Slide 3: Interim Highlights
Interim Highlights FINANCIAL HIGHLIGHTS • Group mine revenue: US$90 US$90.0m 0m (H1 FY 2010: US$48 US$48.4m) 4m) • Profit from mining activity: US$24.5m (H1 FY 2010: US$8.0m) • Operating cashflow: US$11.9m (H1 FY 2010: US$4.8 million outflow) • G Group EBITDA US$20.2m EBITDA: US$20 2 (FY 2010 2010:
Slide 4: Interims Highlights Cont.
Interims Highlights Cont. CORPORATE HIGHLIGHTS • ca. US$83m debt facilities in place with IFC and RMB ca • Repayment of Al Rajhi loan (US$30.7m) and accrued interest • Effective interest in Koffiefontein mine increased from 70% to 74% • BEE partner t iintroduced t d d att Helam H l mine; i allll SA
Slide 5: Summary Results – Key Numbers
Summary Results – Key Numbers 6 months to 6 months to 12 months to 31 Dec 10 31 Dec 09 30 Jun 10 (US$m) (US$m) (US$m) R Revenue* * 90 0 90.0 48 4 48.4 163 7 163.7 Mining & processing costs (66.8) (40.5) (98.9) Profit from mining activity* 24.5 8.0 67.2 Other operating income - 6.7 5.4 Exploration ex
Slide 6: Balance Sheet Snapshot
Balance Sheet Snapshot 31 Dec 2010 31 Dec 2009 (US$m) (US$m) Cash and cash equivalents: Bank 20.8 65.0 Diamond inventories 20.2 34.8 Total¹ 41.0 99.8 Loans, borrowings and deferred consideration: IFC / RMB Debt Facilities (ca. US$83m in total) 54.1 (gross) n/a Al Rajhi loan n/a 50.7 Deferred Cullina
Slide 7: Diamond Market Performance - 2010
Diamond Market Performance - 2010 • Diamond market rebounded fully from Breakdown of global diamond downturn & prices continued to strengthen consumer demand in 2010 throughout g yyear • Continued rising trend witnessed in Petra’s February 2011 tender (prices up 6 – 8%) • Market underpinned by retai
Slide 8: Mine Revenue / Volume Split
Mine Revenue / Volume Split Diamonds Sold Gross Revenue 584,234 carats US$90 million 7% 9% 1% 2% 3% 6% 6% Cullinan Koffiefontein Kimberley Williamson Fissures 64% 19% 83% 8
Slide 9: Cullinan (South Africa)
Cullinan (South Africa) Ownership 74% Petra; 26% Unit 6 months ended 31 6 months ended 31 BEE December 2010 December 2009 Sales Revenue US$M 57.8 40.2 Diamonds sold Carats 481,049 461,365 Average price per carat US$ 120 87 Total Production (ROM & Tailings) • Source of world’s Tonnes treated Tonnes 1
Slide 10: Koffiefontein (South Africa)
Koffiefontein (South Africa) Ownership: 74% effective Unit 6 months ended 31 6 months ended 31 interest; 26% BEE December 2010 December 2009 Sales Revenue US$M 17.2 9.4 Diamonds sold Carats 36,669 28,008 Average price per carat US$ 470 337 Total Production (ROM & Tailings) Tonnes treated Tonnes 802
Slide 11: Kimberley Underground (South Africa)
Kimberley Underground (South Africa) Ownership 74% Petra; 26% Unit 6 months ended 31 6 months ended 31 BEE December 2010 December 2009 Sales Revenue US$M 4.9 n/a Diamonds sold Carats 17,271 n/a Average price per carat US$ $ 285 n/a Total Production (all ROM) Tonnes treated Tonnes 176,527 n/a • Poten
Slide 12: Williamson (Tanzania)
Williamson (Tanzania) Ownership 75% Petra; 25% Unit 6 months ended 31 6 months ended 31 Government of United December 2010 December 2009 Republic of Tanzania Sales S l Revenue US$M 2.0 6.9 Diamonds sold Carats 7,722 48,883 Average g pprice p per carat US$ $ 264 141 Total Production (Alluvial only) T
Slide 13: Finsch – A New Flagship Asset
Finsch – A New Flagship Asset • South Africa’s second largest diamond mine by production • State-of-the-art infrastructure & modern plant • (Shaft 4.6 Mtpa; Plant 7.2 Mtpa) • Resource of 48 Mcts, incl. 26.6 Mcts reserves & 4.7 Mcts tailings • Av. p production of ca. 2 Mcts p pa over last 5 yyrs • Pe
Slide 14: Petra Diamonds – An Exceptional Growth Profile
Petra Diamonds – An Exceptional Growth Profile 6 800 700 5 600 4 500 Expected Gross Expected Carats 3 400 Revenue (Millions) (US$ m) 300 2 200 1 100 0 - FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 (Actual) Cullinan Koffiefontein Kimberley U/G Williamson Fissures F
Slide 15: Balanced Production & Revenue
Balanced Production & Revenue Gross Production FY 2012 (1)(2) Gross Revenue FY 2012 (1)(2) 3.1 Million Carats US$444 million $105 1.0 Cullinan Williamson $178 Koffiefontein 1.5 Kimberley $40 Fissure Mines 0.2 Finsch $36 0.1 0.2 $30 $55 0.1 Mcts US$m Gross Production FY 2019 (1) Gross Revenue FY 2019
