  1. Slide 1: Building an African Gold Mining Powerhouse

    ASX: CHN • Development targeted for 2011 • 104,000 oz per year producer • Huge exploration upside Building an African Gold Mining Powerhouse BGF Equities‐ Gold Investor Road Show August 2010 www.chalicegold.com

  2. Slide 2: Disclaimer & Competent Person's Statement

    Disclaimer & Competent Person’s Statement • This presentation may contain value references and "forward looking statements“ which are subject to various risks and uncertainties that could cause actual results and future events to differ materially from those expressed or implied by such statements I

  3. Slide 3: Chalice Snapshot

    Chalice Snapshot • Creating shareholder wealth through exploration and production: • Focused on East Africa, Listed on ASX (CHN), Listing on TSX (September 2010) • 100% owned Zara Gold Project, Eritrea (subject to gov’t project participation rights): • High‐grade Ore Reserves of 760,000oz @ 5.1g/t:

  4. Slide 4: Corporate Snapshot

    Corporate Snapshot Capital Structure (post 1 for 6 rights issue) • Shares on issue 181M (211M) • Options on Issue 13.075M • Cash (est. August 10) A$5M (~A$17M) Board • Tim Goyder (Executive Chairman) 6 month h share h price i • Dr Doug Jones (Managing Director) • Mike Griffiths (Executive Director)

  5. Slide 5: Zara – Project Location

    Zara — Project Location chalice Gotp MINES 250,000 mE 1,760,000 mj / {| / Bisha yeAgordat 500,000 mE «| Asmara @~ (atcsney ERITREA YS \ Ethiopia Granted Chalice Tenement ta _ 0 25 50 750,000 mE kilometres | Chalice Application [| London Africa Prospecting Licences (CHN 20% interest) Zc Saudi Arabia

  6. Slide 6: Koka – Outstanding Returns, Outstanding Potential

    Koka – Outstanding Returns, Outstanding Potential • Positive Feasibility Study completed • US$122M development of open pit mining operation and treatment plant • ~700,000tpa ~700 000t ore processing i tot produce d 104,000oz pa • Forecast cash operating cost US$338/oz • NPV of US$196M and 35% IRR at

  7. Slide 7: Koka Project – Key Financial Outcomes

    Koka Project – Key Financial Outcomes 100% Project Financial Outcomes* Gold Price (Unleveraged) $900 $1,200 $1,500 Life‐of‐mine EBITDA $381M $589M $797M Average annual EBITDA $54M $84M $114M NPV5% after‐tax cash flows $99M $196M $293M IRR after tax 22% 35% 45% Payback period (years) 28 2.8 21 2.1 18

  8. Slide 8: Koka Gold Deposit

    Koka Gold Deposit • Quartz stockwork system in microgranite • JORC‐compliant Indicated Resource of 5.0Mt @ 5.3 g/t Au for 840,000oz gold • P b bl reserve – 4.6Mt Probable 4 6Mt @ 5 5.1g/t 1 /t • Based on results from 137 diamond drill holes ((~21 21,000m 000m drilled) • ~600m strike length, 20‐30m w

  9. Slide 9: Koka Gold Deposit – 3D Pit Image

    Koka Gold Deposit – 3D Pit Image 9

  10. Slide 10: Koka Gold Deposit – Cross Section

    Koka Gold Deposit – Cross Section Stage 1 pit design – pd4tr Whittle shell 3 Whittle shell 18 Final pit design – pd1tr 10

  11. Slide 11: Koka Gold Mine – Plant Layout

    Koka Gold Mine – Plant Layout Crushed-oreStockpile Primary Crusher Maintenance SAG Mill Gensets CIL Tankage CCD Circuit Stores Gold Room Water Storage Mine Office 11

  12. Slide 12: Koka Gold Mine – Site Layout

    Koka Gold Mine – Site Layout 1.5 km Plant Dump A Plant Dump B Dump C 12

  13. Slide 13: Exploration – The Bigger Picture

    Exploration – The Bigger Picture • Zara Project located within Arabian‐ Nubian Shield – an emerging gold & base metal province • Gold endowment +20Moz – numerous deposits and mines dating back to ancient times • Minimal modern exploration • New world‐class p projects j beingg developed: • 13Moz Suka

  14. Slide 14: Chalice – Huge Exploration Upside

    Chalice – Huge Exploration Upside • Chalice controls ~20,000 sq km of highly prospective tenements & applications in Eritrea • Recent exploration p has identified several zones of extensive mineralisation in addition to the existing Koka resource • Intensive exploration underway within highly prospe

  15. Slide 15: Koka-Konate 'Corridor'

    Koka‐Konate ‘Corridor’ • Multiple structures with alteration and artisanal workings: • Konate – artisanal workings on Koka South quartz stockwork – drilling in progress • Fah – extensive quartz stockwork within 4 km x 0.8 km alteration zone – drilling planned • Koka South – narrow, high‐grade Konate

  16. Slide 16: Konate

    Konate • Zone of intensive artisanal workings 5km south h off Koka: K k • ~600m by up to 20m wide • quartz vein stockwork k k in silica‐sericite l altered l d microgranite • Diamond drilling underway • Guided by structural analysis of vein arrays • Significant quartz veining with sulphides intersect

  17. Slide 17: Koka South

    Koka South • Strong IP resistivity anomaly id tifi d 200‐500m identified 200 500 south th off Koka K k • Ground follow‐up confirmed zone of silica‐sericite altered KOKA microgranite • Potential ‘blind’ system plunging 24/2 8.9/1 gently to south 2.2/1 91/1 92/1 23.7/3 30.7/2 • Drilling confirmed Koka

  18. Slide 18: Regional Geochemical Sampling

    Regional Geochemical Sampling • Systematic geochemical drainage sampling works well in this terrane • Initial BLEG (Bulk Leach Extractable Gold) and multi‐element analyses results reveal numerous high‐order anomalies on Zara and Zara North properties p p • Results >5ppb normally considered anomalous

  19. Slide 19: Eritrea Overview

    Eritrea Overview • Stable bl operating i and d social i l environment • Proactive P ti G Governmentt stance t on mining developments – “open for business” • Modern Mining Code • Increasing foreign exploration & mining investment – 20 groups now active in country • Growing interest from ‘majors’ 19

  20. Slide 20: Summary

    Summary • Koka Gold Deposit: • Advanced high grade gold deposit • Strong g economics • Low technical risk • Feasibility Study completed • Aggressive exploration programs underway to expand resource base • Strategic ground position in emerging gold & base metall province i • Experienced Board and Man

  21. Slide 21: Building an African Gold Mining Powerhouse

    ASX: CHN • Development targeted for 2011 • 104,000 oz per year producer • Huge exploration upside Building an African Gold Mining Powerhouse BGF Equities‐ Gold Investor Road Show August 2010 www.chalicegold.com

  22. Slide 22: Eritrea Mining Act

    Eritrea Mining Act Prospecting licence Royalties • One year, not renewable,not transferrable • Up to 5% for precious metals and 3.5% for other • Maximum size 100km2 metallic t lli minerals i l • Licence fee (US)$33.33 • Annual rental (US)$3.33/km2 Government Participation • 10% free-carried interest