  1. Slide 1: Saint John's Solar Farm

    Saint John’s Solar Farm Renewable Development Fund Project: EP3-3 5/11/10

  2. Slide 2: Project Objectives

    Project Objectives • Familiarize Minnesotans with solar PV and educated the public on Minnesota’s excellent solar resource. • Provide a full-scale demonstration of utility solar power in Minnesota. • Create a foundation of project management experience and knowledge regarding installations of this s

  3. Slide 3: Government Approvals

    Government Approvals • Landuse Approvals/Permits: • Zoning Code text change (to allow solar): Stearns County • Rezoning to District that allowed solar: Stearns County • Conditional Use Permit: Avon Township • Site Permit: Stearns County • NPDES (Stormwater): State of Minnesota • State Building Permi

  4. Slide 4: Site Selection

    Site Selection Best Psswer Int'l, LLC

  5. Slide 5: Site Plan

    Site Plan Best Ps‘swer Int'l, LLC

  6. Slide 6: Installation – Foundation

    Installation – Foundation • Driven Pole Foundation • No concrete • Cost reduction • Minimal Site Disturbance

  7. Slide 7: Installation – Wire & Trench

    Installation — Wire & Trench Best Ps‘swer Int'l, LLC

  8. Slide 8: Installation – Tracker Frame & Motor

    Installation – Tracker Frame & Motor • Two 1.5 HP motors

  9. Slide 9: Installation – Modules

    Installation - Modules • 1820 Modules • 4 Containers

  10. Slide 10: Installation – Commissioning

    Installation – Comissioning • Calibrate Systems • Baseline System Performance • Anti-Island Verification • Meter Installation

  11. Slide 11: Project Timeline (2009)

    Project Timeline (2009) 1. Sign Agreement w/ Host May 2. Design June 3. Zoning/Permitting June-August 4. Equipment Procurement Aug-Sept 5. Site Work September 6. Foundations Sept-Oct 7. Tracker Assembly October 8. Module Installation November 9. Commissioning December

  12. Slide 12: Project Objectives – Results

    Project Objectives – Results • Familiarize Minnesotans with solar PV and educated the public on Minnesota’s excellent solar resource: Site Tours (Over 500 visitors to date) Media Coverage (Print & Television Coverage) Award (MRES Commercial Project of the Year) Educational Seminars Live Project Webs

  13. Slide 13: Live Website

    Live - Website System Size: 400.4 kW DC © Saint John's Solar Farm: Solar «v#se= sss Data Updated: May 6, 2010 9:15am HOW SOLAR WORKS. PROJECT DETAILS | | generation (kWh) Raitt, ty S 2 cu RENT SOLAR G :NERATION A x GENERATED kwh, i TO DATE | Mite Today 3Day Week Monts Year CURRENT WEATHER | Total En

  14. Slide 14: Project Objectives – Results Cont

    Project Objectives – Results Cont • Create a foundation of project management experience and knowledge regarding installations of this size. Contractors, Electricians, Metal Works etc. Engineers, (Electrical, Structural and Civil) Program Managers & Integrators • Generate renewable energy during pea