Slide 16: Appendices
\Y PetraDiamonds Appendices
Slide 17: Capital Structure
Capital Structure High Quality Shareholder Base 18 Feb 11 Share Price Chart Al Rajhi Holdings W.W.L. 13.4% Saad Investments Company Ltd/AWAL Bank 12.3% JP Morgan Asset Management (UK) Ltd 8.7% Capital p Group p International,, Inc. 7.4% Scottish Widows Investment Partnership 5.6% BlackRock Investmen
Slide 18: Exposure To Strong Diamond Market
Exposure To Strong Diamond Market • Diamond supply constraints - world’s largest diamond mines are past their peak • Only around 30 diamond mines of significance globally • Significant supply / demand deficit expected to emerge in 3 years • Strong demand growth continues from China & India – urbanis
Slide 19: The Petra Board
The Petra Board Adonis Pouroulis Johan Dippenaar David Abery Jim Davidson Chairman CEO Finance Director Technical Director S Successful f l mining i i entrepreneur t One off South O S th Africa’s Af i ’ mostt Extensive E t i experience i as Chi Chieff Acknowledged A k l d d worldld authority th it s
Slide 20: A Diversified Production Portfolio
A Diversified Production Portfolio Limpopo Helam Cullinan Mpumalanga Williamson NorthWest Province Johannesburg Gauteng KwaZulu Sedibeng Star Natal Finsch FreeState Kimberley NorthernCape Koffiefontein Production Durban SouthAfrica South Africa • Cullinan EasternCape • Koffiefontein • Kimberley Unde
Slide 21: Building A Leading Diamond Producer
Building A Leading Diamond Producer Q4 FY2011 July 2007 July 2008 November 2008 May 2010 (Pending) Koffiefontein Cullinan Williamson KimberleyUG Finsch 74% Petra 74% Petra 75% Petra 74% Petra 74% Petra 26% Re-Teng 14% Thembinkosi / 25% Government of 26% Sedibeng Mining 26% BEE Partners Diamonds 12%
Slide 22: Group Gross Resources
Group Gross Resources G Gross C Caratt B Base G Gross I it Value In-situ V l 309.1 Mcts US$38.0 billion 48.1 $5.7 4.6 $0.7 7.5 Cullinan $1.4 5.7 57 Williamson Koffiefontein $2.2 Mcts Kimberley US$bn 40.0 $20.8 Fissures Finsch 203.3 $7.2 22
Slide 23: Growth Profile – Historic
Growth Profile – Historic million Gross Production Gross Revenue Recovery in carats Major US$ million rough diamond increase due prices & sale of 1.4 to higher volume 200 Cullinan H it Heritage Cullinan mine 180 1.2 Acquisitions 160 of Cullinan and Willi Williamson 1.0 140 120 0.8 Acquisition of 100
Slide 24: Key Economics
Key Economics Finsch Cullinan Williamson Koffiefontein Kimberley U/G Current production rate (Mtpa) 3.2 2.3 2.1 0.9 0.6 35 3.5 40 4.0 10 0 10.0 12 1.2 10 1.0 Expansion tonnes (Mtpa) (FY2018) (FY2019) (FY2014) (FY2017) (FY2012) ROM US$ / carat (1) 135 105 200 480 250 ( ht) (1) G d (cpht) Grade 47 0 4
Slide 25: Petra Expansion Profile (incl. Finsch)
Petra Expansion Profile (incl. Finsch) Financial Year 2011 2012 2013 2014 2015 2016 2017 2018 2019 Operation Area Finsch Existing Block 4 (630 meter Level) - Block 4 pillars - SLC Block 4 precursor - SLC S C 770 meter Level - Block 5 880 meter Level Development tonnes ROM Tonnes (Mt) 0.8 3.2 3.2 3.2
Slide 26: Block Caving – Aim Of Expansion Programmes
Block Caving – Aim Of Expansion Programmes VIRGIN KIMBERLITE PIPE DRAWPOINTS UNDILUTED ORE UNDERCUT LEVEL PRODUCTION LEVEL LOADERS HAULAGE 26
Slide 27: Cullinan Orebody
Cullinan Orebody CurrentInfrastructure CurrentShaftBottom 580Level PlannedInfrastructure BA5 AUCSouthand 630mLevel BAWPhase1 BB1E CCUT 732mLevel Phase2 830m Level 830mLevel 763mLoadingLevel 950mShaftBottom KimberliteFootprint Kimberlite Footprint CCUT 16Ha@830Level CurrentextentofSouthDecline 1073mB
Slide 28: Koffiefontein Orebody
Koffiefontein Orebody Current Infrastructure Planned Infrastructure West Cave 52b Recovery New Front Cave New Block Cave dd ? PetraDiamonds 490m Level 520m Level 690m Level
Slide 29: Kimberley Underground Orebodies
Kimberley Underground Orebodies 29
Slide 30: Williamson Orebody
Williamson Orebody Y PetraDiamonds 3 year pit shell Ramp Current Pit Bottom Final Pit Bottom (205m)
Slide 31: Finsch Orebody
Finsch Orebody Footprintat800mLevel Mainpipe:4.4ha Precursor:1.6ha 31