition • Tran

  28. Slide 28: Slurry Dewatering and Tailings Deposition Method

    DESIGN TYPES THICKENED Slurry Dewatering and Tailings Deposition Method CONVENTIONAL LOW-DENSITY TAILINGS FILTERED “DRY STACK” PASTE

  29. Slide 29: Stibnite Tailings Consolidation

    STIBNITE TAILINGS CONSOLIDATION ✓ Tested pilot tailings with SICT ✓ Analyzed with SICTA; modeled in both FS Consol and CONDES (steady-state normal consolidation) ✓ Design curve from average of representative LOM tailings, assuming impervious base (i.e., no drainage/wicking – conservative for capacit

  30. Slide 30: Stibnite Tailings Characteristics – A Manageable Risk

    STIBNITE Tailings Characteristics – A Manageable Risk Physical: • Approx. 120 million tons over 14.25-year mill life • Grind to P80 ~85 microns / ranging from fine sand through minimal clay • 85-90% flotation tailings, 10-15% pressure oxidation (POX) tailings • Grind + bulk are from flotation + lime

  31. Slide 31: Typical Water Balance Analysis Results

    DESIGN CONSIDERATIONS Typical Water Balance Analysis Results • Pool volume • Makeup water requirements • Excess water disposal • Schedule (in)sensitivity to consolidation performance

  32. Slide 32: Geotechnical Factor of Safety (FOS)

    TSF CONFIGURATION CONSIDERATIONS Geotechnical Factor of Safety (FOS) FOS = Ratio of design strength to stresses placed on a structure = Ratio of stabilizing forces to destabilizing forces. Evaluated for a variety of potential failure locations/directions and loading conditions Stabilizing: Destabili

  33. Slide 33: Geotechnical Factor of Safety: Chair Example

    TSF CONFIGURATION CONSIDERATIONS Geotechnical Factor of Safety (FOS) FOS = Ratio of design strength to stresses placed on a structure. Simpler approach – building a chair. Stabilizing / Strength: Destabilizing / Stress: • Strength of wooden legs (4? 2?) • Self-weight of chair (ignore for now) • Stre

  34. Slide 34: Closure Considerations

    DESIGN CONSIDERATIONS Closure Considerations ✓ Proactive/walk-away versus reactive/active long-term management ✓ Can evolve in sequence/phases

  35. Slide 35: Stibnite TSF Design

    STIBNITE TSF DESIGN 35

  36. Slide 36: SGP Tailings Facility Design Goes Beyond Idaho State Standards

    SGP TAILINGS FACILITY DESIGN Goes Beyond Idaho State Standards Driven by 4 State Rules, and meets or exceeds many others: STABILITY: 1. Cyanidation (IDEQ) – Static FOS > 1.5 [standalone – unbuttressed] 2. Dam Safety (IDWR) 3. Tailings Impoundments (IDWR) – Pseudostatic (seismic) FOS > 1.0 [standalon

  37. Slide 37: SGP TSF Design in Context

    SGP TSF DESIGN IN CONTEXT Increasing Factor of Safety Dramatically Reduces Risks FOS FOS is not simply the inverse of probability of failure. Increasing FOS can reduce failure probability by 1,000’s SGP TSF: 1 in 10 million Graphic Source: Oboni & Oboni 2020. The Factor of Safety and Probability of

  38. Slide 38: ModPRO2 Design: Starter Facility Slope Stability

    SGP TAILINGS FACILITY DESIGN ModPRO2 Design Slope Stability Analysis – Starter (Stage 1) Facility • Analyzed hypothetical standalone dam (buttress placement begins before tailings deposition) • Approx. 250’ tall • Exceeds minimum static FOS 1.5 • Water level far below crest during limited unbuttress

  39. Slide 39: ModPRO2 Design: Final Facility Slope Stability

    SGP TAILINGS FACILITY DESIGN ModPRO2 design: Slope Stability Analysis – Final facility FOS= Pool – Standalone Dam, FOS = 1.8 (hypothetical only) FOS= Pool – Buttressed, FOS = 5.9 (actual condition at full buildout) Meets or Exceeds Regulatory Standards Rock Buttress At Least Doubles Req’d FOS (Stati

  40. Slide 40: TSF/Buttress Design Configuration

    TSF/BUTTRESS DESIGN CONFIGURATION ✓ Rockfill with downstream raises to maintain freeboard ✓ Composite-lined ✓ Surface water diverted ✓ Underdrains ✓ Over-liner drainage/pore pressure relief TSF: Tailings Storage Facility 40

  41. Slide 41: TSF/Buttress Expansion Phasing

    TSF/BUTTRESS EXPANSION PHASING Stability and Flexibility in Mine Planning and Water Management • Lined TSF expanded to keep pace with ore processing • Design freeboard at “just-full” end of phase. Much more before that. • Buttress expanded to receive rock from pits; far faster than needed for embank

  42. Slide 42: TSF/Buttress Expansion Phasing

    TSF/BUTTRESS EXPANSION PHASING Stability and Flexibility in Mine Planning and Water Management • Trivial pool (10’s of feet) relative to embankment height • Bulk of embankment shell essentially complete in year 5 to final elevation, with substantial buttress. • Post-Year 5 expansions of TSF related

  43. Slide 43: SGP Tailings Facility Closure

    SGP TAILINGS FACILITY CLOSURE Designed to Become Permanent River and Wetland Habitat ✓ Restore Meadow Creek and wetlands ✓ Allow and accommodate natural processes (migration, avulsion, scour, deposition; including alluvial fans). ✓ Protect water quality via isolation from tailings and active and pas

  44. Slide 44: Stibnite TSF Risk Profile (Pre-Mitigation)

    STIBNITE TSF RISK PROFILE (PRE-MITIGATION) Internal Management Team External Design Team Team Regulatory Environment Review Team Team Continuity Climate Hydrology Site Hydrogeology Foundation Characteristics Characteristics Seismicity Risk Mitigation Measures: Geohazards Topography • Freeboard Const

  45. Slide 45: Tailings Safety

    TAILINGS SAFETY No Known Failures of Facilities With These Design Characteristics STIBNITE GOLD PROJECT TAILINGS STORAGE FACILITY DESIGN CHARACTERISTICS: ✓ Downstream constructed Best Practice For Tailings Facility ✓ Engineered rockfill Design ✓ Full composite liner ✓ Reviewed by an independent expe

  46. Slide 46: SGP Tailings Storage Facility Design

    SGP TAILINGS STORAGE FACILITY DESIGN Designed for Water Quality Protection, Long-Term Stability, and Habitat Restoration ✓ Legacy material reuse and reprocessing ✓ Tailings neutralized and TSF fully lined for water quality protection; water treatment in closure ✓ Substantial rock buttress and robust

  47. Slide 47: Webinars

    WEBINARS www.perpetuaresources.com/connect/virtual-events

  48. Slide 48: Thank You.

    THANK YOU. w w w. p e r p e t u a r e s o u r c e s . c o m 48

Perpetua Resources — Technical Presentation (May 2021) on 6ix