Miller Energy Resources — Shareholder Meeting (April 2014)
23 slides from Miller Energy Resources's shareholder meeting presentation, Apr 16, 2014
Slide 1: Miller Energy Resources Shareholder Meeting – April 2014
Miller Energy Resources Shareholder Meeting – April 2014
Slide 2: Forward Looking Statements
Forward Looking Statements Certain statements in this presentation and elsewhere by Miller Energy Resources¸ Inc. are "forward-looking statements" within the meaning of the Private Securities Litigation Reform Act of 1995. These forward-looking statements involve the implied assessment that the reso
Slide 3: Executive Overview
Executive Overview We believe Fiscal 2015 finds us poised for continued value creation with all the necessary pieces in place – access to favorable financing, promising drilling targets, wellbore diversification, and a favorable Alaskan tax environment 2
Slide 4: Alaska Development Advantages
Alaska Development Advantages Tax Incentives & Commodity Prices No severance tax on oil Oil contracts based on ANS pricing (premium to WTI, similar to Brent) Fixed contract with ENSTAR at $6.00/mcf Winter spot market at up to $22.00/mcf Prices negotiated directly with utilities and end use
Slide 5: Existing Alaskan Operations and Tennessee Operations
Existing Alaskan Operations Tennessee Operations Approximately 3,249 boe/d of production at 12/31/13 Significant development opportunity through 3P Osprey platform designed for 21 wells producing 25,000 boe/d with additional Capacity for 13 wells – transfers oil via sub-sea pipeline to Kustata
Slide 6: Infrastructure Asset Overview
Infrastructure Asset Overview Osprey offshore Platform Kustatan production Facility West McArthur, WF production Facilities North Fork Field pipelines and compression equipment ~65 miles of pipelines Alaska ~380 operated wells ~25 miles of pipelines Tennessee 5
Slide 7: Fiscal 2014 Highlights
Fiscal 2014 Highlights Increased Production – Miller has continued to grow production during Fiscal 2014 ̶ Increases due to optimization, reworks, and new drilling ̶ Production increased 219% from ~1,350 boe/d at 4/30/13 to ~4,300 boe/d at 4/15/20141 ̶ Held production constant in Tennessee while a
Slide 8: Average Daily Production Growth
Average Daily Production Growth Fiscal 2014 Daily Production Growth (boe/d) During Fiscal 2014, Miller Energy worked over, recompleted, or drilled the following wells in Alaska RU-1A: sidetrack RU-2A: sidetrack RU-5B: sidetrack RU-7: re-perforate and work-over RU-9: (in progress) - grassro
Slide 9: Growth in Proved Developed Reserves and PV-10
Growth in Proved Developed Reserves and Proved Developed PV-10 Proved Developed Reserves (mboe) Proved Developed Reserve PV-10 Value ($ millions) 8 1,613 8,384 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 4/30/2013 12/1/2013 $32.8 $365.8 $0.0 $50.0 $100.0 $150.0 $200.0 $250.0 $300.0 $350.
Slide 10: Decreasing Cost of Capital
Decreasing Cost of Capital Current Financing $175MM 4-Year Second-Lien Secured Credit Facility by Apollo Investment Corp and Highbridge Principal Strategies at 11.75%, fully drawn at closing ̶ In process of establishing first lien position at lower rates than current second lien debt Series C 10
Slide 11: Unlocking Adjacent Fault Block Value in Redoubt Field
Unlocking Adjacent Fault Block Value in Redoubt Field Worked-over two gas wells, became gas self sufficient, started gas sales 2013 Six target fault blocks Successfully developed two (2) fault blocks Four (4) fault blocks remain to be exploited by step out drilling Worked-over four oil wel
Slide 12: Unlocking Onshore Value in West McArthur River Unit
Unlocking Onshore Value in West McArthur River Unit Started with WMRU Recently drilled into Sword (adjacent fault block) based on DSTs and 3D seismic data, adding significant proved reserves and production Plan to drill Sabre into fault block adjacent Sword using new rig #36 under option with
Slide 13: Alaska Onshore Activities
Alaska Onshore Activities Sword-1: Drill, tested, and completed well (883 BOED 1 of 3 zones), currently testing two other oil zones WMRU-8: Drilled & completing WMRU-2B: Currently drilling, (sidetracked WMRU-2A) Sabre: Design & engineering, permitting underway, entered into option for rig pu
Slide 14: Sword Log: Upper Tyonek, G-0 and Hemlock Zones
Upper Tyonek – Testing and producing oil, awaiting IP rate G-0 Zone – Testing and producing oil, awaiting IP rate Hemlock Zone – Current rate 600 bopd average Sword Log 13
Slide 15: North Fork Acquisition
North Fork Acquisition 100% working interest in $185 million of Proved and Probable PV-10 ̶ Probable SEC PV-10: $93.1 Million ̶ Total Proved SEC PV-10: $92.3 Million Includes six (6) natural gas wells, production and processing equipment and 15,464 acres Multi-year firm natural gas sales contr
Slide 16: Trans-Foreland Pipeline
Trans-Foreland Pipeline Pioneers of concept, new crude oil pipeline linking west side to east side Partnered with Tesoro pipeline group to fund feasibility, design and engineering Over the last two years our companies have worked together to advance the permitting and engineering of the projec
Slide 17: New Rig-36
New Rig-36 Recent Land-base Rig Purchase Entered into option to purchase rig for $3.25MM, including deposit ~2400-HP, ~25,000’ drilling capabilities Planned rig improvements needed for Sabre prospect ie. high PSI mud system, pits, etc. Plan to drill Sabre from WMRU pad Up to 6 wells needed
Slide 18: Tennessee Operations
Tennessee Operations Control approximately 47,000 Gross Acres Operates ~ 190 Oil and 190 Gas wells On-going purchase of WI in wells to further production Re-working older wells to enhance production Drilled the first Horizontal well in the Mississippian Lime targeting oil in Tennessee To
Slide 19: Summary
Summary Increased shareholder value in FY 2014 by reworking, sidetracking and drilling new wells ̶ North Fork acquisition ̶ Refinanced debt at lower cost ̶ Continuing to add shareholder value with continued offshore and onshore development activity Planning for the Future – Miller continues to l
Slide 20: Appendix
Appendix 19
Slide 21: Corporate Organization Chart
Miller Energy Resources, Inc. Corporate Organization Chart Board Of Directors Operations Legal Finance and Accounting Scott Boruff CEO Deloy Miller Founder and Exec. Chairman EVP – TN Ops David Hall COO Kurt Yost SVP, General Counsel Assist. General Counsel Assoc. General Counsel Corporate Controlle
Slide 22: Alaska Organization Chart
2009 2010 2011 2012 Alaska Operations David Hall COO & CIE CEO Drilling Manager (Cont) Drilling Foremen Drilling Engineer Senior Land Man Jr. Land Man Exploration Manager Senior Geologist Resv. Eng. (cont) Geophysics (Cont) Petroleum Tech CPA, Tax spec.(Cont) Production Manager Production Foremen Pr
Slide 23: Tennessee Organization Chart
Pre-2008 2008 2009 2010 2011 2012 2013 Tennessee Operations David Wright EVP Tennessee Operations Shop Hand Rig Hand Rig Hand VP of Geology Data Specialist Geologist and Completion Engineer Drilling Superintendent & Completion Manager Equipment Operator/Driver Rig Hand Ser. Rig Operator Ser. Rig Ope
Miller Energy Resources — Shareholder Meeting (April 2014) on 6ix